Building and Construction in UK Law

In this Topic
Leading Cases
  • East Ham Corporation v Bernard Sunley & Sons Ltd
    • House of Lords
    • 27 Octubre 1965
    “

    Dealing with this subject, the learned editors of Hudson's Building and Engineering Contracts, 8th edition, say at page 319 that there are in fact three possible bases of assessing damages, namely, ( a) the cost of reinstatement; ( b) the difference in cost to the builder of the actual work done and work specified, or ( c) the diminution in value of the work due to the breach of contract.

  • Gilbert Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd
    • House of Lords
    • 25 Julio 1973
    “

    But in construing such a contract one starts with the presumption that neither party intends to abandon any remedies for its breach arising by operation of law, and clear express words must be used in order to rebut this presumption.

  • Applegate v Moss
    • Court of Appeal (Civil Division)
    • 11 Diciembre 1970
    “

    It is used in the equitable sense to denote conduct by the defendant or his Agent such that it would be "against conscience" for him to avail himself of the lapse of time. The section applies whenever the conduct of the defendant or his agent has been such as to hide from the plaintiff the existence of his right of action, in such circumstances that it would be inequitable to allow the defendant to rely on the lapde of time as a bar to the claim.

  • Beaufort Developments (NI) Ltd v Gilbert Ash (NI) Ltd
    • House of Lords
    • 20 Mayo 1998
    “

    If one considers the practicalities of the construction of a building or other works, it seems to me that parties could reasonably have intended that they should have what might be called a provisional validity. Construction contracts may involve substantial work and expenditure over a lengthy period. It is important to have machinery by which the rights and duties of the parties at any given moment can be at least provisionally determined with some precision.

  • Sage v Secretary of State for the Environment, Transport and the Regions and another
    • House of Lords
    • 10 Abril 2003
    “

    When an application for planning consent is made for permission for a single operation, it is made in respect of the whole of the building operation. As counsel for Mr Sage accepted, if a building operation is not carried out, both externally and internally, fully in accordance with the permission, the whole operation is unlawful. She contrasted that with a case where the building has been completed but is then altered or improved.

  • Holding and Management Ltd v Property Holding and Investment Trust Plc
    • Court of Appeal (Civil Division)
    • 27 Julio 1989
    “

    Accordingly, the circumstances to be taken into account in a particular case under one or other of these heads will include some or all of the following: the nature of the building, the terms of the lease, the state of the building at the date of the lease, the nature and extent of the defect sought to be remedied, the nature, extent, and cost of the proposed remedial works, at whose expense the proposed remedial works are to be done, the value of the building and its expected lifespan, the effect of the works on such value and lifespan, current building practice, the likelihood of a recurrence if one remedy rather than another is adopted, the comparative cost of alternative remedial works and their impact on the use and enjoyment of the building by the occupants.

  • Dawnays Ltd v F. G. Minter Ltd and Trollope and Colls Ltd
    • Court of Appeal (Civil Division)
    • 28 Abril 1971
    “

    It is so that the sub-contractor can have the money in hand to get on with his work and the further work he has to do. An interim certificate is to be regarded virtually as cash, like a bill of exchange. Payment must not be withheld on account of cross-claims, whether good or bad - except so far as the contract specifically provides. Otherwise any main contractor could always get out of payment by making all sorts of unfounded cross-claims.

See all results
Legislation
See all results
Books & Journal Articles
See all results
Forms
  • Additional draft case management directions
    • HM Courts & Tribunals Service court and tribunal forms
    Chancery forms, including claim forms and applications for orders.
    ... ... ()  The  claim be transferred to the Technology and Construction Court [ or other Specialist List ] ... script at Chancery Chambers, Case Management Section, The Rolls Building, 7 Rolls Buildings, Fetter Lane, London EC4A 1NL  [        ... ...
See all results