Amey LG Ltd v Cumbria County Council
Jurisdiction | England & Wales |
Judge | His Honour Judge Stephen Davies |
Judgment Date | 11 November 2016 |
Neutral Citation | [2016] EWHC 2856 (TCC) |
Docket Number | Case No: 3MA500110 |
Court | Queen's Bench Division (Technology and Construction Court) |
Date | 11 November 2016 |
His Honour Judge Stephen Davies
Sitting as a Judge of the High Court
Case No: 3MA500110
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
MANCHESTER DISTRICT REGISTRY
TECHONOLOGY AND CONSTRUCTION COURT
Manchester Civil Justice Centre,
1 Bridge Street West, Manchester M60 9DJ
David Streatfeild-James QC, Andrew Singer & Jonathan Ward (instructed by Pinsent Masons LLP, Solicitors, Leeds) for the Claimant
Martin Bowdery, QC, Paul Stafford, Frances Pigott, Lauren Adams (instructed by REN Legal, Solicitors, London EC2) for the Defendant
Hearing dates: 8, 9, 10, 15, 16, 17, 18, 22, 23, 24, 25, 29 February; 1, 2, 3, 7, 8, 9, 10, 14, 15, 16, 17 March; 4, 5, 6, 7, 13, 14, 18, 19, 20, 21 April; 3, 4, 5, 9, 11, 12, 25, 26, 27 May 2016; 27, 28 October; 10 November 2016 (draft judgments circulated 6 September 2016 and 3 November 2016)
JUDGMENT APPROVED
No. | Section | Para. refs. |
General: | ||
1 | Introduction and preliminary matters | 1.1 – 1.54 |
2 | The contract | 2.1 – 2.66 |
3 | The witnesses | 3.1 – 3.89 |
4 | Sources of documents and disclosure issues | 4.1 – 4.57 |
5 | Local area overhead | 5.1 – 5.19 |
6 | Chronology of relevant events | 6.1 – 6.61 |
Amey's claims: | ||
7 | Amey's part 1 claim | 7.1 – 7.30 |
8 | Item (j) – Lillyhall depot works | 8.1 – 8.20 |
9 | Item 1: Sellafield de-trunking (winter) | 9.1 – 9.16 |
10 | Item 2: other de-trunking (scouting / winter) | 10.1 – 10.13 |
11 | Item 3: red diesel – road marking vehicles | 11.1 – 11.19 |
12 | Item 4: red diesel – MEWPS | 12.1 – 12.9 |
13 | Item 6: landfill tax | 13.1 – 13.25 |
14 | Item 8: increased employer national insurance contributions | 14.1 – 14.11 |
15 | Item 12: Better Highways rate | 15.1 – 15.92 |
16 | Item 13: Better Highways trial support | 16.1 – 16.18 |
17 | Item 14: Better Highways impact cost | 17.1 – 17.34 |
18 | Item 17: patching thickness | 18.1 – 18.34 |
19 | Item 19: uplift for works carried out in specified periods | 19.1 – 19.17 |
20 | Item 20: timebound works | 20.1 – 20.14 |
21 | Item 23: efficiency savings on volumes of works | 21.1 – 21.26 |
22 | Item 24: account production costs | 22.1 – 22.10 |
Cumbria's counterclaims: | ||
23 | Schedule 1: winter services | 23.1 – 23.3 |
24 | Schedule 2: patching and patch testing: introduction | 24.1 – 24.6 |
25 | (1) Visual defects | 25.1 – 25.189 |
26 | (2) Work not done | 26.1 – 26.49 |
27 | (3) Incorrect materials | 27.1 – 27.15 |
28 | (4) Patch testing | 28.1 – 28.11 |
29 | Schedule 2: surfacing and surface testing: introduction | 29.1 – 29.8 |
30 | (1) Visual defects | 30.1 – 30.63 |
31 | (2) Thickness | 31.1 – 31.11 |
32 | (3) Surface testing | 32.1 – 32.26 |
33 | Schedule 5: street lighting overcharging | 33.1 – 33.18 |
34 | Schedule 7: notified defects outstanding | 34.1 – 34.66 |
35 | Schedule 8: waste material | 35.1 – 35.17 |
36 | Schedule 13: subcontractor uplifts | 36.1 – 36.13 |
37 | Balance due and Interest | 37.1 – 37.3 |
38 | Glossary | 38.1 |
Introduction and preliminary matters
I will begin this judgment by way of a general introduction, and then proceed to address some preliminary matters, including the approach I have adopted in deciding some of the claims in this case, a consideration of the reliance placed by Cumbria on extrapolation, and an overview of the technical issues involved.
(a) General introduction
This is a claim and counterclaim arising out of a contract under which the claimant, Amey, agreed to provide highways maintenance and associated services for the defendant, Cumbria, for a term of 7 years starting 1 April 2005. The services had previously been provided by Cumbria's direct labour organisation (DLO), which was effectively taken over by Amey. Over the duration of the contract around 36,000 individual works instructions were issued by Cumbria, with an approximate processed value of £250 million. This included the laying of around 2,200 surfacing beds, with a combined area of around 4.2 million m 2 and a total value of around £41 million, and the issuing of around 1,700 separate patching instructions, with a combined area of around 745,000 m 2.
Before outsourcing its DLO Cumbria had already outsourced its highways department, responsible for overseeing the highways maintenance services, to the professional services company, Capita, who was to act as overseeing organisation under the contract. The intention was that all 3 organisations would work in partnership for the benefit of Cumbria's road users.
Although there were, as might be expected, some difficulties along the way, the overall impression is one of reasonable satisfaction on all sides for the first few years of the contract. However in 2008 Cumbria decided to conduct a root and branch review of its highways maintenance services prompted, it appears, by a perception of widespread dissatisfaction with the state of Cumbria's roads, coupled with budgetary pressure to make financial savings. The review process involved the use of external management consultants and had the enthusiastic support of new senior management within Cumbria's highways section. It culminated in a decision to bring Capita's services back in-house once its contract expired at the end of January 2011, and a decision to do the same with Amey's services once its contract expired at the end of March 2012. This decision was taken despite Cumbria being aware that Capita and Amey were very keen to obtain extensions to, or renewals of, their contracts and, in Amey's case, was prepared to offer significant price reductions to secure a contract extension. Cumbria also decided, at around the same, time to trial and then to roll out a new model for undertaking basic road maintenance and repairs, known originally as Customer Care and subsequently as Better Highways. The decision was taken not to await the expiry of the Capita contract and the Amey contract before introducing this new model.
From 2009 onwards the relationship between Amey and Cumbria had steadily deteriorated, so that by the time the contract expired a number of claims and counterclaims had already been intimated, with Cumbria making substantial deductions from Amey's final monthly payment applications, and with both parties actively preparing to pursue claims against the other under the final account process. Neither the final account process nor the subsequent pre-action protocol process resulted in an overall settlement of the claims and counterclaims, with the result that Amey commenced proceedings in the Manchester Technology and Construction Court in December 2013. The claim as pleaded amounted to over £30 million together with interest. The counterclaim, even after taking into account Cumbria's valuation of Amey's claims, was around £20 million. The parties have endeavoured to settle their disputes throughout the course of the proceedings, including undertaking a week-long mediation in May 2014, and have achieved some success, but the majority of the claims and counterclaims remain in dispute.
At the first substantive case management conference the case was listed for a 16-week trial commencing early 2016 and, despite a number of difficulties and disputes along the way the parties have worked hard and co-operated to ensure that the trial date was maintained. The parties sensibly agreed that the trial should be a paperless trial, in circumstances where otherwise the parties and the court would have been overwhelmed by the sheer volume of documentation in paper and electronic format generated during the course of the contract and the dispute.
Although there is considerable strength of feeling within both parties in relation to what each considers to be the discreditable conduct of the others in certain regards, and although the case has been vigorously contested on both sides, I should record my gratitude at the outset to those advising and representing the parties for co-operating with a view to ensuring that, despite the challenges involved, the litigation process ran reasonably smoothly and the trial was able to be completed within the time allocated.
The trial proper began on 8 February 2016 and took 42 days of court time, the first 3 being taken up with oral opening submissions and contested applications, the next 24 with factual evidence, followed by a short break and then 12 days of expert evidence, with a further short break for written closing submissions and concluding with 3 days of oral closing submissions, ending on 27 May 2016. I also had the benefit in the first week of a site visit day, where I was taken to a number of different roads within Cumbria and shown various features of relevance to the issues in this case.
It was recognised by me and by the parties that my judgment produced after this stage could not conclusively determine all of the issues, particularly the final ascertainment of some of the figures, and that certain further working out by the parties, assisted by their quantum experts, would be necessary once I had determined the substantive issues in dispute. Following circulation of this judgment in draft on 6 September 2016 it was agreed that the parties should have time to consider it and to seek to agree or address the outstanding matters, and a further 2 day hearing was scheduled for 27 – 28 October 2016 to determine any outstanding matters which could not be agreed. Prior to that hearing the quantum experts held further discussions and produced a further joint statement. The parties also produced a very helpful combined list of typographical errors. Cumbria also produced a document running to 36 pages,...
To continue reading
Request your trial-
Zagora Management Ltd & Others v Zurich Insurance Plc
...to what both parties hoped would be a satisfactory conclusion. The litigation between Zagora and LHM was transferred to the Manchester TCC (“the TCC action”) where it proceeded to a trial before HHJ Raynor QC. Separately, a further action was brought in the Manchester Chancery Division (“th......
-
Building Design Partnership Ltd v Standard Life Assurance Ltd
...The first is the decision of HHJ Stephen Davies, sitting as a judge of the High Court, in Amey LG Ltd v Cumbria County Council [2016] EWHC 2856 (TCC). In that case, one element of Cumbria's counterclaim concerned claims for patching and surfacing roads which were supposed to be maintained b......
-
Standard Life Assurance Ltd v Gleeds (UK) (A Firm)
...was not.” 84 All four counsel referred me with alacrity to HHJ Stephen Davies' decision in Amey LG Ltd. v. Cumbria County Council [2016] EWHC 2856 (TCC) and the useful discussion in it of extrapolation cases. The claim involved about 36,000 allegedly defective road surfacing works under a l......
-
Blackpool Borough Council v Volkerfitzpatrick Ltd
...the date of practical completion. I was referred to my own consideration of this topic in my judgment in Amey v Cumbria County Council [2016] EWHC 2856 (TCC) where I said at [25.184] that: “In my view the more appropriate way to address this issue is that if Cumbria accepts, as it does in i......
-
Independent Experts: Lessons From The Courts
...Group Plc – per Mr Justice Coulson. 13. [2017] EWCA Civ 63. 14. [2017] EWCA Civ 63. 15. See paragraph 13.3.1 of the TCC Guide. 16. [2016] EWHC 2856 (TCC). 17. [2017] EWHC 29 (TCC). 18. [2015] EWHC 3074 (TCC). Please click here to view previous issues of The content of this article is intend......
-
Proof By Sampling In Construction Disputes
...Ltd [2021] EWCA Civ 1793, Cable v Liverpool Victoria Insurance Co Ltd [2020] EWCA Civ 1015, Amey LG v Cumbria County Council [2016] EWHC 2856 (TCC) and Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2017] EWHC 1763 (TCC) 2. Technology and Construction Court Guide (2nd edit......
-
Probability and non-probability sampling: innovative tools of truncating evidence in complex construction disputes
...in construction disputes. But, what about non-probability sampling? The TCC judgment of Amey LG Limited v. Cumbria County Council [2016] EWHC 2856 (TCC) considered and accepted the proposition that disputing parties may, by way of non-probability sampling, prove the liability and quantum of......
-
Intellectual property
...116 Such 108 See, eg, the FIDIC Red Book (2nd edition, 2017) clause 15.2.3(b). 109 See, eg, Amey LG Ltd v Cumbria County Council [2016] EWHC 2856 (TCC) at [4.12]–[4.23], per HHJ Stephen Davies. 110 Hughes v Lenny (1839) 5 M&W 183 [151 ER 79]; he “Ijaola” [1979] 1 Lloyd’s Rep 103 at 115–116,......
-
Table of cases
...329 (TCC) III.26.227 amey LG Ltd v amey Birmingham highways Ltd [2019] EWhC 234 (TCC) III.24.92 amey LG Ltd v Cumbria County Council [2016] EWhC 2856 (TCC) II.6.379, II.8.41, II.11.180, II.11.184, II.13.14, II.14.137, II.14.139, III.16.28, III.26.85, III.24.249 amey LG Ltd v Cumbria County ......
-
Litigation
...Royal Brompton Hospital NHS Trust v Hammond [2001] BLR 297 at 302 [24], per Aldous LJ. 347 See Amey LG Ltd v Cumbria County Council [2016] EWHC 2856 (TCC) at [1.12]–[1.34], per HHJ Stephen Davies. See also paragraph 26.83. 348 Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd ......
-
Price and payment
...(TCC) at [366]–[376], per Jackson J; Banham Marshall Services v Lincoln CC [2007] EWhC 402 (QB); Amey LG Ltd v Cumbria County Council [2016] EWhC 2856 (TCC) at [37.35], per hhJ Stephen Davies. 1416 See paragraph 25.202. 1417 See paragraph 26.306f. 1418 Eg, Queensland Building and Constructi......