Dear Katie and Mark
Approval of the 88th supplemental agreement to the track access contract
between Network Rail Infrastructure Limited and Arriva Rail London
Limited dated 9 November 2007
We have today approved the above supplemental agreement submitted to us formally on
23 October 2023 under section 22 of the Railways Act 1993 (the Act). This follows an
earlier informal submission of a draft agreement for our consideration. This letter explains
the reasons for our decision.
Purpose
The purpose of this agreement is to amend a bespoke provision in Schedule 4, Part 3,
Paragraph 2.4 “Network Rail payments” to better reflect current day access requirements.
Industry consultation
A consultation was not necessary for this application as the changes do not impact any
other party.
ORR review
Our review of the application raised no concerns.