AXA Insurance UK Plc v Cunningham Lindsey United Kingdom

JurisdictionEngland & Wales
JudgeMR JUSTICE AKENHEAD
Judgment Date18 December 2007
Neutral Citation[2007] EWHC 2464 (TCC),[2007] EWHC 3023 (TCC)
Docket NumberCase No: HT 06 209,Claim No: HT–06–209
CourtQueen's Bench Division (Technology and Construction Court)
Date18 December 2007
Between
Axa Insurance (UK) Plc
Claimant
and
Cunningham Lindsey United Kingdom
Defendant

[2007] EWHC 2464 (TCC)

Before

Mr Justice Akenhead

Claim No: HT–06–209

IN THE HIGH COURT OF JUSTICE

QUEEN's BENCH DIVISION

TECHNOLOGY & CONSTRUCTION COURT

St Dunstan's House

133–137 Fetter Lane

London EC4A IHD

Mr J Nicholson QC (instructed by Davies Lavery) appeared on behalf of the Claimant

Mr J Harvey and Mr J Purnell (instructed by Kennedys) appeared on behalf of the Defendant

Ruling

MR JUSTICE AKENHEAD
1

This is an application by the Defendant for leave to amend its Defence to plead a number of assertions relating to quantum and, more particularly, as to causation. The amendments sought are drafted in a form which could be incorporated in the Defence.

2

This claim by Axa, the insurance company, relates to alleged professional negligence of loss adjusters, Cunningham Lindsey, in relation to the reinstatement of an old farmhouse in Leicestershire (Orchard Farm, Burbage, near Hinckley). There had been subsidence, for which Axa had accepted liability under a householder's policy. Cunningham Lindsey was retained by Axa to provide services in connection with that reinstatement in 1999 and 2000. The scope of those services is in dispute. There is no issue, however, that the reinstatement did not proceed well; the reasons why, however, are in issue. Suffice it to say, Axa and Cunningham Lindsey parted company in about April 2000.

3

Axa then retained Cameron Durley Consulting Engineers to investigate, draw up work schedules or lists and supervise or monitor the completion works which took place between about August 2000 and August 2001. Whilst the original sum insured was just over £200,000, and the expectation when Cunningham Lindsey was involved was of a reinstatement cost of something less than £100,000, the eventual cost to Axa is said to have been over 1.5 million. Axa claim that the bulk of this cost is attributable to the negligence of Cunningham Lindsey; this is denied. Recently, at or shortly before the beginning of the trial, Axa sought leave to amend its quantum down to about £1.1 million, with various credits having been given; that was not opposed.

4

This trial has been fixed for almost a year, an order being made in that regard on 24th October 2006. Orders were then made for the exchange of expert reports. Those orders have been amended from time to time, most recently on 27th July of this year, when it was ordered that civil and structural engineering supplementary reports should be served by 14th September 2007. Axa's civil and structural engineering expert is Mr Kirwin of Cameron Durley, who was also personally, directly and intimately, involved in the completion works, whilst Cunningham Lindsey's expert in all disciplines is Mr Smithurst.

5

From correspondence put before me from the parties' solicitors, it was agreed that Mr Kirwin's and Mr Smithurst's supplementary reports should be mutually exchanged. Mr Smithurst's was apparently ready by 14th September 2007, whilst Mr Kirwin's was not ready until about 10th October. At about that time, both experts' reports were served, I believe Mr Smithurst being served before Mr Kirwin's. Whilst I have read Mr Kirwin's supplementary report, I have not read Mr Smithurst's because objections are made to its contents in part, there being a suggestion that it includes without prejudice material. I am told that it contains criticisms of Mr Kirwin's involvement in 2000 and 2001.

6

Mr Kirwin's supplementary report is, in the main, not responsive to earlier exchanged reports. It primarily relates to his examination of files of Glenborough Estates, who were the first contractor who worked under Cunningham Lindsey in 1999, albeit they were replaced in the latter half of that year with other contractors.

7

So far as I can ascertain, prior to this amendment, there had been no criticisms made by the defendant or their experts of Mr Kirwin. I have been referred by Mr Harvey to paragraphs 8.4 to 8.10 of Mr Smithurst's report of 16th April of this year. I cannot see, however, that there are any criticisms of a professional nature of Mr Kirwin in those paragraphs. They relate more to assertions by Mr Smithurst that, given the instructions which his firm received from Axa, it became inevitable that too much cost was incurred or cost was incurred which was not attributable to any allegations that might be made against Cunningham Lindsey.

8

I have also been referred to paragraphs 3.8 to 3.11 of the joint statement prepared by Mr Smithurst and Mr Kirwin. Again, I do not see in there any professional criticism of what Mr Kirwin may or may not have done during his period of involvement in 2000 and 2001.

9

Turning now to the proposed amendments, I am minded to allow the amendments which appear on the first page, except for the allegation at the bottom of the page in (ii) beginning “and/or its own failure to control or limit the work done and the costs of the claim”. These amendments relate to assertions either that AXA gave the wrong instruction(s) to Cameron Durley or that Cameron Durley exceeded those instructions; they are not seriously opposed. It seems to me—and there is not any or much objection to this from the claimant—these are matters which have been out in the open for a substantial period of time, and I do not see that Axa would have any prejudice in dealing with it, either through Mr Kirwin and/or Axa's other experts or in any other way. I am reluctant to allow the part which I have identified because it is really unparticularised and it does not relate to the instruction(s) which Cameron Durley received, unlike the rest of the proposed amendments on that page.

10

However, the allegations which are sought to be made on the second and third page of this draft amendment are prefaced with these words:

“In any event, the Defendant will say that the causative effect of any breach of contract and/or negligence which may be proved against the Defendant (other than that hereinbefore expressly omitted) was broken by one or more or all of the following matters which, for the avoidance of doubt, were not reasonably foreseeable and/or represent Axa's failure [or possibly its failure] to mitigate its loss.”

11

There then follow some 15 subparagraphs, A to O, in which a number of failures are alleged against Cameron Durley and, indeed, against Axa. Now, save for some of those allegations, I am not prepared to allow leave to amend. It seems to me that the defendant seeks to make a positive case that the chain of causation was broken by a large number of what are said to be Cameron Durley's failures and, indeed, Axa's failures. In these days, since the introduction of the CPR, it has become more important that positive cases on quantum by the defendants are pleaded. In the old days, it might have been satisfactory just simply to say, “Quantum is denied”, but it is satisfactory no longer. This is important because there is a line of authority, about which I make no comment, which might suggest that the chain of causation can be broken by the negligence of an expert adviser or designer retained by a claimant who is carrying out remedial or completion works, the costs of which are claimed as damages.

12

Now, I make no finding as to whether negligence has to be established or not; that is in issue and obviously I will hear argument about that. But certainly the way that these amendments are put would enable the defendant, if they were allowed, to argue that there had been negligence on the part of Cameron Durley in and about their conduct of the completion works which, if established as negligence, might then be sought to be relied upon to break the chain of causation.

13

The problem here is that, because Mr Kirwin is a witness of fact and also an expert, if these allegations of failure are established or sought to be established, the claimant has not procured the services of another engineering expert. That engineering expert, being independant at least in the sense of having had no involvement in the history, would have been able to comment on what are said to be failures on the part of Cameron Durley to do what it is said that they should have done. Mr Kirwin (who, for better or for worse, is being called also as an expert) would be open to the very real charge that, in dealing with allegations against himself personally, he could not exercise an appropriate degree of independence. I am told by Mr Nicholson, and I accept in general terms, that there is irredeemable prejudice as a result because they have not in fact brought on board such further expert.

14

Now, it seems to me that that is irredeemable because it is too late now, on Day Three of the trial, for the claimant to bring in an independent engineering expert, not without a massive disruption to and, indeed, inevitable adjournment of, this trial, which I would be most reluctant to allow. Therefore, that seems to represent, in general terms, irredeemable prejudice. Therefore, on that ground, the amendments should be disallowed.

15

There are, however, three exceptions to that. Three of the allegations relate to various alleged Cameron Durley's failures. They are:

“(b), Cameron Durley's failure to investigate adequately or at all what work CEB had specified and was undertaken by Glenborough Estates and Pearce;

“(d), Cameron Durley's failure to undertake any or any adequate inquiries of Glenborough Estates and Pearce to establish whether they had undertaken the allegedly defective work and, if so, on whose instructions, and whether any and, if so, what work had been carried out by the policyholders;

“(f) Cameron...

To continue reading

Request your trial
17 cases
2 firm's commentaries
  • Fire Safety; Risk Of Amending Appended Schedules To Contracts And Delaying Remediation
    • United Kingdom
    • Mondaq UK
    • 27 January 2023
    ...remedy the defects? In determining this issue the court followed the principles set out in Axa Insurance UK Plc v Cunningham Lindsey [2007] EWHC 3023 (TCC). The key point was that, as in Struthers v Davies [2022] EWHC 333 [TCC]; it was not enough for Lendlease to present an alternative sche......
  • Causation: Recovery By Insurers From Loss Adjusters
    • United Kingdom
    • Mondaq United Kingdom
    • 1 February 2008
    ...policy, and not be drawn into paying for additional works. Further reading: Axa Insurance UK Plc v Cunningham Lindsey United Kingdom [2007] EWHC 3023 (TCC). This article was written for Law-Now, CMS Cameron McKenna's free online information service. To register for Law-Now, please go to Law......
5 books & journal articles
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...614) II.10.108 ACA Developments Pty Ltd v Sullivan [2004] NSWSC 304 II.6.94 ACA Insurance UK plc v Cunningham Lindsey United Kingdom [2007] EWHC 3023 (TCC) III. 23.65, III.26.75 A Cameron Ltd v John Mowlem & Co plc (1990) 52 BLR 24 (CA) II.6.403, III.23.40, III.24.02, III.25.38 ACB v homson......
  • Dispute resolution
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...of contract caused A to incur a loss in settling a dispute with B. See also AXA Insurance UK plc v Cunningham Lindsey United Kingdom [2007] EWHC 3023 (TCC) at [271]–[273], per Akenhead J; Anwar Patrick Adrian v Ng Chong & Hue LLC [2014] SGCA 34 at [205]–[210]. 264 Royal Brompton Hospital NH......
  • Damages
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...v London Borough of Southwark [2006] EWHC 1411 (TCC) at [155], per Ramsey J; AXA Insurance UK plc v Cunningham Lindsey United Kingdom [2007] EWHC 3023 (TCC) at [274]–[275], per Akenhead J; Hunt v Optima (Cambridge) Ltd [2013] EWHC 681 (TCC) at [254]–[259], per Akenhead J (appeal allowed, on......
  • Litigation
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...& Farmer (No 2) [2006] EWHC 1222 (TCC) at [5]–[6], per HHJ Coulson QC; Axa Insurance (UK) plc v Cunningham Lindsey United Kingdom [2007] EWHC 2464 (TCC); Governing Body of the Charterhouse School v Hannaford Upright [2008] BLR 239 at 247–248 [47], per Akenhead J. he granting of leave to ame......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT