Bluewater Energy Services BV v Mercon Steel Structures BV and Others

JurisdictionEngland & Wales
JudgeMr Justice Ramsey
Judgment Date30 June 2014
Neutral Citation[2014] EWHC 2132 (TCC)
Docket NumberCase No: HT-10-355
CourtQueen's Bench Division (Technology and Construction Court)
Date30 June 2014

162

Other Variations

162

Issue 14. Did Mercon fail to comply with the notice requirements in clause 14.3 to 14.7 in respect of any claimed variations and, if so, what effect does this have (if any) on its right to payment?

162

Clause 14 of the Contract

162

Variation Orders and Variation Order Requests

168

Issue 15: What is the value of the variation account (excluding VOR 8), including discount (if any)?

168

VORs agreed between the parties

168

Fabrication of main bearing support rings (option O6.1) [VOR 126]

169

Additional E&I works [VORs 128, 129, 227, 228, 230, 239, 243, 256, 258, 270]

169

Costs to execute Site Instruction 21 [VOR 148]

169

Fabricating slotted holes in cover ring [VOR 235]

169

Unloading of platforms and supports [VOR 236]

169

Costs to execute Site Instruction 43 [VOR 250]

169

Disputed VORs

169

VO-003 – Resubmission of Drawings

169

Increased size of contract scope, including 5th leg to the substructure (800T mooring loadcase) [VOR-004]

171

Change of material specification to PCFW36S [VOR 6]

175

Extra cutting and welding costs for adding Type 1 steel [VOR 34]

176

Increased size and required number of guides in pile sleeves [VOR 87]

177

Additional machining and cladding [VOR 144]

177

New design main bearing [VOR 147]

178

Additional Cost for Shipments 1 (VOR-161 Rev 2), 2 (VOR-229 Rev 1) and 3 (VOR-266 Rev 2)

179

Costs for turntable rotation/clash test [VOR 162]

181

Additional piping fabrication and materials [VORs 172, 174, 185, 186, 187, 188, 189, 190, 191, 192, 193, 194, 195, 196, 197, 198, 199, 200, 203, 204, 205, 206, 207, 208, 209, 210, 211, 212, 213, 214, 215, 216, 217, 218, 219, 220, 221, 222, 223, 224, 225, 226, 244, 245, 254]

182

Removal of top part of end plates to comply with transport restrictions [VOR 241]

185

Painting repair Central Column Gorinchem [VOR 247]

186

Yoke Hinge House rotation test [VOR 248]

186

Installation Yoke Hinge House on to Yoke Hinge Body [VOR 249]

186

Temporary placing FMS structures on quay [VOR 255]

187

Preheating of thick plates [VOR 267]

187

Summary

187

Discount on Total Value of VOs

190

Other Bluewater Claims

190

Issue 21(a): What sums are due, if any, in respect of LADs for Key Personnel?

190

Introduction

190

Contractual provisions

191

Submissions

191

Decision

194

Exchange of the Project Manager from P van Daele to R. de Jong (€50,000)

195

Removal of the Site Construction Manager Astrakhan, P. Van den Brule, without replacement (€50,000)

196

Exchange of Transportation and Logistics Manager from J. Marijnissen to M. Hoep (€30,000)

196

Exchange of Mechanical Completion and (pre) Commissioning Manager from T Jordaans to a person unknown to the Claimant and then to E. van Leliveld (€30,000)

196

Removal of the HSE Engineer J Koning, without replacement, €20,000.

. 197

Summary

197

Compensation of Expenses – Custom Duties and Charges

198

Additional Sailing costs for optimisation of FMS stowage and shipment of piles

199

Engineering Costs for relocation of Drain Tank due to Changed Transport Split

199

Failure to deal with Customs clearance for "free issue" equipment temporarily Imported

200

Sorting mix-up of Project Materials in Container

200

Management & Engineering Costs

200

Loss of Profit on Management & Engineering Costs

201

Steve Osmond Costs — Remeasure Database

201

Bluewater Welding Expert Costs

202

J Glazenburg Costs — Remeasure Database

202

Costs for provision of HSE Plan

202

Personnel at SEC — Additional involvement

203

Costs for provision of Commissioning Plan

203

Chairing "kick-off" meeting at EEW in Germany

203

Welding Procedures — Costs of specific advice

204

Chairing "kick-off" meeting at MRC, Schiedam

204

Chairing "kick-off" meeting at SIF, Roermond

204

DNV Additional and extended costs — Fabrication Witness

204

DNV Additional and extended costs — Design Review

205

Failure to return surplus free-issue steel

205

Additional Costs to Make Pendulums transportable by Rail and Additional Costs for Transportation of Pendulums

207

Additional Procurement Costs, Ballast Tank Materials

208

Summary

208

Issue 21(c): What sums are due, if any, in respect of post-termination damages?

208

Sums paid to ASPO

211

Sums paid to Mercon not for properly reimbursable work

212

Insulation work

212

Issue 21(d): What sums are due, if any, in respect of NCRs?

212

Miscellaneous NCRs (NCR-2, 4, 5, 6, 8, 9, 10, 55, 64, 66, 69, 71, 72, 73)

212

NCR 1 – Rectification Work Ice Resistant Zone

215

NCR 051 – Missing Stud Bolts / Gaskets to Pipework

216

NCR 077 – Non-Supply and Installation of Connection between Swivel Leak Tank and Grease System / Bearing

217

NCR 012 – Non Conforming Bolting of Grating of Chain Stopper and Non-Conforming Bolting and Grating of Hose Connection Tower

217

NCR 055 – Warning Signs

217

NCR 014 – Non-Conforming Tubing, Braces, Handrailing of Yoke Arm, Platforms

218

NCR 015 – Non-conforming Sheave Supports and Keep Plates on Chain Stopper (CS) Platform

. 219

NCR 016 – Ballast Tank Openings

220

NCR 017 — Non-Conforming Connection between Winch arm and HPU (Yoke Arm)

220

NCR 060 – Non-Supply of Lighting Materials

221

NCR 076 and 003 – Non supply and Installation of Hydraulic Connections between the HPU (FMS) and Winch (HCT)

221

NCR 052 – Incorrect Orientation of Substructure at Quay ASPO

222

Additional Costs for ASPO office facilities

224

Additional Costs for ASPO Progress Reporting

224

Costs of Bluewater Project Management and Engineering

224

Loss of Profit on Bluewater Project Management

225

NCRs 7, 20, 21, 53, 54 & 79 Failure to provide the MRB/As-Built documentation

225

Summary

226

Issue 21(e): What sums are due, if any, in respect of other costs to complete?

227

Incentive Payment

228

Seafastenings (certificates 1,5,6,14,17 and 21)

228

Customs Charges and Duties (certificates 7, 13, 15, 18 and 26)

229

Provision of Warranty Services

229

Area Rent

229

Delivery of Load Out Procedure

230

Conclusion

230

Issue 21(f): What sums are due, if any, in respect of Russian Federation VAT?

230

RFVAT on the Payment Contract

233

Payment Contract: Reimbursable cost invoices

233

Payment Contract: Ransom Payment

235

RFVAT on the Work Contract

235

Invoice 2008–73

237

Invoice 2008–56

237

RFVAT paid to Mercon but not paid to ASPO

237

Summary: RFVAT Claims

237

Other Mercon Claims

237

Issue 22: Is Mercon entitled to claim for lost profit (if Bluewater wrongly terminated the contract) and, if so, in what sum?

237

Clause 25

237

Unpaid Balance of RFVAT

239

Overall summary and conclusion

239

Mr Justice Ramsey

Introduction

1

These proceedings relate to claims arising under a sub-contract ("the Contract") made between the Claimant ("Bluewater") and the Defendant ("Mercon") for the fabrication of a tower based soft yoke mooring system ("SYMS") for installation as part of the development of the Yuri Korchagin Field in the Caspian Sea.

2

Bluewater was a company in the Bluewater Group. Companies

within that group entered into a contract with the Russian oil company, Lukoil, for the design, construction and installation of the SYMS.
3

Mercon in turn sub-contracted parts of the Contract work to a number of companies, including Astrakhan Shipbuilding Production Association LLC ("ASPO"), based in Astrakhan.

The SYMS

4

The SYMS consisted of various components which included the sub ? structure which was pre ?fabricated by ASPO under its subcontract with Mercon. There was then a Central Column which was a tubular section. This was manufactured by SIF, a subcontractor to Mercon based in Holland. The Central Column was delivered to Mercon for the fitting of stiffeners/trunnions before being transported to Astrakhan where it was integrated with the sub-structure. Together they formed the Jacket. Another component was the piles on which the Jacket was to be installed. These were fabricated by another subcontractor to Mercon, EEW in Rostock, Germany. The piles were also transported to Astrakhan.

5

A further component was the Topsides. These consisted of a number of elements such as the turntable, pig receiver deck, hose connection deck and tower. They were fabricated by Mercon at its yard in Gorinchem. The Topsides were transported in two parts from Gorinchem to ASPO's yard and integrated there. Another component was the Yoke assemblies, the principal parts of which were the Yoke End, the Yoke Hinge body or 'casting' and the Yoke Hinge house or 'housing'. These were shipped to Astrakhan together with the Crane Structure.

Brief Chronology

6

After tendering, a Letter of Intent for the work was provided by Bluewater and signed by Mercon in December 2006.

7

The Contract was made on 26 March 2007. It contained various Options, some of which in due course were exercised. Option 5 was exercised on 29 March 2007, immediately after the Contract was made, although it was not formalised into a Variation Order until VO-005 in March 2008. This Option related to the...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
5 cases
  • Triple Point Technology, Inc. v PTT Public Company Ltd
    • United Kingdom
    • Supreme Court
    • 16 July 2021
    ...the Greenore case [2006] EWHC 3119 (TCC); the Shaw case [2010] EWHC 1839 (TCC); the LW Infrastructure case [2012] BLR 13; the Bluewater case 155 Con LR 85. (iii) The clause continues to apply until the second contractor achieves completion: the Hall case [2010] EWHC 586 (TCC); the Crestdrea......
  • Tata Consultancy Services Ltd v Disclosure and Barring Service
    • United Kingdom
    • King's Bench Division (Technology and Construction Court)
    • 17 May 2024
    ...Services [2011] B.L.R. 384 (Comm Ct) at [262] and of the approach of Ramsey J in Bluewater Energy Services BV v Mercon Steel Structures [2014] EWHC 2132 (TCC); 155 ConLR 85 at [308]–[312]). Although an over-simplification to some degree, ultimately the provision of the infrastructure by HP......
  • Apsara Restaurants (Barbados) Ltd v Guardian General Insurance Ltd
    • Caribbean Community
    • Caribbean Court of Justice
    • 22 January 2024
    ...Ltd [1955] AC 370; Biogen Inc v Medeva plc [1998] 1 LRC 21, [1977] RPC 1; Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132 (TCC); Blyth v Blyth [1966] AC 643; Bond v Dunster Properties Ltd [2011] EWCA Civ 455; Boodoo v A-G of Trinidad and Tobago [2004] UKPC 17,......
  • Tata Consultancy Services Limited v Disclosure and Barring Service
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 17 May 2024
    ...in Abu Dhabi v SD Marine Services [2011] B.L.R. 384 (Comm Ct) at [262] and of the approach of Ramsey J in Bluewater Energy Services BV v Mercon Steel Structures [2014] EWHC 2132 (TCC); 155 ConLR 85 at [308]–[312]). Although an over-simplification to some degree, ultimately the provision of ......
  • Get Started for Free
3 firm's commentaries
  • Liquidated Damages And Unfinished Works
    • United Kingdom
    • Mondaq UK
    • 23 September 2019
    ...Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd [2011] SGHC 163; Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132 (TCC). Liquidated damages apply until the works are completed under a separate contract by a replacement contractor: Hall v Van der Heiden [2......
  • Liquidated Damages Not Recoverable Where Contract Terminated Prior To Completion
    • Singapore
    • Mondaq Singapore
    • 2 September 2019
    ...Pte Ltd v Lim Chin San Contractors Pte Ltd [2011] 4 SLR 477; and Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132. [3] Hall v Van Der Heiden (No 2) [2010] EWHC 586; Crestdream v Potter Interior Design (2013) HCCT 32/2013; and GPP Big Field LLP v Solar EPC Solutions......
  • Good Faith: English Law v the UAE Civil Code
    • United Kingdom
    • Mondaq UK
    • 26 January 2015
    ...day out of date chocolate mousse). [2013] EWHC 1151 (TCC). TPC 2005 as amended in 2008. (2) Mercon Holding BV; (3) Mercon Groep BV [2014] EWHC 2132 (TCC). [2008] EWCA Civ 116 In the Compass case, Jackson LJ had rejected such an implied term on the grounds that the term in question was an ab......
7 books & journal articles
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...WASC 287 I.3.197 Blue Station Ltd v Kamyab [2007] EWCA Civ 1073 II.6.366 Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132 (TCC) I.3.191, II.6.283, II.6.327, II.6.334, II.6.420, II.7.22, II.9.94, II.9.138, II.11.95, II.13.165, II.13.182, II.13.217 Blundell v Musgrav......
  • Contract terms
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...UKPC 11 at [15]; Chartbrook Ltd v Persimmon Homes Ltd [2009] 1 AC 1101; Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132 (TCC) at [706]–[707], per Ramsey J. In Singapore, the parol evidence rule is enshrined in statute: Evidence Act (Cap 97, 1997 revised edition) (......
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...of State (2004) 104 Con Lr 110 at 204 [332]–205 [335], per hhJ hornton QC; Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWhC 2132 (TCC) at [839], per ramsey J. a countersignature does not, however, make the content of a time sheet conclusive: JDM Accord Ltd v Secretary o......
  • Variations
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...Society Ltd [1998] EWhC Technology 339 at [292], per hhJ hornton QC. 54 See Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWhC 2132 (TCC) at [66], per ramsey J. 55 See, eg, West 3 Mechanical Contractors Ltd v Mizen Design Build Ltd [2014] EWhC 4004 (TCC) at [97]–[99], per......
  • Get Started for Free