Chapter 10: The site
| Library | The Law and Practice of Complex Construction Projects |
| Pages | 95-99 |
| Author | Fabio Solimene |
In general terms, the construction site (sometimes also referred to as building site) is the area of land on which construction works are being carried out. The Construction (Design and Management) Regulations 2015 1 (CDM Regulations) indicate that a construction site is the area that “
For obvious reasons, the site plays an important role in a construction project and the relevant contractual terms are usually heavily negotiated as the site may be the source of major disputes between the parties.
Construction contracts provide an obligation on employers to give contractors access to and possession of the site (although the employer’s obligation does usually extend to acts that are outside the employer’s control 3 ) within an agreed term. Full access to the site is normally granted from the commencement date (i.e., the date in which the works are to be commenced, which usually coincides with the date in which the employer issues a so-called notice to proceed). The contract may state that access to site shall be subject to it being necessary to perform the works. Absent of such provision, access will be intended as undisturbed exclusive possession. 4 It is worth noting that the employer’s obligation to give the contractor timely access to the site is an implied term of the contract even in the absence of an express provision. 5
The contractual provision covering access to the site will usually also describe the consequences and remedies in case the employer fails or delays to provide access to site to the contractor in compliance with the contract. Usually, the contractor will be entitled to an extension of time (provided that completion is or will be delayed due to the delayed access to the site) and the compensation of any prolongation borne by the contractor as a consequence thereof, unless the delay was caused by the contractor. However, an employer’s failure to grant access to the site does not usually entitle a contractor to terminate the contract: (i) as a result of repudiation of the contract by the employer, unless the employer’s conduct clearly indicates that it has no intention at all of providing access to the contractor; or (ii) for breach of contract, 6 unless the breach is sufficiently serious, e.g., where time is stated to be of the essence and the delay in accessing site would have an impact on completion. However, in such case the parties will usually agree on an extension of time, unless a later completion would not make any sense for any of the parties (e.g., because by agreeing on a new completion date the employer would be deprived from the benefit of the project or the contractor would be in breach of a different contract due to an overlap with the project whose completion date was postponed).
Upon the contractor taking possession of the site (and until the employer retakes possession), the relevant responsibility, including any responsibility on the equipment, material and any other property present on site, will shift on the contractor so that the contractor will usually be required to indemnify the employer for any damages thereof. For this reason, it is common for contractors to enter into so-called contractors’ all risks (C.A.R.) insurance policies against possible risk of physical damages to the site. However, albeit less common in practice, the parties to a construction contract may agree that the employer shall bear the risk of any damages arising during the work, e.g., due to fire or explosion. However, such clauses would be interpreted by the courts as exclusion clauses which may not exempt contractors from the consequence of events covered by the clauses resulting from the contractor’s own negligence. 7
Construction contracts normally specify what party takes this risk in case the site conditions prove unexpectedly more adverse than anticipated. Such a situation would probably affect the project and lead to an increase of cost and time required to complete it. For example, in the case of an offshore wind farm, a contractor may be provided by the employer with geotechnical data and information on seabed, sub-surface and hydrological conditions which prove to be inaccurate (e.g., due to the presence of...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting