Chapter 13: Performance
| Library | The Law and Practice of Complex Construction Projects |
| Pages | 109-124 |
| Author | Fabio Solimene |
Quality control systems are processes aimed at ensuring that products, materials and services (including work and work units) comply with the relevant requirements. Such processes are typically carried out by measuring the final quality characteristics of the product or service (or any unit of it) by comparing them with the specific quality standards 1 so to find out any differences between the results obtained and the desired results and find solutions to correct any errors. Quality control systems also usually provide for tests and inspections being carried out during the construction process in order to identify and possibly correct errors before a final result is obtained.
Construction contracts also often refer to quality assurance systems, which are processes aimed at ensuring that the quality procedures implemented during the design phase of a construction project effectively meet the employer-established quality standards for service, performance and production of a project (or a unit thereof). This is obtained by creating a set of rules about minimum quality of, for example, materials (e.g., size, shape and composition), equipment (e.g., safety), how quality is measured (e.g., high standards), project management (e.g., bidding procedures), people skills and experience (e.g., certifications, track record), and procedures aimed at ensuring that such rules are complied with in order to meet the required standards.
A typical quality assurance and quality control clause in a construction contract would set forth the contractor’s obligation to institute and maintain quality assurance and quality control systems in line with the requirements of the contract with specific reference to the standards to be met for the specific project and relevant units.
Commencement generally refers to the moment in which a contractor starts the construction works, and will typically be proceeded by pre-construction activities such as design, procurement and mobilisation, obtaining planning permissions and building regulations approvals, notifying the various competent authorities, etc.
The commencement date may be a fixed date, or the date on which the employer gives the contractor the green light by issuing a so-called notice to proceed (or, usually, as soon as reasonably practicable after that), or a date calculated starting from the occurrence of a certain event (e.g., upon the contractor being given possession of the site or a number of months from the date on which any necessary permissions have been obtained).
The commencement date has important legal implications as from that date the contractor will typically take on a number of obligations such as those relevant to the health and safety of the site.
Where the contract includes a commencement date, and the contractor does not commence the works within that date, this may be construed as a repudiation of the contract entitling the employer to terminate the contract (subject to any conditions under the contract such as the employer’s obligation to first send a notice to the contractor urging it to commence the works within reasonable time or within a reasonable certain date). However, where the contractor has a lawful excuse to delay commencement, a court may find that the contractor has not repudiated the contract and hold any resulting termination unlawful. In
Where a construction contract does not include a commencement date, the contractor is under no obligation to commence work within a specific date unless such a commencement date may be inferred from the circumstances of the contract. However, the contractor will still be required to complete the work within the completion date stipulated in the contract (or within reasonable time of the employer providing access to the site in case the contract does not include a completion date). 3
A programme is a tool enabling contractors to forward-plan so to ensure a project is delivered on time, within budget and in line with the agreed quality standards. The Society of Construction Law Delay and Disruption Protocol 4 states that:
to assist in managing progress of the works and to reduce the number of disputes relating to delay and disruption, the Contractor should prepare and the Contract Administrator (CA) should accept a properly prepared programme showing the manner and sequence in which the Contractor plans to carry out the works. The programme should be updated to record actual progress, variations, changes of logic, methods and sequences, mitigation or acceleration measures and any EOTs granted 5 .
As such, a programme may include, among other things: (i) the project’s scope of work; (ii) the different development phases; (iii) the anticipated timing of each phase; (iv) the order in which the contractor intends to carry out the works (i.e., the activities that can be carried out simultaneously and those that need to be sequenced); (v) reviews and updates made to account for unforeseen changes to schedule, additional requirements, delays, etc., whenever the previous programme is inconsistent with actual progress; (vi) the periods for each review; (vii) any supporting documents (e.g., description of the construction methods, estimate of the number of contractor’s personnel dedicated to the various tasks, indication of equipment required on the site for each phase, etc.). In addition, a programme may also include budgets for each activity and expected cash flow for each phase.The contract may provide that the contractor shall produce the programme. In such case the document produced by the contractor will be considered a statement of the contractor’s intention (or best endeavours) that the works will be performed in accordance with that programme. 6 If the contractor fails to produce the programme, this may constitute a breach of contract.
A construction contract may oblige the contractor to “strictly” follow the programme. In such case, the contractor will be in breach of contract in case of failure to adhere to that programme. 7 In this case, when the breach may result in a delay in the completion of the works, the contractor will be typically allowed to take steps to ameliorate the consequences of that breach by taking later accelerative measures. 8 Where, instead, the contract is silent on the binding nature of the programme, the contractor will not be bound to work to that programme. 9 Moreover, in case the programme prepared by the contractor indicates a completion date which is earlier than the one agreed in the contract, the contractor will not be in breach of contract in case completion does not occur within the earlier date indicated in the programme, 10 unless the contract states otherwise.
Employers are not usually obliged to comply with the programme. However, the parties may agree that an employer’s failure to comply with the programme will entitle the contractor to submit a revised programme where the employer’s failure has had the effect to delay completion. The contract may also state that, in such case, the contractor will also usually be entitled to an extension of time.
Employers are also usually entitled under the contract to ask the contractor to prepare a revised programme in case they consider that the existing one fails to comply with the contract or is inconsistent with actual progress of the works.
Unless the contract provides otherwise, contractors can programme the works as they deem suitable to achieve completion of the works by the completion date agreed in the contract. However, construction contracts usually include clauses on how contractors should proceed with the works. A typical wording would be that the contractor shall progress the works “
continuously, industriously and efficiently with appropriate physical resources so as to progress the works towards completion substantially in accordance with the contractual requirements as to time, sequence and quality of work. 13
It is worth noting that, in order to comply with such obligation both elements must be present so that a contractor may be in breach in case it has progressed regularly but not diligently and vice-versa. 14 Both obligations relate to the level of resources allocated by the contractor to achieve the contractual objective. 15 However, where the contractor progresses the works, but not in a “Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting