Chapter 14: Time

LibraryThe Law and Practice of Complex Construction Projects
Pages125-137
AuthorFabio Solimene
14.1: Extension of time for completion 14.1.1: Extension of time in general

Extension of time clauses have the effect of extending the date by which the works shall be completed, so relieving the contractor of its obligation to pay damages (liquidated or general, according to the contract) for late completion, in cases where the works have (critically) fallen behind schedule for reasons that are not attributable to the contractor (i.e., where the delay is due to acts of the employer or to so-called neutral events, such as a force majeure event). In the absence of an extension of time clause, time will be “at large” and the contractor will be obliged to complete within a reasonable time. EOT clauses are therefore beneficial for both contractors and employers as they: (i) allow contractors more time to complete the works and eliminate or reduce (depending on the length of the extension) their liability for liquidated damages (in case the contract provides for liquidated damages in case of delay); and (ii) set a new completion date, so preserving the employers’ entitlement to liquidated damages (if the contract provides for such damages) for delays for which the contractor is culpable (so avoiding time becoming at large).

The benefits of an extension of time are summarised as follows in the SCL Protocol: 1

The benefit to the Contractor of an EOT is to relieve the Contractor of liability for damages for delay (usually LDs) for any period prior to the extended contract completion date and allows for reprogramming of the works to completion. The benefit of an EOT for the Employer is that it establishes a new contract completion date, prevents time for completion of the works becoming ‘at large’ and allows for coordination/planning of its own activities.

Whether a contractor is entitled to an EOT is ultimately a matter of contract. However, in order for an EOT to be afforded it will be necessary that the delay on which basis the EOT is requested be critical, i.e., leading to the contractor’s incapacity to complete within the agreed completion date. As a result, in case a contractor has planned to complete the works ahead of the contractual completion date, a delay not attributable to the contractor which prevents it from completing within the planned date of completion is irrelevant and will usually not entitle the contractor to an EOT, unless the delay has also affected the contractor’s ability to complete within the contractual completion date.
14.1.2: Extension of time clause

As mentioned, whether a contractor is entitled to request an EOT and in what cases will depend on the terms of the contracts. A typical EOT clause may provide as follows: (i) that the contractor shall not be entitled to an EOT where the delay is the result of its own acts, omissions, defaults or negligence (or his subcontractors); (ii) that the contractor will be entitled to EOTs in case of specific events provided in the contract. These will be events for which the employer is responsible such as variations, acts of prevention, employer’s failure to give the contractor timely access or possession of the site, suspension of the works instructed by the employer, neutral events such as changes in law, force majeure, exceptionally adverse weather conditions, etc.; (iii) the specific procedure the contractor should comply in case it considers itself to be entitled to an EOT (which will typically be in line with the one provided in the contract for all other contractor’s claims); (iv) the contractor requesting an EOT shall mitigate the effects of any delay to the works; (v) the EOT will not affect any delay damages already accrued, even if not yet claimed by the employer; (vi) in case of concurrent delays, any delay for which the employer is responsible which is concurrent with other delays caused by the contractor will not be considered to calculate the EOT.

EOT clauses also include language aimed at covering ownership of the “float”. The float is defined in the SCL Protocol 2 as: the amount of time by which an activity or group of activities may be shifted in time without causing Delay to Completion. Therefore, the float is the amount of time that work activities can absorb, in excess of their original intended duration, without impacting on the critical path of the works. Until the float is completely exhausted, a delay to progress will not result in the contract completion date being missed, but merely in an erosion of the float. The float is a resource which is subject to “ownership” by any of the parties (or the project). Both parties will typically seek to own the float and the issue is usually cause of disputes between them. The opposing interests of the parties are clearly summarised as follows in the SCL Protocol: 3

The ‘ownership’ of float causes particular arguments in disputes over entitlement to an EOT. A Contractor may argue that it ‘owns’ the float, because, in planning how it proposes to carry out the works, it has allowed additional or float time to give itself some flexibility in the event that it is not able to carry out the works as quickly as it planned. If, therefore, there is any delay to the Contractor’s progress for which the Contractor is not responsible, it may contend that it is entitled to an EOT, even if the delay to progress will not result in the contract completion date being missed, but merely in erosion of its float. On the other hand, an Employer may typically say that the Contractor has no EOT entitlement unless the delay to progress will result in a contract completion date being missed. So (the Employer may say) the project owns the float.

The approach suggested in the SCL Protocol is that the parties state in the contract which party “owns” the float in the EOT clause as absence or ambiguity about float generates uncertainty and disputes are likely to follow. In case the contract does not contain any provisions as to the float, the float will be owned by the project so that, unless the contract states otherwise, in case of non-critical employer delays having the effect of eroding the float, a contractor may not claim an EOT, nor may it recover its acceleration costs in case it sought to accelerate the works to keep the float time. This approach is consistent with the current judicial thinking. 4
14.2: Acceleration 14.2.1: Acceleration in general

As the word suggests, acceleration in construction projects is the process of working at a faster pace than originally anticipated. However, the precise meaning of the word is somewhat obscure under English law. As stated by Judge Hicks in the case of Ascon Contracting Ltd v Alfred Mcalpine Construction Isle of Man Ltd: 5

‘acceleration’ tends to be bandied about as if it had a precise technical meaning, but I have found nothing to persuade me that this is the case.

Despite that, the issue of acceleration is very often raised in the context of complex construction projects, and claims for additional costs resulting from acceleration measures are quite common.

It is worth noting that acceleration should not be confused with mitigation. The SCL Protocol 6 clarifies that:

Mitigation simply means to make less severe or lessen delay, disruption and/or the resultant costs and/or loss. Acceleration is a subset of mitigation, and typically refers to the situation where additional costs are incurred to seek to overcome all or part of delay or disruption (for example, to ensure that that the contract completion date is achieved). Where the Employer is responsible for that delay or disruption, the Contractor may claim its acceleration costs from the Employer. This situation is distinct from a Contractor’s general duty to mitigate its loss when it suffers delay and disruption or incurs additional cost due to an Employer Risk Event. That general duty to mitigate does not require the Contractor to incur additional costs.

14.2.2: Categories of acceleration

There are three categories of acceleration, i.e., instructed (or directed) acceleration, constructive (or implied) acceleration and voluntary acceleration.

14.2.2.1: Voluntary acceleration

Voluntary acceleration occurs when a contractor unilaterally decides to accelerate its own work, e.g., to recover its own delays. In this case, the contractor will not be entitled to any damages.

14.2.2.2: Instructed (or directed) acceleration

An instructed acceleration occurs when the employer issues a specific acceleration instruction order to the contractor. In such instruction the employer may direct the contractor: (i) complete the project earlier than the contractually agreed completion date; (ii) re-sequence the work and/or reorganise the works (e.g., by using more or different equipment and/or hiring more labourers and/or having labourers doing overtime or additional shifts) in order to complete the original project scope of the work, plus additional or changed work within the agreed completion date (e.g., in case the contractor has been granted an EOT, but the employer instructs the contractor to complete within the original completion date) or to recover contractor-caused delays that threaten the achievement of the agreed completion date.

The consequences for a contractor that fails to accelerate upon a valid instruction, may be severe. In the case of Masons v W D King 7 the court held that in such cases the contractor may be liable for actual loss deriving from the delay over and above the contractually stipulated liquidated damages.

14.2.2.3: Constructive (or implied) acceleration

Constructive acceleration occurs when a contractor encounters excusable delay entitling it to an extension of time, which the employer fails to grant. In such cases, a contractor may decide to accelerate the works to meet the contractually agreed completion date to avoid risk of incurring delay damages (or simply to avoid delaying other projects), but then claim...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex