Chapter 15: Managing time, cost and quality – a tale of two buildings 1

LibraryContracts for Construction and Engineering Projects
Pages186-201
AuthorDonald Charrett
15.1: Introduction

Successful project management of the delivery of a building involves managing the three elements of time, cost and quality to the satisfaction of the Employer. Conversely, a perceived shortcoming in one or more of those elements in the procurement of a building project will be seen by the Employer as a “failure” – “an unacceptable difference between expected and observed performance”. 2 That is, an Employer may perceive the outcome of a building project to be a failure if the project cost more than anticipated, took longer to complete than anticipated or the final quality fell below expectations.

Engineering or building failures in the more generally accepted sense of structural failure capture the public's attention, particularly when they result in significant loss of life. However, “failures” in the broader sense as defined above are also newsworthy, particularly if they involve publicly funded buildings or infrastructure. Cost overruns and late delivery of public infrastructure are virtually certain to be subject to public scrutiny. Such public attention can in turn capture the attention of politicians who can be subjected to considerable political pressure to “do something”. That “something” not infrequently takes the form of a public enquiry or investigation, sometimes a Royal Commission. Further, substantial Government expenditure is usually subject to scrutiny by an independent Auditor.

The theme of this chapter is the lessons that can be learned from the delivery of two seminal building projects – the Australian Parliament House in Canberra (APH), and the Scottish Parliament House in Edinburgh (SPH). Whilst these projects were completed at different times (1988 and 2004 respectively), and in different countries, it will be seen that there are many common factors, including the method of project delivery. APH received significant adverse comments on the cost and time management of the construction by the Auditor General, who published a critical “Efficiency Audit”. 3 After completion of the building, the Parliament House Construction Authority (PHCA) prepared its own publication documenting the history of the project and the lessons learned, and rebutting the Auditor General's criticisms. 4 There was, however, no independent public enquiry as such into the procurement of APH. The procurement of SPH was also the subject of examination by the Scottish Auditor General on two occasions, in 2000 when construction was at an early stage, 5 and in 2004 near the end of the project. 6 Further, no doubt as a consequence of the publicity given to the substantial time and cost overruns of SPH, there was a public enquiry into all aspects of the procurement of SPH conducted by Lord Fraser, building on the Auditor General's findings. 7 The sources of the following comments on these two high-profile public buildings was derived from these public documents.

It should be emphasised that neither of these two buildings could be considered a “failure” in the traditional sense, nor is it suggested that there was any shortfall in the expected quality of either building. These buildings are both architectural award-winning very high-quality nationally symbolic buildings, providing an environment for the complex workings of democratic parliaments, accessible by the people. It is however arguable that the substantial cost overrun for SPH constituted a “failure” in that there was an unacceptable difference between the budget cost and the final as constructed cost, as well as an unacceptable difference between the scheduled date for completion and the actual date of completion. Whether or not the final cost and time of delivery of APH constituted a “failure” depends on whether the view of the Auditor General or the PHCA is accepted.

15.2: Similarities in delivery of the Australian Parliament House and the Scottish Parliament House

Clearly, no two buildings on different sites, let alone in different countries, with different functional requirements and constructed at different times, can be directly comparable. However, the following factors relevant to the project delivery method and its implementation were similar for these two buildings:

  • Construction of a long-lasting Parliament building as a National Symbol.

  • Procurement and project management by civil servants responsible to the Government and Parliament.

  • Architect selected after an international design competition.

  • Emphasis on very high building quality, both as a functioning, long-lasting durable building, and as a showcase for local craftspeople, artisans and artists.

  • Procurement and construction by a Construction Manager who managed the construction by letting and administering a large number of trade subcontracts.

  • A very tight construction programme that could only be achieved through fast track construction in which construction was commenced before the design was complete.

  • Changed user requirements, including significant increase in space after the design had been commenced.

  • Considerable public scrutiny of achievement of time, cost and quality targets.

  • Architect's pursuit of excellence, notwithstanding the (largely unsuccessful) Project Manager's attempts to impose budgetary constraints.

15.3: Australian Parliament House 15.3.1: Procurement

An international design competition was held in 1979 to select the design for Australia's new Parliament House. Key aspects of the competition brief were:

  • Budget cost $151m in May 1978 prices.

  • Building to be opened on Australia Day 1988.

  • Usable area of 60,300 m2 for 188 Parliamentarians, 124 Representatives and 64 Senators.

  • High-quality materials and finishes.

  • National symbol.

  • Building to last 200 years.

No doubt mindful of the possible time and cost consequences of innovative structural design (e.g. Sydney Opera House, 8 1976 Montréal Olympic Stadium), an early decision was taken that the structure was to be conventional, using existing technology. Nevertheless, there were substantial challenges “which derived from the building's massive size, extensive range of facilities, number of advanced electronic systems, tight program, shortage of resources, extensive approval process and quality standards”. 9 The site for the building covers 32 ha, and the building itself an area 300 m long by 300 m wide.

The Australian Government formed the Parliament House Construction Authority as the government body with overall responsibility to project manage the delivery of the project. The PHCA provided overall direction to the project, and was responsible to the Parliament and the Cabinet through the Minister for the Capital Territory. A Cabinet Committee and a Joint Standing Committee of Parliament provided the PHCA with user requirements.

The PHCA made an early decision that the project would have to be “fast tracked” by commencing construction before design was completed, in order to meet the opening date, set by Parliament. As a consequence of fast tracking, the construction was procured by construction management, in which a joint venture of John Holland and Concrete Constructions managed a large number of trade subcontracts. The architect was the Principal Consultant engaged by PHCA, and the engineering consultants (structural, mechanical, electrical etc.) were secondary consultants, technically responsible to the architect. The cost consultant (quantity surveyor) was directly responsible to PHCA, as was the Construction Manager.

PHCA explained its choice of procurement method as follows:

In simple terms, the task was to design and build the country's largest piece of public architecture, designed to last more than 200 years, to exceptional levels of quality and finish. … Time constraints meant that bold planning decisions were needed in the early stages to achieve this completion target. The most significant of these was the adoption of a fast track approach, which enabled construction to begin while planning was still in progress. The Parliament House Construction Authority (PHCA) believes that the building could not have been completed on time if traditional methods had been employed. 10

The original building budget of $151 m was prepared by the National Capital Development Commission (NCDC) based on a conceptual notional design with a usable floor area of 58,000 m2 and a gross area of 80,000 m2. The winning architectural design had a usable area of 69,057 m2, which the PHCA estimated added an additional $33 m to the budget. The PHCA also estimated that the winner's design involved an additional $36 m for underground car parking, circulation, plant rooms, site works, landscaping, energy-saving devices and increased standards and finishes that were not provided for in the competition brief budget. Significantly, not only did the winner's design include a larger usable area than provided for in the competition brief, but the efficiency factor (usable area divided by gross area) was 53.5%, considerably less than the 72.5% assumed by the NCDC in its conceptual design. After the winning design had been selected in 1980, the approved budget was revised from $151 m to $220 m in May 1978 prices, the basis on which the PHCA was required to report to the Parliament. The budget approved by Parliament contained neither contingencies, nor any provision for cost escalation arising from inflation. 11 As the PHCA noted: “The building budget for the new Parliament House was destined to be controversial because of misunderstandings of its base cost and the effects of additions, variations and other factors which were not part of the original calculation.” 12

15.3.2: Project performance

In the event, APH was opened in May 1988 (not 26 January as originally planned), and the actual final cost was $1,076 m. The Auditor General conducted an “Efficiency Audit” of the design and construction of APH in 1987 during...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex