Chapter 6: General contract negotiation issues
| Library | The Law and Practice of Complex Construction Projects |
| Pages | 65-74 |
| Author | Fabio Solimene |
The “scope of work” is the work that the parties agreed the contractor shall perform. It is an essential term of a construction contract as there may be no binding agreement if the scope of work is not agreed in sufficient detail. What is sufficient detail is a matter of interpretation.
For large projects, it would be impracticable for the parties to agree up to the last detail of the works. As a result, the parties are not expected to define the scope of work in a comprehensive way, 1 and the contract will usually not be held incomplete if the parties have left out the details on fixtures, fittings and finishes.
The courts will normally hold that a contractor’s scope of works includes any works which the parties obviously intended to form part of the contractor’s scope under the contract, even if not mentioned specifically in contract documents. In the case of
It is clearly to be inferred from the language of the specification that the plaintiff was to do the flooring, for he was to provide the whole of the material necessary for the completion of the work; and unless it can be supposed that a house is habitable without any flooring, it must be inferred that the flooring was to be supplied by him. In my opinion, the flooring of a house cannot be considered an extra any more than doors or windows.
Later cases likeIt is therefore crucial that contractors’ tenders clearly state what is included and what is excluded in the price they are offering.
Where a tender indicates that the price does not cover a certain part of the scope of work, where the tender is sufficiently clear on the point the courts may infer that such part of the works is within the contractor’s scope, but will be charged at an extra cost to the contract price unless the employer decides that it shall be performed by a third party or contract states explicitly or implicitly those works are excluded from the tender price. 4
The scope of work is a technical matter and is generally included in a schedule which forms part of the contract documents. The contractual clause relevant to the scope of work is sometimes referred to as “contractor’s obligations”. It will usually state that the contractor undertakes to the employer to carry out and complete the works in conformity with the provisions of the contract in consideration of the payment of the contract price.
By entering into a construction contract a contractor undertakes to do a certain work. Depending on the type of project and the agreement between the parties, this may include designing, manufacturing, supplying, constructing, transporting, installing, testing, commissioning the works, remedying any defects, etc. The fulfilment of such obligations is measured against the agreed scope of work and the technical specifications agreed in the contract.
A contractor is normally required to carry out its services with a certain standard of care. In general terms, the standard of care may be defined as the degree of care and caution which the party providing a certain service must exercise when undertaking such service. In other words, the standard of care sets a benchmark for the quality of the services provided by the contractor.
When considering construction projects, the standards of care are “reasonable skill and care” and “fitness for purpose”.
Under English law, unless the parties agree otherwise, the standard of care that a contractor must use is “reasonable skill and care” so that a contractor will not be in breach of its obligations if it can demonstrate that it acted with reasonable skill and care when undertaking its services.
What constitutes reasonable skill and care will be assessed applying the common law test for negligence which provides that a professional person is not negligent if he carries out his work to the same standard that another reasonably competent member of his profession would have met.
The test is the so-called Bolam test which was formulated in
Where you get a situation which involves the use of some special skill or competence, then the test as to whether there has been negligence or not is … the standard of the ordinary skilled man exercising and professing to have that special skill. A man need not possess the highest expert skill; … it is sufficient if he exercises the ordinary skill of an ordinary competent man exercising that particular art.
It is worth mentioning that in the 2015 medical case ofwhether in the circumstances of the particular case, a reasonable person in the patient’s position would be likely to attach significance to the risk, or the doctor is or should reasonably be aware that the particular patient would be likely to attach significance to it.
Where the construction contract does not include an express provision on the standard of care to be used by the contractor, a duty to act with reasonable skill and care may be implied by virtue of Section 13 of the Supply of Goods and Services Act 1982 which states that “
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting