CIS General Insurance Ltd v IBM United Kingdom Ltd

JurisdictionEngland & Wales
JudgeMrs Justice O'Farrell DBE,Mrs Justice O'Farrell
Judgment Date19 February 2021
Neutral Citation[2021] EWHC 347 (TCC)
CourtQueen's Bench Division (Technology and Construction Court)
Docket NumberCase No: HT-2018-000154
Date19 February 2021

[2021] EWHC 347 (TCC)

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT (QBD)

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

Mrs Justice O'Farrell DBE

Case No: HT-2018-000154

Between:
CIS General Insurance Limited
Claimant
and
IBM United Kingdom Limited
Defendant

Alex Charlton QC, Lawrence Akka QC & Michael Lazarus (instructed by Addleshaw Goddard LLP) for the Claimant

Nigel Tozzi QC, Matthew Lavy & Iain Munro (instructed by CMS Cameron McKenna Nabarro Olswang LLP) for the Defendant

Reading dates: 14 th, 15 th & 16 th January 2020

Hearing dates: 20 th 21 st, 22 nd, 23 rd, 27 th, 28 th, 29 th, 30 th January 2020

4

th, 5th, 6th, 10th, 11th, 12th, 13th, 17th, 18th, 19th, 20th, 24th, 25th, 26th, 27th February 2020

2

nd, 3rd, 4th, 5th, 9th, 10th, 11th, 12th, 19th March 2020

Closing submissions (in writing): 8 th, 9 th, 27 th and 28 th April 2020

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

Mrs Justice O'Farrell DBE

INDEX

1. Introduction

Para 1–25

2. Chronology

Background to the transformation programme

26–37

Tender Process

38–44

The IT solution proposed by IBM

45–50

Due Diligence

51–56

Interim Service Agreement

57–62

The MSA

63–93

Implementation tools

94–95

Agile methodology

96–100

Release 1

101–131

The turning point

132–139

Deterioration of the relationship between the parties

140–163

The AG 5invoice issue

164–175

Termination

176–185

3. The Dispute

Para 186–190

The Issues

191

Evidence

192–197

4. Issue 1—Termination

Para 198–200

The software license payments

201–216

AG5 Milestone

217–232

Milestone payment process

233–253

AG milestone dispute

254–265

Discussion and finding on the AG5 milestone

266–281

Contractual provisions re invoices

282–283

AG 5 invoice submission and rejection

284–299

Validity of invoice

300–316

Was the AG5 invoice disputed?

317–330

Set-off

331–358

Termination

359–364

Wilful Default

365–399

Summary of findings on termination

400

5. Issue 2—Breach of Warranty Claim

Para 401–402

Clause 12.1 (c) warranty

403–419

Pleaded case

420–422

Whether Insurer Suite was written for the US market

423–428

Extent to which Insurer Suite re-written or developed

429–454

Analysis of Insurer Suite Code

455–473

All reasonable steps

474–495

Consequences of any breach of warranty

496–499

Conclusion of the warranty claim

500

6. Issue 3—Reporting Claim on State of Insurer Suite

Para 501–503

Reporting obligations

504–508

Pleaded allegations

509–510

Insurer Suite as at the date of the MSA

510

Knowledge attributable to IBM

511–512

Cards on table meeting

513–526

Consequence if IBM reported difficulties

527–533

7. Issue 4—Delays and reporting failures

Para 534–536

IBM's obligations to achieve the Milestone Dates

537–553

Expert evidence in respect of delay

554–561

Milestone IMP-018c

562–602

Milestone IMP-021

603–638

Release 2 milestones

639–649

Reporting of delays

650–656

Conclusion on delay and reporting

657–661

8. Issue 5—Quantum

Para 662–664

Contractual exclusion or limitation of liability

665

Wasted expenditure claim

666–669

Legal principles

670–679

Discussion and finding on wasted costs claim

680–688

The Bond interest and transactional fees

689–695

Contractual caps

696–703

Quantum of wasted expenditure claim

704–727

Claim for delay and reporting failures

728–734

NOM Resource

735–738

COM Exit

739

Property Costs

740

Testing Resources from SQS and Test Direct

741

Sopra Steria data migration resource and architect resource

742

Experian and GSX

743

Accenture

744

Assurance by PwC and PA Consulting

745

IMP-018 Milestone

746

IBM additional work

747

Dual run resource

748

Bottomline Contract

749

Management expenses and secondees

750–751

IBM's counterclaim

752

Conclusions

753–754

Mrs Justice O'Farrell
1

This case concerns a claim for wasted costs and damages arising out of the termination of a contract for a new information technology system.

2

The claimant (“CISGIL”) was a wholly owned subsidiary of the Co-operative Group Limited (“the Co-op Group”). CISGIL's business is the underwriting and distribution of general insurance products. Its principal products are home insurance and motor insurance which it underwrites and sells to its members and customers through a variety of retail channels, including direct website and telephone sales, aggregators (comparison web sites) and third-party brokers.

3

In about 2014, there was a re-organisation within the Co-op Group. The life insurance division was divested and separation of the Co-op Bank was initiated. CISGIL's network infrastructure, data centre, hardware, software and applications were all shared with the Co-op Bank. They were cumbersome and outdated and, when the Coop Bank left the shared platform, the operation and maintenance costs would be unsustainable. CISGIL considered that access to a flexible and contemporary IT infrastructure would enable it to provide tailored services to its customers and to compete as a market-leading digital and data-based business. Therefore, CISGIL decided to purchase and implement a new IT solution for its business (“Project Cobalt”).

4

On 16 June 2015 CISGIL entered into a contract with the defendant (“IBM”) for the supply of a new IT system for CISGIL's insurance business and for management of the system for a term of ten years. The contract comprised a Master Services Agreement (“the MSA”), an Implementation Statement of Work (“the Implementation SOW”) and the Managed Service Statement of Work (“Managed Service SOW”).

5

The cost of supply and implementation of the new system was £50.2 million. The cost of the management services to be provided over a period of ten years from implementation of the system was estimated to be £125.6 million.

6

By a contract dated 16 June 2015 IBM engaged Innovation Group (“IG”) to supply software and services for the insurance platform solution required, using a proprietary software called “Insurer Suite”.

7

The MSA provided for IBM to deliver the new operating platform substantially before the longstop date of 31 December 2017, when CISGIL's insurance business would be separated from the Co-op Bank:

i) the contractual completion date for the home insurance platform (“Release 1 Go Live”) was 30 April 2016, subsequently extended to the end of May 2016 by way of a working agreement;

ii) the contractual completion date for the motor insurance platform (“Release 2 Go Live”) was 15 August 2016; and

iii) the contractual date by which all historic customer data would be transferred from the existing system to the new system was the end of October 2016.

8

Delays occurred to Project Cobalt. The contractual dates for Release 1 Go Live and Release 2 Go Live were not met.

9

In 2016 IBM exercised its audit rights against IG and in 2017 it exercised step-in rights against IG.

10

On 24 March 2017 IBM submitted an invoice in the sum of £2.9 million in respect of milestone Application Gate 5. IBM's position is that the AG5 milestone reflected payments due in respect of software licences and became payable in January 2017. CISGIL's position is that payment was not due because the AG5 milestone had not been achieved and CISGIL had not authorised payment or issued a purchase order for the same.

11

By email dated 27 March 2017 CISGIL refused to accept or pay IBM's invoice for the milestone payment.

12

On 12 May 2017 CISGIL gave notice that it intended to exercise rights of set off against any sums due in respect of the invoice.

13

On 22 June 2017 IBM served on CISGIL a final notice in respect of the invoice. CISGIL did not pay the invoice.

14

On 27 July 2017 IBM purported to exercise a contractual right of termination based on CISGIL's failure to pay the invoice for the AG5 milestone.

15

CISGIL disputed IBM's right to terminate, treated the purported termination as repudiatory breach and by letter dated 28 July 2017 purported to accept such repudiation.

16

CISGIL's primary claim is for damages of £128 million in respect of its wasted costs arising out of the alleged wrongful termination by IBM.

17

CISGIL has an alternative claim against IBM for breach of a contractual warranty. Its case is that IBM contractually warranted that it had taken all reasonable steps and satisfied itself as to all risk, contingencies and circumstances as to its performance of the MSA but the warranty was untrue. Insurer Suite was not a proven, commercial off-the-shelf product that was highly configurable and capable of meeting most of CISGIL's requirements with a minimum amount of customisation of the out-of-the-box (“OOTB”) product. IG did not have the resources to undertake the nature and extent of base development required. Damages in the sum of £70.4 million are claimed on the basis that CISGIL would not have entered into the MSA had it known that the warranty was untrue.

18

CISGIL has alternative claims against IBM arising out of the delays to the project. Its case is that a material factor in the late delivery of the platform was that Insurer Suite had been developed for use in the United...

To continue reading

Request your trial
2 cases
  • Soteria Insurance Ltd (formerly CIS General Insurance Ltd) v IBM United Kingdom Ltd
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 4 April 2022
    ...OF APPEAL (CIVIL DIVISION) ON APPEAL FROM BUSINESS AND PROPERTY COURT TECHNOLOGY AND CONSTRUCTION COURT (QBD) MRS JUSTICE O'FARRELL [2021] EWHC 347 (TCC) Royal Courts of Justice Strand, London, WC2A 2LL Bankim Thanki QC, Michael Lazarus & Laurentia de Bruyn (instructed by Addleshaw Goddard ......
  • Galtrade Ltd v BP Oil International Ltd
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 5 July 2021
    ...have been so generated. The Defendant also relied on the decision of O'Farrell J in CIS General Insurance Ltd v IBM United Kingdom Ltd [2021] EWHC 347, at 139 I will deal with this argument shortly because I believe it is misconceived: a. Starting with the clause 66.1, the term “ loss of an......
2 firm's commentaries
  • Singapore goes its own way on ‘no oral modification’ clauses
    • Singapore
    • JD Supra Singapore
    • 17 May 2021
    ...Teng Siang Charles v Hong Choon Hau [2020] SGHC 182. 4 See, for example, CIS General Insurance Limited v IBM United Kingdom Limited [2021] EWHC 347 (TCC), paragraph 310. 5 Construction and engineering contracts usually contain provisions relating to 'variations', which do not have the effec......
  • Contractual Damages And Exclusion Clauses: You Get What You Bargained For (CIS V IBM)
    • United Kingdom
    • Mondaq UK
    • 23 June 2021
    ...benefit, e.g. payments to the counterparty, third parties and internal costs). In CIS General Insurance Ltd v IBM United Kingdom Ltd [2021] EWHC 347 (TCC), O'Farrell J analysed the authorities on the two measures of contractual loss. She held that, although the two methods for quantifying l......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT