Chapter 13: Commissioning and start-up
| Library | The Application of Contracts in Developing Offshore Oil and Gas Projects |
| Pages | 158-163 |
| Author | Philip Loots,Donald Charrett |
Commissioning is the orderly sequence of testing, adjustment and bringing into operation of those subunits and units of the project, after the construction and installation work is finished. The term is most usually applied to dynamic plant, i.e. projects containing process, mechanical, electrical and instrumentation equipment and systems whose performance has to be proved under operating conditions. Commissioning is preceded by pre-commissioning: the tests conducted to verify that the construction and installation work has been carried out correctly, and that the equipment is safe to operate.
For relatively simple systems, the commissioning can be straightforward, often following standard procedures and documentation provided by suppliers or published by the appropriate technical authorities. The commissioning of such systems is usually carried out by the Contractor, followed by testing in the presence of the Owner’s representatives before the project is handed over for use.
The commissioning of a major project is, however, a complex and intricate series of start-up operations and may extend over many months. It often requires extensive planning and preparatory work, which commences long before the construction is complete. In such a situation, the Owner may simply be an observer to the commissioning phase or, depending on the contractual relationships, the Owner may take responsibility for it, with the Contractor in attendance. In any case, the Owner and project management should be involved in the planning and preparation for commissioning. Its complexity is often overlooked. Great flexibility is needed in the resourcing of commissioning operations in order to respond to changing circumstances as the work proceeds. In addition, the Owner should arrange training of operating staff sufficiently in advance for them to participate in commissioning and start-up. Provision should be made for the possibility of deliberate acts of sabotage by militant unions, which should not be discounted.
Whatever the contractual relationships, the commissioning of a major project involves a number of parties and needs active management. The management organisation for both pre-commissioning and commissioning should be agreed, and key personnel mobilised during the construction phase. The criteria that should be set for the commissioning organisation are:
-
a simple structure to suit the specialised nature of the work, i.e. avoiding multiple layers of management
-
single point responsibility for all commissioning activities with the appointment of a commissioning manager
-
formation of an integrated team, each member having clearly specified responsibilities, authority and resources, while respecting the contractual relationships between the parties involved
-
active involvement of the Owner in the commissioning of the facility.
Whether the project is complex or relatively simple, a number of preconditions for commissioning must be met. It should be recognised that commissioning is not simply an extension of construction, but a separate set of activities which...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting