Chapter 12: Construction

LibraryThe Application of Contracts in Developing Offshore Oil and Gas Projects
Pages142-157
AuthorPhilip Loots,Donald Charrett
12.1: Introduction

The construction phase is discussed in this chapter, taking as an example an unspecified medium-to-large project, in which several contractors may be engaged under separate contracts. Other situations would present different pictures; a management contract (EPCM), or indeed the common arrangement with a single contractor responsible for all construction and most of the procurement (EPC), are just two such examples. However, the differences between these situations relate only to how the work is managed; they are mainly in contract terms and in the assignment of responsibility for managing the integration of many items from many sources into a coherent whole. In one case the Owner’s project management team might be responsible for procurement and coordination; at the other extreme these functions might be the total responsibility of the Contractor, with the Owner’s team taking a monitoring role. In both cases the functions to be performed are similar.

The facility is built, generally in sections ( modules ), for ease of transportation. When the construction work has been completed to the required percentage, it is ready to for transportation to the field. At this point the Contractor is at its most powerful; it has the finished article. A structure or facility constructed onshore must be loaded onto a barge or ship and connected to the deck with sea fastenings (welded connections) to ensure that it can withstand the stresses imposed by the sea journey. After the sea fastenings have been completed the facility is ready for sailaway. The term sailaway literally means that a constructed facility sails away or is transported from its dock to the field. Transportation requires a “window” of good weather sufficient to allow for transit from the fabrication yard to the site and installation.

Installation means that the facilities, are placed in the required position at the field location by heavy lift vessels. Semi-submersible vessels may also be used to place the topsides onto the jacket by ballasting down when in position above the jacket. Hook-up refers to the work of connecting the subset of facilities and pipelines, and tying in the electrical system so that the facility is operational, but as yet, untested. Commissioning involves the testing of each system, cleaning the pipelines and producing hydrocarbons in small quantities to test the systems.

At the completion of commissioning, the Contractor will usually put in its Notice of Mechanical Completion, signifying that the construction activity has been completed. A series of inspections and the identification of any remaining work or any corrective work to be undertaken follows, before the Certificate of Mechanical Completion is issued by the Owner. Closeout means that the facility is in place, has been tested and production proper can commence. The construction is in effect at an end, and the guarantee period starts.

Most of the project budget is expended during the construction phase, certainly if equipment purchase is included. From the Owner’s point of view, 90% of the budget is committed once the contracts are placed; the cost control function now emphasises cost containment and reporting. Planning at all levels of the contracts and contracted work must be effective.

The Contracts should preferably have a clean start, with necessary design information and other documentation issued at the commencement where the Contract so requires. This contrasts with the fast track situation in which construction is overlapped with design. This frequent drive for shorter timescales and shorter payback periods has many pitfalls, not least the division or overlapping of responsibilities involving the Owner, designers and Contractors, and inadequate scoping of the work. The successful completion of a project on this basis is usually the product of joint planning, continual review, flexible contracts, and, above all, first-class cooperation.

Whatever the situation, a reviewer must know the way in which the construction was planned, and how it is being organised, controlled and documented.

12.2: Planning for construction

As the emphasis in the work of the project changes from design towards construction, so this change affects the project management organisation. 1 The task of managing the design is progressively reduced, and the construction management team has to be established. It is usual about this time for the Project Manager and some key staff to move to the site, because this is now the centre of the work.

Essential steps in planning for construction should be included in the project plan already prepared; these include the development of the procurement strategy, definition of construction work packages, draft contract documents, time schedules and cost plans. All this work has the aim of ensuring that Contracts are placed at the times required by the master programme, and that the construction is properly managed from then on.

These steps, together with other activities which are related to the site and are now required before mobilisation takes place, include the following tasks:

  • Prepare and agree the construction management organisation and appoint staff in key positions.

  • Prepare construction management procedures covering such aspects as planning and reporting, quality assurance and quality control, change control, documentation, and cost and invoice control.

  • Define policies and requirements for:

  • labour agreements and industrial relations

  • provision of construction plant

  • provision of site facilities, including labour accommodation, laydown areas, communications systems

  • site safety and health

  • Prepare the construction programme.

  • Finalise construction cost budgets, itemised by cost-centre and by contracts; show contingency and escalation allowances.

Modern contracts typically contain detailed requirements for the Contractor to implement formalised quality assurance procedures. Quality assurance (QA) is a formalised process of recording conformance with a documented set of procedures that specify the steps to be followed to achieve a quality product. It is not the same thing as quality control (QC), which comprises implementation of monitoring of the procedures required to achieve the required quality

Some of the above activities arise from the need to adopt certain common standards among the several independent Contractors working on the same site. These standards must be set by the Owner’s project team in order to achieve efficient and harmonious operation without unnecessarily limiting the Contractors’ freedom of action. 2 Defining these standards will enable each Contractor, when appointed, to be aware of the exact scope of its responsibilities for the work to be executed, which areas of the site are to be under its control, how coordination with other Contractors is to be affected and what common facilities are provided.

Arrangements for deployment and training of staff for the operation of the completed project works facility should also be settled, and the extent of the Contractors' involvement defined. Finally, any restrictions affecting the Contractors' possession of the site, or portions thereof, must be stated. Provisions for simultaneous operations must be made. Obviously, such matters are normally covered by the Contract conditions and are particularly significant if existing facilities are in operation at the site. Restrictions may also arise from the interest of, or agreements with, adjoining owners, and whether it is a 'green-fields' or brown-fields' site.

12.3: Change order procedure

The early stages of construction provide a fruitful source of delays, variations and potential contract claim situations that can arise in many ways. 3 Of great interest in a review of the construction phase are the procedures for dealing with approvals and potential variations, and the manner in which they are managed.

Some examples of the ways in which the best laid plans can go wrong are listed below; these are chosen mainly because they may affect both design and construction, and may have contractual consequences:

  • incomplete scope of work definitions

  • confusion around design philosophy: design life and service life 4

  • late request from the Owner for a design change

  • late request from the design office for a design change (this could happen especially, but not only, where overlap exists between design and construction)

  • omissions, mistakes or inconsistencies in the construction contract drawings or documents

  • unforeseen site conditions

  • access clashes

  • equipment offered by the Contractor that does not entirely meet the specification

  • equipment offered that does not fit in the space provided

  • changed method of construction

  • design change for safety reasons

  • relying on information incorrectly.

Project management should decide how the response to these issues should be organised, what action should be taken, and how it should be documented. Questions which a reviewer in any particular case should consider comprise the following:
  • Do adequate procedures exist for approvals, change control and reporting? Are they being implemented?

  • Do the contractual relationships assist or inhibit the above process?

  • Has responsibility been allocated for control, action and follow-up?

  • How are potential changes in design or construction identified and resolved?

  • How are the effects on time and cost taken into account?

12.4 Case Study: Interest – direct loss and expense – FG Minter v Welsh Health Technical Services Organisation (1980) 13 BLR 1

By clauses 11(6) and 24(1) respectively of the 1963 RIBA/JCT forms of contract, the Contractor was entitled to be paid ‘direct loss and expense’ not reimbursable under the preceding variation valuation rules, in the one case, or as a result of disturbance of progress due to late...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex