Chapter 5: Contract strategy

LibraryThe Application of Contracts in Developing Offshore Oil and Gas Projects
Pages53-67
AuthorPhilip Loots,Donald Charrett
5.1: Introduction

The contract strategy is the plan for the development of the facility. It drives all decisions regarding configuration and drives engineering and construction decisions throughout the project. It considers all stakeholders’ agendas as well as wider political, social and risk issues. The nature and structure of the Owner’s project management organisation and the Contracts entered into will also depend upon the contracting strategy chosen by the Owner.

Three important and interconnected factors in the Owner’s selection of contract strategy are its tolerance for risk, the resources available for project management, and the degree of control the Owner wishes to exercise.

At the outset, the Owner will have to consider:

  • Can the complete facility be contracted under a single EPC Contract?

  • Will the execution be segmented, based on a number of smaller (EPC) contracts, which need to be managed by the main Contractor?

The need to consider and decide upon a contract strategy prior to completion of the FEED phase cannot be over-emphasised. Different contract strategies will cause different impact to risk, time and cost
5.2: Specific issues for offshore for offshore construction contracts

These early decisions impact on the conditions of contract. Contractors for marine construction generally have less appetite for risk than contractors working onshore. This is because of the very high cost of maintaining the marine construction vessels (the spread ) on site, and the relative unpredictability of elements such as weather, subsea geotechnical conditions and the impact of delay on the forward commitment of the spread. In the case of force majeure , 1 a marine contractor may be compensated for time-related costs incurred as a result of downtime due to a cyclone, whereas this is less likely to apply to a contractor working onshore. Marine load-out dates for prefabricated modules are relatively inflexible due to the cost of and demand for specialised transport and construction vessels. It is extremely important that shore-based fabrication of marine facilities is completed on time. Heavy lift vessels ( HLVs) and special purpose transport vessels cannot be kept waiting.

Should shore based deliverables such as prefabricated modules be late, they may have to be shipped offshore in an incomplete state. Once the shore-based construction deliverables have been loaded out at sea, carrying out further construction work on them whether by way of change or finishing is extremely expensive and time-consuming. Considerably more manpower is required; accommodation (by way of flotel 2 or marine construction support vessel ( MCSV )) and other support services for the workforce may have to be provided with the resulting safety, industrial relations ( IR ), logistical, cost and planning risks and challenges. The transfer of personnel from accommodation facilities to their workplace at sea can be a very high risk. Safety is paramount.

5.3: EPC or EPCM Contract? 5.3.1: EPC

For many years the most desired way for an Owner to procure a major construction project, particularly one being project financed, was via a fixed price, lump sum turnkey route; the so-called engineering, procurement and construction contract (EPC Contract). The term lump sum turnkey typically refers to contracts where Contractor agrees to a fixed price contract in order to complete the works set out in the contract and hand over a completed facility to the Owner (hence, the allusion to turning over the keys). 3 It appears that the most desirable way for an Owner to procure a major construction project, particularly one being project financed, is still via a fixed price, lump sum EPC turnkey contract.

There is a common misconception that the EPC Contract is of necessity a lump sum contract. EPC is a contracting structure related to risk allocation and other project-specific factors unrelated to how the Contractor is to be compensated. It is therefore possible to have a cost-reimbursable, fixed fee, rates-based or other payment regime for an EPC Contract. By choosing a fixed price lump sum contract, funders and Owners expect to get the degree of certainty as to time and cost that they require. Too much reliance should however not be placed on this alone, nor on certainty of an award to the ‘lowest price’ bidder, as the lowest tendered price is not necessarily the best price. 4

Such has been the popularity of the EPC method of procurement that organisations such as FIDIC (International Federation of Consulting Engineers – Fédération Internationale des Ingénieurs-Conseils) responded to the need for appropriate standard forms that more closely reflected market conditions by the introduction of its Conditions of Contract for EPC/Turnkey Contracts (the Silver Book). 5 Orgalime (the European Engineering Industries Association) followed by publishing the Orgalime Turnkey Contract for Industrial Works (2003), and ICC (the International Chamber of Commerce) published the ICC Model Turnkey Contract for Major Projects (2007). Other organisations including ENAA (Engineering Advancement Association of Japan), 6 ICE (Institution of Civil Engineers), 7 and NEC (New Engineering Contract), 8 have also published standard form contracts that are typically used for infrastructure.

5.3.2: EPCM

By contrast, an EPCM Contract is a professional services contract which has a radically different risk allocation and different legal consequences. The key difference is that under an EPCM Contract, other parties are direct contractors to the Owner and construct the project. Under the EPCM model the Contractor does no building or construction – rather, it develops the design and manages the construction process on the Owner’s behalf. The EPCM Contractor is the construction manager, but not the builder/constructor, and will not accept liability for completion on time or budget. As such, the EPCM Contractor is usually responsible for the overall planning, design, site accommodation, procurement, environmental quarantine compliance and logistics for the project, but not for the performance of the project works.

There is no standard form of contract for this type of procurement, although Standards Australia have published AS4916–2002 Construction Management – General Conditions.

While there has been an increase in cost reimbursable contracts (usually with a target price pain/gain share mechanism built in), EPCM Contracts are increasingly the market response to major projects in the oil and gas and mining sectors and in the power and desalination sectors and for international mega-projects. This change of emphasis away from fixed price turnkey may reflect the bargaining position of many EPC Contractors in today’s market and, to some extent, intellectual property issues and the increasing size, risk and complexity of the projects being tendered internationally. No single contractor or combination of contractors is generally willing to contract for mega-projects on an EPC for a lump sum.

5.3.3: Patented process

Where a patented process is involved there may be the process supplier, which is usually an engineering company with proprietary technology. Its prime business is to provide the process engineering design or technology, which consists to a large extent of the chemistry or technology necessary to achieve the process which produces the product from the plant. Sometimes the process supplier may itself also be an EPC Contractor thereby capable of offering the single point of responsibility approach favoured by Owners and funders. Indeed, where the process supplier is not also the EPC Contractor, Owners will still endeavour to make the EPC Contractor responsible for the process, although few EPC Contractors will accept this responsibility. Where the process supplier is not also the EPC Contractor, there will be a separate EPC or EPCM Contractor, who is primarily responsible for the remainder of the engineering design and, in the case of an EPC Contract, the construction of the project. There are also the trades or Subcontractors and major vendors engaged either by the EPC Contractor directly or, in the case of an EPCM arrangement, directly by the Owner.

5.4: Stage 1: Front-end engineering and development FEED

When planning the project, the Owner and lenders need to consider which of the following potential options they wish to be available at the conclusion of Stage 1 FEED:

  1. If the FEED has been produced by an EPC Contractor willing and capable to develop the FEED into a detailed design and to build the project, the Owner may seek to continue the FEED Contract on the existing or similar terms and conditions and deliver the project at the agreed tender rates using the FEED Contractor -this may lead to some bidders having to form joint ventures or consortia to be able to carry out the whole of the work.

  2. More often, at the end of the FEED phase, the Owner may wish the FEED Contractor to deliver the project in the form of a lump sum EPC Contract. In order to ensure that the lump sum route is still available to the Owner at the end of the FEED stage, a mechanism may be built into the FEED Contract giving the Owner the option to convert the FEED Contract into a lump sum EPC Contract on completion of the FEED. However, the FEED Contractor often resists the imposition of such a mechanism since it knows that, on completion of the FEED, there may be no other EPC Contractor available, or capable, or willing to develop the FEED and build the project. In such circumstances, the FEED Contractor is in the most advantageous position either to be awarded the EPC Contract, (but at a negotiated price not dependent upon an agreed formula or mechanism), or simply to insist that it will only build the project on a cost reimbursable basis (which may, counterintuitively, not be detrimental to the Owner, provided...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex