Deerns UK Ltd v VDC LHR11 Ltd

JurisdictionEngland & Wales
CourtTechnology and Construction Court
JudgeMr Justice Eyre
Judgment Date23 June 2026
Neutral Citation[2026] EWHC 1509 (TCC)
Year2026
Docket NumberCase No: HT-2026-000123
Between:
Deerns UK Limited
Claimant
and
VDC LHR11 Limited
Defendant
Before:

Mr Justice Eyre

Case No: HT-2026-000123

IN THE HIGH COURT OF JUSTICE

KING'S BENCH DIVISION

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice,

Rolls Building

Fetter Lane, London, EC4A 1NL

Samuel Townend KC (instructed by Brabners LLP) for the Claimant

Justin Mort KC (instructed by CMS Cameron McKenna Nabarro Olswang LLP) for the Defendant

Hearing date: 5 th June 2026

Approved Judgment

This judgment was handed down remotely at 12:00 noon on 23 rd June 2026 by circulation to the parties or their representatives by e-mail and by release to the National Archives.

Mr Justice Eyre

Introduction .

1

By a consultancy agreement of 23 rd April 2025 (“the Contract”) the Defendant engaged the Claimant (“the Consultant”) to provide engineering consultancy services in relation to a development at Chandos Park Estate, London NW10.

2

In these proceedings the Claimant seeks payment of £910,501.71 plus VAT. It contends that this sum is due following the Defendant's failure to serve timely pay less notices in respect of two applications for payment. The Claimant says that the Contract, properly interpreted, failed to provide for a final date for payment as required by s110(1)(b) of the Housing Grants, Construction and Regeneration Act 1996 (“the HGCRA”). As a consequence, the relevant provisions of the Scheme for Construction Contracts (“the Scheme”) applied. The effect was, the Claimant says, that the final date for payment was 17 days after the relevant due date and any pay less notice had to be served not less than 5 days before that date. Although the Defendant served pay less notices in respect of the Claimant's applications they were after the dates provided for by the Scheme and so, the Claimant says, out of time.

3

The Defendant disputes the Claimant's interpretation of the Contract. It says that when the Contract is properly interpreted it is to be read as having provided a final date for payment which was compliant with the HGCRA. Accordingly, the contractual terms were not superseded by the provisions of the Scheme with the consequence that the Defendant's pay less notices were within time.

4

The Defendant supplements its argument as to the proper interpretation of the Contract with a number of further contentions which were a series of fall-back positions in the event that the court did not accept the Defendant's interpretation argument. First, it said that the parties' dealings had given rise to an estoppel by convention which had the effect that the Contract had been operated in a way which was compliant with the HGCRA and that the Claimant was estopped from contending that there was non-compliance. In that regard the Defendant also submitted that the assertion of an estoppel meant that the case was not suitable for determination by way of a Part 8 claim but should, instead, be adjourned (potentially after determination of the interpretation issue) for the estoppel issue to be decided after pleadings, disclosure, and the exchange of further evidence with provision for cross-examination. Next, the Defendant said that, even if the Contract did not comply with the HGCRA with the consequence that the Scheme was to apply, the Scheme was to be applied in such a way as to cause the minimum change to the terms agreed by the parties. It said that, when that was done, the effect would be that its pay less notices were to be regarded as having been served timeously. Finally, the Defendant said that there were serious doubts as to the Claimant's solvency and that these warranted a stay on the execution of any judgment in the Claimant's favour in the light of the potentially substantial claim which the Defendant had against the Claimant.

5

It follows that it will be necessary to consider:

i) The proper interpretation of the terms of the Contract.

ii) Whether the Contract provides a final date for payment meeting the requirements of the HGCRA.

iii) If not, whether an award in the Claimant's favour should await determination of the Defendant's estoppel argument following further particularisation and a further exchange of evidence.

iv) Whether, if the estoppel argument is addressed at this stage, the asserted estoppel is established and has the effect that the Contract is to be seen as compliant with the HGCRA.

v) How the Scheme is to be applied if it is applicable here.

vi) Whether execution of any judgment in favour of the Claimant should be stayed.

The Relevant Terms of the Contract .

6

Clause 7 of the Contract addressed the terms of payment. Sub-clauses 7.2 and 7.3 are of note for current purposes and, with original emphasis, provided that:

“7.2 The Fee shall (subject to VDC's rights of set-off and deduction) be payable in the instalments stated in Schedule 1 (the ‘ specified dates’). The application date for payment of each instalment shall be the specified date in Schedule 1 and the Consultant shall submit an invoice on or before the relevant application date. The due date for payment of each instalment shall be the specified date in Schedule 1. The Consultant's invoice shall state the amount the Consultant considers due to him as at the due date and the basis on which such amount has been calculated (the ‘ Notified Sum’) and shall be accompanied by such documents, receipts and vouchers as may reasonably be required by VDC. The final date for payment shall be 30 days after the relevant due date save that if the Consultant invoice is issued late, the final date for payment shall be postponed by the same number of days by which the Consultant's invoice is late.

7.3 If VDC intends to pay less than the Notified Sum, VDC shall not later than five days before the relevant final date for payment give notice to the Consultant of that intention (a ‘ Pay Less Notice’) specifying the amount VDC considers to be due to the Consultant at the date the notice is given and the basis on which that amount has been calculated. Where such notice is given, VDC shall pay the Consultant not less than the amount stated as due in that notice on or before the final date for payment. If no Pay Less Notice is given in respect of any invoice, VDC shall pay the Notified Sum on or before the final date for payment.”

7

At paragraphs 6 and 6.1, Schedule 1 said:

“6. The Fee shall be calculated on a time charge basis as follows, provided always that such charges are intended to be incurred as set out in the Calculation of Service Fee including Resource Schedule (Numbered Document 4) and any material deviations from such schedule shall be subject to clause 8.1 and only payable to the extent that additional fees are agreed under clause 8.1:

6.1 subject to paragraph 6 above, the number of hours worked by the Consultant shall be multiplied by the Hourly Rates, such hours to be worked during Business Hours.”

8

At paragraph 7 that schedule provided that:

“The Fee shall be paid by instalments as follows:

The Consultant shall submit its monthly invoices to VDC in accordance with the Schedule of Valuation Dates (Numbered Document 10). If Valuation Dates are not stated (or if the schedule of Valuation Dates has expired), the Consultant shall invoice the VDC at the end of each month for Services performed during that month.”

9

The Defendant placed considerable weight on the Schedule of Valuation Dates and I have appended that at Appendix 1.

10

The Contract uses the word “invoice” at different points. There is reference to the “Consultant's Invoice” at two points in clause 7.2 and it is the late issuing of that invoice which causes the final date for payment to be postponed. Then, paragraph 7 of Schedule 1 provides for the Consultant to submit monthly invoices in accordance with the Schedule of Valuation Date. Next, the heading of column F of the Schedule of Valuation Dates is “Consultant issues invoice to Employer”. That is to occur on the dates in that column which have been calculated as 2 days after issue of the Payment Notice by the Employer's Agent. The parties are agreed that the reference to the Consultant's Invoice in clause 7.2 is not a reference to the Column F invoice. Instead, it is to be read as a reference to the Column B payment application by the Consultant. That interpretation is clearly correct.

The Relevant Notices .

11

The sum claimed by the Claimant is the total of the amounts which it contends are due pursuant to applications for payment numbers 7 and 8. The relevant due dates for those were 4 th February 2026 and 6 th March 2026 respectively. The Claimant says that the effect of the application of Scheme was that the final dates for payment were 21 st February and 6 th March respectively, meaning that any pay less notices were to be served by 16 th February and 18 th March. The pay less notices were in fact served on 27 th February and 25 th March.

12

The chronology was helpfully set out in Mr Townend KC's written submissions for the Claimant thus:

The Applicable Law .

Application 7

Application 8

Application

28 th January (£943,587.77)

27 th February (£873,080.45)

Due Date

4 th February

6 th March

Payment notice issued by VDC

9 th February (£555,855.60)

11 th March (£354,616.11)

Pay Less Notice date (if Agreement amended by the Act)

16 th February

18 th March

Final Date for Payment (if Agreement amended by the Act)

21 st February

23 rd March

Pay Less Notice issued by VDC

27 th February

25 th March

Pay Less Notice date (if Agreement not amended by the Act)

1 st March

31 st March

Final Date for Payment (if Agreement not amended by the Act)

6 th March

5 th April

13

Section 109 of the HGCRA provides for a party to a construction contract to be entitled to instalments, stage payments, or periodic payments thus:

“(1) A party to a construction contract is...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
1 cases
  • Netomnia Ltd v MJ Quinn Integrated Services Ltd
    • United Kingdom
    • Technology and Construction Court
    • July 24, 2026
    ...fails. Clause 6.5.5 remained effective and the AFP failed to satisfy its requirements. Estoppel . 73 In Deerns UK Ltd v VDC LHR11 Ltd [2026] EWHC 1509 (TCC) at [64] and [65] I adopted the analysis by Akenhead and O'Farrell JJ of the requirements for an estoppel by convention in the followin......