Equitix Esi CHP (Wrexham) Ltd v Bester Generacion UK Ltd

JurisdictionEngland & Wales
JudgeMr Justice Coulson
Judgment Date08 February 2018
Neutral Citation[2018] EWHC 177 (TCC)
CourtQueen's Bench Division (Technology and Construction Court)
Docket NumberCase No: HT-2017-000373
Date08 February 2018
Between:
Equitix ESI CHP (Wrexham) Limited
Claimant
and
Bester Generacion UK Limited
Defendant

[2018] EWHC 177 (TCC)

Before:

THE HON Mr Justice Coulson

Case No: HT-2017-000373

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice

Rolls Building, Fetter Lane, London, EC4A 1NL

Mr Luke Wygas (instructed by CMS Cameron McKenna Nabarro Olswang LLP) for the Claimant

Mr Tom Owen (instructed by Decimus Fearon LLP) for the Defendant

Hearing date: 29 January 2018

Mr Justice Coulson

The Hon.

1

INTRODUCTION

1

Pursuant to a contract dated 29 April 2016, the claimant engaged the defendant to design and build the Wrexham Biomass Fired Energy Generating Plant (“the Project”). The claimant is a SPV created specifically for the Project. The defendant is a contractor specialising in renewable energies.

2

Initial progress on the Project was slow. On 23 February 2017, the claimant issued a notice of adjudication seeking a declaration that the defendant was not entitled to an extension of time. The adjudicator was Mr Michael Blackburne. By a decision dated 16 June 2017, he concluded that the defendant had no entitlement to an extension of time. On that basis, the defendant was therefore to blame for the delays which had accrued.

3

At midnight on 17 July 2017, the claimant terminated the contract. On 28 July, the claimant notified the defendant that it had elected not to continue with the Project.

4

On 16 August 2017, the claimant issued an Interim Account under the relevant clause of the contract dealing with the situation after termination, requiring the defendant to pay £11,592,733.67 by 5 September 2017. This amount was made up of around £8 million, which were the sums previously paid by the claimant to the defendant, and which the claimant now sought to be repaid; and about £3 million in respect of other claims.

5

There was a dispute about the validity of the claimant's termination and the basis/accuracy of the Interim Account. The claimant referred that dispute to adjudication by way of a notice dated 13 October 2017. Mr Blackburne was again appointed the adjudicator. By a decision dated 22 November 2017, he ordered that the defendant pay to the claimant the sum of £9,805,032.27, with a further sum of £4,948.45 per day by way of interest.

6

The claimant now seeks to enforce the adjudicator's second decision. That is resisted by the defendant on two grounds. The first is the contention that the contract included for works which were expressly excluded from the Housing Grants (Construction and Regeneration) Act 1996 (“the 1996 Act”) and that therefore the adjudicator had no jurisdiction to decide the second adjudication, so that his decision was invalid. The second ground relates to the first: it is whether the defendant properly reserved its right to argue the jurisdiction point and/or whether the defendant conferred ad hoc jurisdiction on the adjudicator. If the defendant is wrong to resist enforcement on both these grounds, there is a third issue relating to the stay of execution sought by the defendant. I am very grateful to both counsel for their faultless written and oral submissions.

2

THE CHRONOLOGY

7

There are two aspects of the contract to which reference should be made. The first concerns the provision that applied where the claimant elected not to continue with the Project after termination (clause 15.7), and the second concerns the adjudication (and related) provisions (clauses 20.4–20.7).

8

Clause 15.7 deals with the calculation of loss in circumstances where, following the claimant's termination of the contract, the claimant decides not to continue with the Project. It is prolix, but needs to be set out in full:

“15.7 Actual Net Loss

In circumstances where the Employer elects not to continue with the Works following termination of the Contract, the Employer shall prepare a net loss statement (and the Parties agree that the Employer may delay preparing such statement until all amounts to be comprised in such statement can be finally determined) which will calculate the amount of compensation and damages the Contractor shall pay to the Employer (the “ Net Loss Statement”). The amount shall be calculated as follows:

Actual Net Loss = F + G + H + I – J + K

F is the total amount of any monies previously paid to the Contractor by the Employer pursuant this Contract;

G is the amount calculated as ten percent (10%) per annum (pro rata for part thereof) on the full amount of the Contract Price from the date of signature of this Contract until the date that full and final payment is made under this Clause by way of compensation for the Employer's committed costs of capital;

H (subject to Clause 15.7A (Decommissioning on Termination) below), is the costs incurred by the Employer in decommissioning the Works (to the extent that the Employer undertakes any decommissioning Works in accordance with Clause 15.7A (Decommissioning on Termination));

I is the additional costs and expenses (if any) actually incurred by the Employer after the date of termination of this Contract in determining the Actual Net Loss;

J is the amounts previously paid to or recovered by the Employer on an interim basis pursuant to Clause 15.7(b); and

K is the amount of any liability of the Employer in respect of third party claims (including claims under the Lease, the Power Purchase Agreement Management Services Agreement, the Fuel Supply Agreement and the Project Development Agreement) arising from the termination of the Project;

in each case without double counting. Such Actual Net Loss shall become due for payment (the “ Due Date”) to or by the Employer from or to the Contractor upon the date of the Net Loss Statement setting out the Actual Net Loss and the Employer shall promptly provide the Contractor with such supporting breakdowns, calculations and documentation as the Contractor may reasonably require to satisfy itself as to the basis for such calculation. The final date for payment shall be twenty (20) days after the Due Date. If the Contractor wishes to dispute the amounts set out in the Net Loss Statement the Contractor shall give written notice to the Employer within ten (10) days of receipt of the Net Loss Statement and the matter shall be referred for determination pursuant to Clause 20.2 (Referral to Adjudication). The amount determined by the adjudicator as payable in relation to the Net Loss Statement shall be payable ten (10) days after such determination, Either Party shall be entitled to refer the matter for further determination pursuant to Clauses 20.5 (Notice of Dissatisfaction) and 20.7 (Courts).

(a) The Employer shall be entitled to certify an on account payment (the “ Interim Account”) calculated in accordance with Clause 15.7 (Actual Net Loss) Such Interim Account shall be calculated by the Employer within thirty (30) days of the date of termination of this Contract as follows:

Interim Account F + G + H + I + L

Where:

F, G, H and I are as specified in Clause 15.7(a) above; and

L is the forecast amount of any liability of the Employer in respect of third party claims (including claims under the Lease, the Power Purchase Agreement Management Services Agreement, the Fuel Supply Agreement and the Project Development Agreement) arising from the termination of the Project.

in each case without double counting. Such Interim Account shall become due for payment (the “ Due Date”) to or by the Employer from or to the Contractor upon the date of the Interim Account setting out the Actual Net Loss and the Employer shall promptly provide the Contractor with such supporting breakdowns, calculations and documentation as the Contractor may reasonably require to satisfy itself as to the basis for such calculation. The final date for payment shall be twenty (20) days after the Due Date. If the Contractor wishes to dispute the amounts set out in an Interim Account the Contractor shall give written notice to the Employer within ten (10) days of receipt of the Interim Account and the matter shall be referred for determination pursuant to Clauses 20.2 (Referral to Adjudication). The amount determined by the adjudicator as payable in relation to the Interim Account shall be payable ten (10) days after such determination. The decision of the adjudicator shall be final and binding for the purposes of the Interim Account and shall not be referable by either Party for further determination pursuant to Clauses 20.5 (Notice of Dissatisfaction) or 20.7 (Courts) or otherwise.

15.7A Decommissioning on Termination

In circumstances where Clause 15.5(b) (Compensation on Termination) applies, the Contractor shall fully decommission the Works at its own cost within a reasonable period following termination of this Contract and in any case in accordance with any obligations of the Employer in relation to timing of any such decommissioned Works. The Parties agree that if the Contractor fails to decommission the Works in accordance with this Contract the Employer may carry out the decommissioning work itself or by others at the Contractor's cost and the Contractor shall (pursuant to Clause 15.7 (Actual Net Loss) be liable to the Employer for the costs incurred by the Employer in decommissioning the Works.

15.7B Title to any decommissioned items shall pass to the Contractor only once the Contractor has fully and finally settled all liabilities due under this Contract.”

9

In short, the final accounting between the parties, in circumstances where the defendant's contract has been terminated and the Project has come to an end, is achieved by way of the Net Loss Statement. The contract gives no timeframe for the calculations and discussions necessary for the completion of the Net Loss Statement. But it makes plain an entitlement on the part of the...

To continue reading

Request your trial
10 cases
  • Gosvenor London Ltd v Aygun Aluminium UK Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 28 March 2018
    ...J (as he then was) after the hearing of 1 February 2018 in this case, namely Equitix ESI CHP (Wrexham) Ltd v Bester Generacion UK Ltd [2018] EWHC 177 (TCC), the same judge again considered the principles set down in Wimbledon. He stated at [62] that they were a summary that was not set in s......
  • Bexheat Ltd v Essex Services Group Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 19 April 2022
    ...this summary was not intended to be an inflexible list, referring to his judgment in Equitix ESI CHP (Wrexham) Ltd v Bestor UK Ltd [2018] EWHC 177 (TCC) at [62]: “It was, of course, not my intention that this summary should be set in stone. It was simply a summary of the main points establ......
  • Bresco Electrical Services Ltd ((in Liquidation)) v Michael J Lonsdale (Electrical) Ltd
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 24 January 2019
    ...as an effective objection to a claim for the enforcement of the relevant adjudication decision…” 90 Finally, in Equitix ESI CHP (Wrexham) Limited v Bestor Generacion UK Limited [2018] EWHC 177 (TCC), I referred to these cases and said: “ Allied P&L is important because the responding party......
  • Gosvenor London Ltd v Aygun Aluminium Uk Ltd
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 3 December 2018
    ...to in a number of subsequent cases, it was not intended to be an inflexible list. In Equitix ESI CHP (Wrexham) Ltd v Bestor UK Ltd [2018] EWHC 177 (TCC); [2018] BLR 281, I noted at paragraph 62: “It was, of course, not my intention that this summary should be set in stone. It was simply a ......
  • Request a trial to view additional results
3 firm's commentaries
  • Projects & Construction Law Update - March 2018
    • United Kingdom
    • Mondaq UK
    • 21 March 2018
    ...click here. The Construction Act power generation exemption - will it apply? Equitix ESI CHP (Wrexham) LTD v Bester Generacion UK LTD [2018] EWHC 177 (TCC) The question of whether or not a dispute can be adjudicated if it arises under a contract which includes works that do not come within ......
  • When Can A Party Seek A Stay Of An Adjudicator's Decision?
    • United Kingdom
    • Mondaq UK
    • 29 November 2018
    ...of the adjudication decision. Note: Around the same time the case of Equitix ESI CHP (Wrexham) Limited v Bester Generacion UK Limited [2018] EWHC 177 (TCC) also addressed the grounds for a stay of execution of an adjudicator's In that case the court also considered the principles in Wimbled......
  • Construction Case Law Update - Top 5 Adjudication Cases Of 2018 (Video)
    • United Kingdom
    • Mondaq UK
    • 27 March 2019
    ...will not be viewed lightly by the Courts and will be scrutinised closely. Equitix ESI CHP (Wrexham) Ltd v Bester Generacion UK Ltd [2018] EWHC 177 (TCC) Equitix engaged Bester to design and build the Wrexham Biomass Fired Energy Generating Plant. In a dispute referred to adjudication, the a......
3 books & journal articles
  • Statutory adjudication
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...v Cofely Engineering Services [2009] EWHC 1120 (TCC) at [51], per Coulson J; Equitix ESI CHP (Wrexham) Ltd v Bester Generacion UK Ltd [2018] EWHC 177 (TCC) at [37], per Coulson J. 350 Fastrack Contractors Ltd v Morrison Construction Ltd [2000] BLR 168 at 178–179 [32], per HHJ hornton QC; Gr......
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...(UK) Ltd v Whessoe-Volker Stevin Joint Venture [2010] BLr 415. See also Equitix ESI CHP (Wrexham) Ltd v Bester Generacion UK Ltd [2018] EWhC 177 (TCC) at [28]–[29], per Coulson J. adjudication under part II of the housing Grants, Construction and regeneration act 1996 (UK) is discussed in C......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...v Veolia Energy & Utility Services UK plc [2019] EWHC 593 (TCC) III.24.36 Equitix ESI CHP (Wrexham) Ltd v Bester Generacion UK Ltd [2018] EWHC 177 (TCC) II.6.83, III.24.60, III.24.64, III.24.141, III.24.142 Equuscorp Pty Ltd v Glengallan Investments Pty Ltd (2004) 218 CLR 471 I.2.56, I.2.16......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT