Gb Gas Holdings Ltd v Accenture

JurisdictionEngland & Wales
JudgeMr Justice Field
Judgment Date06 November 2009
Neutral Citation[2009] EWHC 2734 (Comm)
CourtQueen's Bench Division (Commercial Court)
Docket NumberCase No: 2008 Folio 397
Date06 November 2009

[2009] EWHC 2734 (Comm)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

COMMERCIAL COURT

The Law Courts Winchester

High Street

Winchester SO23 9EL

Before: Mr Justice Field

Case No: 2008 Folio 397

Between
GB Gas Holdings Limited
Claimant
(1) Accenture (UK) Limited
(2) Accenture SCA
(3) Accenture International Sarl
(4) Accenture Inc
Defendants

Jeffery Onions QC and Sonia Tolaney (instructed by Linklaters LLP) for the Claimant

Geoffrey Vos QC, Joe Smouha QC and Philippa Hopkins (instructed by Freshfields Bruckhaus Deringer LLP) for the Defendants

Hearing dates: 29, 30 June and 2, 6 and 7 July 2009

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

Mr Justice Field

Mr Justice Field:

Introduction

1

This is a trial of a number of preliminary issues arising out of proceedings brought by the Claimant (“Centrica”) for breach of an agreement dated 28 January 2002 (“the JPA”), as amended, under which the counterparty, Accenture plc, contracted to design, supply, install and maintain a new IT system (“the Jupiter System”), including an automated billing system based on pre-packaged SAP IS-U software.

2

Under the JPA, the Jupiter System was to be delivered in 5 software releases, the third of which (“Release 3”) was to be the billing system.

3

GB Gas Holdings Limited is a subsidiary of Centrica plc which was originally part of the British Gas Corporation. Through its subsidiary, British Gas Trading Limited, Centrica supplies gas and electricity to residential customers in England and Wales. In 2002, at the time of the execution of the JPA, Centrica plc supplied energy to 18.8 million customers (13.4 million gas accounts and 5.4 million electricity accounts) and each month was issuing approximately 5 million bills.

4

The first defendant (“Accenture”) became a party to the JPA by a novation dated 24 November 2003. Accenture carries on business as a global management consulting, technology services and outsourcing company. The other defendants are guarantors of Accenture.

5

The roll out of Release 3 was considerably delayed. There were disputes between the JPA parties over the functional and system performance of Releases 1 and 2 and there were concerns about: (i) the adequacy of the testing regime in respect of Release 3; (ii) the future development of Releases 4 and 5; and (iii) Accenture's cashflow problems. A settlement of these disputes was agreed on 29 June 2004, the formal terms of which were set out in Contract Change Note 165 (“CCN 165”) dated 19 July 2004.

6

Under CCN 165:

i) Centrica agreed to pay an additional £10 million to the overall amount payable to Accenture under the JPA (Clause 1.1).

ii) Accenture agreed to provide an additional 18,000 man days towards completion of Release 3 (Clause 1.5).

iii) Accenture agreed to a three to four month pilot of Release 3B with live users for which the parties were to agree a set of objective pilot acceptance criteria to identify any faults in relation to Release 3B during the pilot. It was also agreed that the relevant warranties under clause 15 of the JPA would not start to run until after completion of the pilot and the start of the migration of accounts from the old billing systems to the new one, rather than at the start of the pilot.

iv) Releases 4 and 5 were suspended.

7

On 21 December 2005, the parties agreed that the planned migration of 2 million customer accounts from existing billing systems to the new system should be conducted in two phases, comprising 1.25 million customer accounts at the end of December 2005 and 0.75 million customer accounts during February 2006. Between December 2005 and March 2006 4.5 million customer accounts were migrated to Release 3B.

The Warranty Provisions in the JPA and the Amended JPA

8

On 31 March 2006, the JPA was amended by the Jupiter Programme Contract Amendment No.1. The amended agreement is called hereafter “the Amended JPA”. The amendments that are especially relevant to this trial are those to the warranty provisions contained in Clause 15 of the JPA. The drafting technique in the original Clause 15 was to set out what was warranted and then to provide what was to happen in the case of a breach of a warranty depending on whether the breach involved a “Fundamental Defect” (as defined) or a “Material Defect” (as defined). To that end, Clauses 15.2, 15.3 and 15.4.1 – 15.4.6 of the JPA provided:

15.2

Release Warranties

15.2.1 Subject as provided below Accenture warrants to Centrica that

(i) for the duration of the Initial Warranty Period:

(a) each Release will comply in all material respects with its Statement of Release Requirements separately and when combined with the previously delivered Releases; and

(b) completion of each Release will not materially adversely affect functionality achieved in any previously delivered Releases;

(ii) in respect of the Release(s) which implement the Billing System (currently planned to be Release 3), for the duration of the Full Warranty Period:

(a) each Release will comply in all material respects with its Statement of Release Requirements separately and when combined with the previously delivered Releases; and

(c) completion of each Release will not materially adversely affect the functionality achieved in any previously delivered Releases.

and in respect of this Clause 15.2.1(ii) only with regard to any functionality, processes, End User or data volumes which do not occur or are not used, operated or introduced during the Initial Warranty Period

15.2.2 Without limiting Clause 15.2.1, for the relevant Warranty Period:

(i) a Release will be free from material design and material programming and material implementation errors; and

(ii) a Release will meet in all material respects the Statement of Release Requirements to give Centrica the capability to achieve competitive advantage and the System will be capable of providing the Benefits.

15.3 Warranty Process

The Parties shall agree, prior to 31 July 2002 or (if earlier) the Acceptance Date for Release 1, a process for the notification and rectification of claims under Clauses 15.1.1, 15.2.1 and 15.2.2 including processes for (i) the categorisation of such warranty claims as being within the scope of Clauses 15.1.1, 15.2. 1 or 15.2.2 (ii) the prioritisation of and tracking of such claims, and (iii) acceptance by Centrica of rectifications and/or work arounds delivered by Accenture and if the Parties fail to agree such a process within a reasonable time, the matter shall be referred to the Dispute Resolution Procedure.

15.4 Level of Effort

15.4.1 Accenture will fix Material Defects and Fundamental Defects to the level of effort set out in this Clause 15.4 during the relevant Warranty Period.

15.4.2 Material Defects

Upon being notified by Centrica of a Material Defect Accenture shall promptly take all steps reasonably necessary to correct the Material Defect breach provided always that for the avoidance of doubt in no event shall the cost spent on fixing (being calculated on either the Time and Materials Basis or the Maintenance Daily Rate, whichever is relevant to the appropriate personnel being used) exceed the cap on liability set out in Clause 16. This shall constitute Accenture's entire liability and Centrica's sole and exclusive remedy for a Material Defect. For the avoidance of doubt, the only situation in which Centrica shall have a claim for damages for a Material Defect shall be if Accenture does not promptly take all steps reasonably necessary to correct the breach, and nothing in this Clause 15.4.2 shall remove Centrica's right to terminate this Agreement in accordance with its terms.

15.4.3 Fundamental Defects

Upon being notified by Centrica of a Fundamental Defect Accenture shall do what a commercial, reasonable and prudent organisation using the System to carry on its business would do when acting in its own best interests (having due regard to the costs necessary and benefits likely from correcting the Fundamental Defect) provided always that in no event shall the cost spent on fixing (being calculated on either the Time and Materials Basis or the Maintenance Daily Rate, whichever is relevant to the appropriate personnel being used) exceed the cap on liability set out in Clause 16. This shall constitute Accenture's entire liability and Centrica's sole and exclusive remedy for a Fundamental Defect. For the avoidance of doubt, the only situation in which Centrica shall have a claim for damages for a Fundamental Defect shall be if Accenture does not promptly use the endeavours set out in this Clause 15.4.3 to correct the breach and nothing in this Clause 15.4.3 shall remove Centrica's right to terminate this Agreement in accordance with its terms.

15.4.4 Reduction in Cap

The effort expended by Accenture in meeting its obligations under this Clause 15 will be calculated on either the Time and Materials Basis or the Maintenance Daily rate, whichever is relevant to the appropriate personnel being used, and will be treated as liability of Accenture and will count towards and reduce the aggregate liability cap set out in Clause 16. Accenture shall agree an action plan for fixing particular breaches of warranties with Centrica, implement such plan and keep Centrica informed as to the amount of money spent.

15.4.5 Data and Documentation

Notwithstanding Accenture's obligations under Clauses 15.1.1, 15.2.1 and 15.2.2 in relation to defects under Clause 5 (Data Audit, Cleansing, Matching, Conversion and Migration) Accenture will only be obliged to fix errors and to remedy the causes and consequences of such errors and then only errors notified during the Initial Warranty Period. In relation to Documentation defects shall be dealt with in accordance with Clause...

To continue reading

Request your trial
3 cases
  • Gb Gas Holdings Ltd v Accenture
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 30 Julio 2010
    ...EWCA Civ 912 [2009] EWHC 2734 (Comm)" class="content__heading content__heading--depth1"> [2010] EWCA Civ 912 [2009] EWHC 2734 (Comm) IN THE HIGH COURT OF JUSTICE COURT OF APPEAL (CIVIL DIVISION) ON APPEAL FROM THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION COMMERCIAL COURT Before: The Rig......
  • Scottish Power Uk Plc v BP Exploration Operating Company Ltd and Others
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 25 Septiembre 2015
    ...Lloyd's Rep 277, para 55. I do not regard this observation as affecting the analysis. The same applies to the obiterdicta in GB Gas Holdings Ltd v Accenture (UK) Ltd [2009] EWHC 2734 (Comm) at para 91 (Field J), and on appeal at [2010] EWCA Civ 912, para 69 (Longmore LJ), to which counsel ......
  • GB Gas Holdings Ltd v Accenture (UK) Ltd & 3 Others
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 23 Noviembre 2009
    ...as authentic. Mr Justice Field 1 This judgement follows on from the judgement already delivered in these proceedings reported at [2009] EWHC 2734 (Comm) ("the first judgement") and should be read in conjunction therewith. 2 In addition to the issues determined in the first judgement, Burto......
1 firm's commentaries
  • Allocating Risk In IT Contracts
    • United Kingdom
    • Mondaq United Kingdom
    • 28 Junio 2011
    ...Watford Electronics Ltd v Sanderson CFL Ltd [2001] All ER (Comm) 696 GB Gas Holdings Limited v Accenture (UK) Limited and others, [2009] EWHC 2734 (Comm) Hadley v Baxendale (1854) 9 Exch 341 BSkyB Limited and another v HP Enterprise Services UK Limited (formerly Electronic Data Systems Limi......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT