GPP Big Field LLP v Solar EPC Solutions SL (formerly known as Prosolia Siglio XXI)

JurisdictionEngland & Wales
JudgeMr Salter
Judgment Date07 November 2018
Neutral Citation[2018] EWHC 2866 (Comm)
CourtQueen's Bench Division (Commercial Court)
Docket NumberClaim No LM-2016-000101
Date07 November 2018

[2018] EWHC 2866 (Comm)

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

LONDON CIRCUIT COMMERCIAL COURT (QBD)

Royal Courts of Justice. Rolls Building

Fetter Lane, London, EC4A 1NL

Before:

Mr Richard Salter QC

Sitting as a Deputy Judge of the High Court

Claim No LM-2016-000101

Between:
(1) GPP Big Field LLP
(2) GPP Langstone LLP
Claimants
and
Solar EPC Solutions SL (formerly known as Prosolia Siglio XXI)
Defendant

Mr Matthew Parker and Ms Pia Dutton (instructed by NewLawsLegal) appeared for the Claimants

Mr Richard Walford (instructed by James Burkett Solicitor) appeared for the Defendant

Hearing dates: 11, 12, 13, 14, 18, 25, 26 June 2018

Judgment Approved

Contents

(1) Introduction

5

(2) Background

6

(2.1) The parties

6

(2.2) The people involved

7

(2.3) The witnesses

7

(2.4) The tariffs

9

(2.5) The insolvency of the Contractor

11

(3) The Hamptworth contract

11

(3.1) The claims, the defences and the counterclaim

11

(3.2) The claim under clause 21.5

14

(3.2.1) The relevant provisions of the Hamptworth contract

14

(3.2.2) Is clause 21.5 an unenforceable penalty?

24

(3.2.3) Was any part of the relevant delay caused by force majeure?

28

(3.2.4) Conclusion

39

(3.3) Actual loss

39

(3.4) Guarantee defences

41

(3.4.1) The terms of the guarantee

41

(3.4.2) Is clause 6.2 a guarantee or indemnity?

42

(3.4.3) Does the doctrine of “unusual features” and/or the rule in Holme v Brunskill apply to contracts of indemnity

44

(3.4.4) Unusual features

52

(3.4.5) Discharge by variation

55

(3.5) Counterclaim

58

(4) The Beaford Brook contract

61

(4.1) The claims, the defences and the counterclaim

61

(4.2) The claim under clause 21.5

62

(4.2.1) Is clause 21.5 an unenforceable penalty?

62

(4.2.2) Was the project delivered on time?

62

(4.2.3) Has the second claimant waived its right to claim Delay Damages?

64

(4.2.4) Conclusion

67

(4.3) Actual Loss

67

(4.4) SDLT

69

(4.4) Counterclaim

69

(5) The Rookery Farm contract

70

(5.1) The claims, the defences and the counterclaim

70

(5.2) The claim under clause 21.5

71

(5.2.1) Is clause 21.5 an unenforceable penalty?

71

(5.2.2) Has the second claimant waived its right to claim Delay Damages?

71

(5.2.3) Conclusion

72

(5.3) Actual loss

72

(5.4) The claim in relation to the ROCs

73

(5.4.1) The ROCs obligation

73

(5.4.2) The claim

73

(5.4.3) Clause 28.1

75

(5.4.4) The overlap with clause 21.5

81

(5.4.5) Conclusion

83

(5.5) SDLT and cost to complete

83

(5.6) Counterclaim

83

(6) The Bidwell contract

84

(6.1) The claims, the defences and the counterclaim

84

(6.2) The claim under clause 21.5

86

(6.2.1) Is clause 21.5 an unenforceable penalty?

86

(6.2.2) The correct period

86

(6.2.3) Conclusion

91

(6.3) Actual loss

91

(6.4) The claim in relation to the ROCs

91

(6.5) SDLT

93

(6.6) Costs to complete

93

(6.6.1) The claim and the defences

93

(6.6.2) The second claimant's loss results from its own breach of contract

96

(6.6.3) Was an agreement reached in August 2014?

98

(6.6.4) Were lower prices available

98

(6.6.5) Power inverters (Item 1)

99

(6.6.6) Fencing (Item 2) and the security system (Item 6)

100

(6.6.7) Switchgear (Item 3)

103

(6.6.8) Planting (Item 7)

104

(6.6.9) Rent (Item 8)

105

(6.6.10) Project management

106

(6.6.11) Conclusions

106

(6.7) Counterclaim

107

(7) The Lower Marsh Farm contract

109

(7.1) The contract

109

(7.2) The relevant dates

109

(7.3) The claim and set off

110

(7.4) Decisions

111

(7.3.1) The amount of the counterclaim

111

(7.3.2) Delay Damages

111

(7.3.2) Responsibility for the Contractor's failure to complete the work

111

(7.3.3) Security Guards and CCTV

112

(7.3.4) Planting

113

(7.3.5) Electrical works etc

113

(7.3.6) Conclusion as to set off

113

(8) Overall conclusions

114

(8.1) The 5 EPC contracts

114

(8.1.1) Hamptworth

114

(8.1.2) Beaford Brook

114

(8.1.3) Rookery Farm

114

(8.1.4) Bidwell

114

(8.1.5) Lower Marsh Farm

115

(8.2) Solar's liability

115

(8.3) The final accounting

115

(8.3.1) The first claimant

115

(8.3.2) The second claimant

115

(8.4) Judgment

116

Mr Salter QC:

(1) Introduction

1

The disputes which have given rise to this action concern five Engineering, Procurement and Construction (“EPC”) contracts relating to solar power generation plants in the United Kingdom. Those EPC contracts were made between one or other of the claimants (“GPP”) as employer, and Prosolia UK Ltd (“the Contractor”) as contractor. The Contractor is now insolvent. The defendant in this action (“Solar”) was the parent company of the Contractor, and is sued as guarantor and/or indemnifier of the Contractor's obligations under four of the EPC contracts. The claim, in broad terms, is for damages (both liquidated and unliquidated) for late and/or non-completion of the works required by those four EPC contracts. Solar, in turn, counterclaims against GPP (under an assignment from the administrator of the Contractor) for the balance of the sums which it asserts remain due under all five of the EPC contracts.

2

The five EPC contracts with which this action is concerned are as follows:

2.1 The “Hamptworth” contract dated 14 May 2012 between the first claimant and the Contractor, for the construction of a solar plant at Big Field, Hamptworth Estate, Salisbury SP5 2DS for a total price of £7,849,161.

2.2 The “Beaford Brook” contract dated 7 February 2013 (as amended by a deed of variation dated 2 October 2013) between the second claimant and the Contractor, for the construction of a solar plant at Upcott Barton, Beaford, Winkleigh, Devon for a total price of £5,925,607.49.

2.3 The “Rookery Farm” contract dated 1 March 2013 (as amended by deeds of variation dated December 2013 and 11 March 2014) between the second claimant and the Contractor, for the construction of a solar plant at Kimbolton Road, Stow Longa, Huntingdon PE28 0TR for a total price of £6,644,954.

2.4 The “Lower Marsh Farm” contract dated 9 August 2013 between the second claimant and the Contractor, for the construction of a solar plant at Kingston St Mary, Somerset for a total price of £6,258,364.

2.5 The “Bidwell” contract dated 11 October 2013 between the second claimant and the Contractor, for the construction of a solar plant at South Downs, Dartington, Totnes, Devon for a total price of £5,492,180.72.

3

GPP was represented at trial by Mr Matthew Parker and Ms Pia Dutton. Solar was represented by Mr Richard Walford. I am grateful to all of the advocates, and to the teams behind them, for the clarity and economy with which they have presented their cases.

(2) Background

4

Although the claims, defences, and counterclaims in relation to these five EPC contracts involve a number of common legal issues, each has its own particular facts, and the terms of each contract, although often materially the same, are not always identical in all respects. It is therefore necessary for me to take each contract in turn, and to consider the claims, defences, and counterclaims in relation to each of them separately, referring back where a decision that I have reached in relation to one contract also decides a similar issue in relation to another. Before I do that, however, it may be helpful for me to set out some of the common background to these disputes.

(2.1) The parties

5

The claimants are special purpose limited liability partnerships incorporated in England. The first claimant is owned by two Danish kommanditselskab (usually abbreviated as “K/S”), Green Power Partners K/S (“GPP K/S”) and Solar Rooftops III K/S. (The K/S is the Danish equivalent of the English limited liability partnership.) The second claimant is owned by GPP II UK K/S and Green Power Partners II K/S. These Danish entities are all investment vehicles for funds managed by Mr Lars Christian Gaarn-Larsen.

6

Solar (formerly known as Prosolia Siglo XXI Sociedad Limitada Unipersonal) is a Spanish company which is the parent company of a group specialising in the construction of solar power plants. From about 2009, Solar's group had collaborated with the funds managed by Mr Gaarn-Larsen on solar projects in Spain and elsewhere in continental Europe. In about 2011, seeing an opportunity created by the favourable renewable energy tariffs in the United Kingdom, Solar and Mr Gaarn-Larsen decided to work together on a number of projects in the United Kingdom.

7

For that purpose, the Contractor was incorporated on 20 July 2011. The first director of the Contractor was Mr Francisco Garcia Hernandez (known as “Paco”, but to whom I shall refer as “Mr Garcia”). It was Mr Garcia, in particular, who was responsible for seeking out and identifying the opportunity to construct a solar power plant at a particular site. In doing so he was acting on behalf of the Contractor and on behalf of another company associated with Solar, Comprasolar UK Limited (“Comprasolar”), of which he was also the only director. In each case, Mr Garcia (or someone working under him) was the person who initially secured a lease or other rights over the land and any necessary planning permissions, before the projects were sold to Mr Gaarn-Larsen's funds. Indeed, in relation to the Hamptworth project, the first claimant itself was originally set up, owned and run by the Contractor and Comprasolar. The Contractor and Comprasolar then sold the first claimant to Mr Gaarn-Larsen's funds on 14 May 2012, at the same time as the first claimant, the Contractor and...

To continue reading

Request your trial
6 cases
  • Triple Point Technology, Inc. v PTT Public Company Ltd
    • United Kingdom
    • Supreme Court
    • July 16, 2021
    ...second contractor achieves completion: the Hall case [2010] EWHC 586 (TCC); the Crestdream case (2013) HCCT 32/2013; the GPP case [2018] EWHC 2866 (Comm).” 29 Sir Rupert Jackson rejected the argument that the principle in Glanzstoff could be confined to cases where the contract was termin......
  • Strategic Advantage SPC (for and on behalf of HSG Rooftops SP) v High Street Rooftop Holdings Ltd
    • United Kingdom
    • Chancery Division
    • September 30, 2020
    ...agreement. Such non-waiver terms are enforceable and effective: see GPP Big Field LLP, GPP Langstone LLP v Solar EPC Solutions SL [2018] EWHC 2866 (Comm) per Mr Richard Salter QC at [203.3]. It is not therefore open to the Company to argue that any failure or delay by the Applicant to take......
  • Brown-Forman Beverages Europe, Ltd v Bacardi UK Ltd
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • May 19, 2021
    ...by Mr Richard Salter QC sitting as a deputy judge of the High Court in GPP Big Field LLP and another v Solar EPC Solutions SL [2018] EWHC 2866 (Comm) at paragraph 34 I now turn to the critical question, which is whether on its proper construction paragraph 5 applies in the circumstances of......
  • Triple Point Technology, Inc. v PTT Public Company Ltd
    • United Kingdom
    • Court of Appeal (Civil Division)
    • March 5, 2019
    ...and, very recently, by Mr Richard Salter QC sitting as a deputy High Court judge in GPP Big Field LLP v Solar EPC Solutions SL [2018] EWHC 2866 (Comm). 101 Bluewater Energy Services BV v Mercon Steel Structures BV [2014] EWHC 2132 (TCC) is a complex case, which does not lend itself to pit......
  • Request a trial to view additional results
11 firm's commentaries
  • Liquidated Damages And Unfinished Works
    • United Kingdom
    • Mondaq UK
    • September 23, 2019
    ...[2010] EWHC 586 (TCC); Crestdream Ltd v Potter Interior Design Ltd (2013) HCCT 32/2013; GPP Big Field llp v Solar EPC Solutions SL [2018] EWHC 2866 (Comm). Sir Rupert stated that the textbooks treat the second category as the orthodox. He expressed his doubts about the cases in the third ca......
  • The Supreme Court Favours "Orthodox Approach" To Liquidated Damages Clauses: Triple Point Technology, Inc v PTT Public Company Ltd ' Court Of Appeal Overturned
    • United States
    • Mondaq United States
    • July 23, 2021
    ...second contractor achieves completion: the Hall case [2010] EWHC 586 (TCC); the Crestdream case (2013) HCCT 32/2013; the GPP case [2018] EWHC 2866 (Comm)." The Supreme Court having rejected the application of Glanzstoff and making clear that it was not authority for any legal principle (in ......
  • Projects & Construction Law Update - Janary 2019
    • United Kingdom
    • Mondaq UK
    • January 14, 2019
    ...judgment here. Penalty doctrine considered in solar EPC case (1) GPP BIG FIELD LLP (2) GPP LANGSTONE LLP v SOLAR EPC SOLUTIONS SL [2018] EWHC 2866 (Comm) In this case, two of the main issues in dispute were the applicability of the force majeure provisions and the enforceability of the liqu......
  • Liquidated Damages On Work Never Completed
    • Hong Kong
    • Mondaq Hong Kong
    • May 2, 2019
    ...reward the contractor for its own default, a stance adopted by the Commercial Court in GPP Big Field LLP v Solar EPC Solutions SL [2018] EWHC 2866 (Comm). In the present case, the clause specifically referred to liquidated damages accruing "up to the date PTT accepts such work". The Court o......
  • Request a trial to view additional results
5 books & journal articles
  • Security for performance
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • April 13, 2020
    ...[2016] EWhC 166 (TCC) at [23], per Edwards- Stuart J), nor in respect of an indemnity ( GPP Big Field LLP v Solar EPC Solutions SL [2018] EWhC 2866 (Comm) at [131]–[147], per DhCJ richard Salter QC). 94 Compare Mercers v New Hampshire Insurance Co Ltd (1992) 60 BLr 26 at 50, where Scott LJ ......
  • Damages
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • April 13, 2020
    ...Ltd v China National Chartering Co Ltd [2017] UKSC 35 at [98], per Lord Sumption JSC; GPP Big Field LLP v Solar EPC Solutions SL [2018] EWHC 2866 (Comm) at [349], per DHCJ Richard Salter QC. See also Collings Construction Co Pty Ltd v ACCC (1998) 143 FLR 308 at 328, per Cole JA [NSWCA]; Sta......
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • April 13, 2020
    ...chan J; Glen Water Ltd v Northern Ireland Water Ltd [2017] niQB 20 at [64], per Keegan J; GPP Big Field LLP v Solar EPC Solutions SL [2018] eWHc 2866 (comm) at [102]–[105], per dHcJ richard Salter Qc; Maeda Kensetsu Kogyo Kabushiki Kaisha v Bauer Hong Kong [2019] HKcFi 916 at [7]–[33] per m......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • April 13, 2020
    ...I.2.57, I.2.139 GPN Ltd v O2 (UK) Ltd [2004] EWHC 2494 (TCC) I.2.127, I.2.130, I.5.22 GPP Big Field LLP v Solar EPC Solutions SL [2018] EWHC 2866 (Comm) II.6.327, II.11.163, II.12.26, II.13.86, II.13.134, II.13.146, II.13.150, II.13.179 GPS Marine Contractors Ltd v Ringway Infrastructure Se......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT