Grove Developments Ltd v S&T(UK) Ltd
| Jurisdiction | England & Wales |
| Court | Queen's Bench Division (Technology and Construction Court) |
| Judge | Mr Justice Coulson |
| Judgment Date | 27 February 2018 |
| Neutral Citation | [2018] EWHC 123 (TCC) |
| Docket Number | Case Nos: HT-2017-000336 |
| Date | 27 February 2018 |
The Hon Mr Justice Coulson
Case Nos: HT-2017-000336
HT-2017-000381
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Royal Courts of Justice
Rolls Building, Fetter Lane, London, EC4A 1NL
Mr Alexander Nissen QC (instructed by Macfarlanes LLP) for the Claimant
Mr Anthony Speaight QC and Mr Matthew Thorne (instructed by Trowers and Hamlins LLP) for the Defendant
Hearing dates: 19 and 25 January 2018
Judgment Approved
The Hon.
INTRODUCTION
By a construction contract dated 26 March 2015, the claimant (“Grove”) engaged the defendant (“S&T”) to design and build a new Premier Inn Hotel at Heathrow Terminal 4. The hotel was to include 613 bedrooms and a pedestrian link bridge. The contract sum was £26,393,730.04. The contract incorporated the JCT Design and Build Contract 2011. The contractual completion date was 10 October 2016. Practical completion was not achieved until 24 March 2017.
Since then, there have been three adjudications between the parties: the first decided that the Schedule of Amendments was part of the contract; the second adjudication decided that S&T were not entitled to a full extension of time, but were entitled to an extension of time down to 9 January 2017; and the third adjudication decided that Grove's Pay Less Notice of 18 April 2017 was invalid. This last decision meant that, on the face of it, S&T were entitled to be paid in excess of £14 million pursuant to their interim application no. 22. Grove had already anticipated a potentially adverse result in the third adjudication by the issue of their CPR Part 8 proceedings.
Between them, those Part 8 proceedings, together with S&T's counterclaim and S&T's separate enforcement action in respect of the decision in the third adjudication, raise four issues for the court's determination:
(a) Issue A: whether or not Grove's Pay Less Notice complied with the requirements of the contract;
(b) Issue B: whether, even if the Pay Less Notice did comply with the contract, the result in the third adjudication in S&T's favour should still be enforced;
(c) Issue C: whether in principle, at this stage, Grove is entitled to commence a separate adjudication seeking a decision as to the ‘true’ value of interim application 22;
(d) Issue D: whether Grove's notices in respect of liquidated damages were properly issued. This is a separate and discrete issue from the previous three.
I deal with those issues in this way. In Section 2 I set out the relevant contract terms. In Section 3 I identify the relevant events. In Sections 4, 5, 6 and 7 I deal in detail with each of Issues A-D in turn. I am aware that Section 6, which deals with Issue C (whether an employer has the right to adjudicate the ‘true’ value of an interim application, in circumstances where their payment notice and/or pay less notice is deficient or non-existent) will be of particular interest to the construction industry, so I make no apologies for its length. There is a short summary of my conclusions in Section 8.
THE CONTRACT TERMS
The terms of the contract relevant to Issues A-D are set out in paragraph 6 below. The amendments to the standard form, which are taken from the Schedule of Amendments, are shown as underlined.
The terms were as follows:
This Contract shall incorporate all the provisions of the Joint Contracts Tribunal Design & Build Contract 2011 (DB 2011), as amended by the Schedule of Amendments attached to the Conditions.
2.28 If the Contractor fails to complete the Works or a Section by the relevant Completion Date, the Employer shall issue a notice to that effect (a ‘Non-Completion Notice’). If a new Completion Date is fixed after the issue of such a notice, such fixing shall cancel that notice and the Employer shall where necessary issue a further notice.
2.29.1 Provided
2.29.1.1 The Employer has issued a Non-Completion Notice for the Works or a Section; and
2.29.1.2 the Employer has notified the Contractor before the due date for the final payment under clause 4.12.5 that he may require payment of, or may withhold or deduct, liquidated damages,
the Employer may, not later than the day beforethe final date for payment of the amount payable under clause 4.12, give notice to the Contractor in the terms set out in clause 2.29.2.
2.29.2 A notice from the Employer under clause 2.29.1 shall state that for the period between the Completion Date and the date of practical completion of the Works or that Section:
2.29.2.1 he requires the Contractor to pay liquidated damages at the rate stated in the Contract Particulars, or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; and/or
2.29.2.2 that he will withhold or deduct liquidated damages at the rate stated in the Contract Particulars, or at such lesser stated rate, from sums due to the Contractor. 1
2.29.2.3 If the Employer fixes a later Completion Date for the Works or a Section, the Employer shall pay or repay to the Contractor any amounts recovered, allowed or paid under clause 2.29 for the period up to that later Completion Date.
2.29.2.4 If the Employer in relation to the Works or a Section has notified the Contractor in accordance with clause 2.29.1.2 that he may require payment of, or may withhold or deduct, liquidated damages, then, unless the Employer states otherwise in writing, clause 2.29.1.2 shall remain satisfied in relation to the Works or Section, notwithstanding the cancellation of the relevant Non-Completion
Notice and issue of any further Non-Completion Notice.4.7.1 Interim Payments shall be made by the Employer to the Contractor in accordance with section 4 and whichever of Alternative A (Stage Payments) or Alternative B (Periodic Payments) is stated in the Contract Particulars to apply.
4.7.2 The sum due as an Interim Payment shall be an amount equal to the Gross Valuation under clause 4.13 where Alternative A applies, or clause 4.14 where Alternative B applies, in either case less the aggregate of:
4.7.2.1 any amount which may be deducted and retained by the Employer as provided in clauses 4.16 and 4.18 (‘the Retention’);
4.7.2.2 the cumulative total of the amounts of any advance payment that have then become due for reimbursement to the Employer in accordance with the terms stated in the Contract Particulars for clause 4.6; and
4.7.2.3 the amounts paid in previous Interim Payments.
4.8.3 Where Alternative B applies, for the period up to practical completion of the Works, Interim Applications shall be made as at the monthly dates specified in the Contract Particulars for Alternative B up to the date of practical completion or the specified date within one month thereafter. Subsequent Interim Applications shall be made at intervals of 2 months (unless otherwise agreed), the last such application being made upon the expiry of the Rectification Period or, if later, the issue of the Notice of Completion of Making Good (or, where there are Sections, the last such period or notice). The due date in each case shall be the later of the specified date and the date of receipt by the Employer of the Interim Application.
Clauses 4.9.1, 4.9.2, 4.9.3, 4.9.4
4.9.1 The final date for payment of an Interim Payment shall be 21 days from its due date.
4.9.2 Not later than 5 days after the due date the Employer shall give a notice (a ‘Payment Notice’) to the Contractor in accordance with clause 4.10.1 and, subject to any Pay Less Notice given by the Employer under clause 4.9.4, the amount of the Interim Payment to be made by the Employer on or before the final date for payment shall be the sum stated as due in the Payment Notice.
4.9.3 If the Payment Notice is not given in accordance with clause 4.9.2, the amount of the Interim Payment to be made by the Employer shall, subject to any Pay Less Notice under clause 4.9.4, be the sum stated as due in the Interim Application.
4.9.4 If the Employer intends to pay less than the sum stated as due from him in the Payment Notice or Interim Application, as the case may be, he shall not later than 3 days before the final date for payment give the Contractor notice of that intention in accordance with clause 4.10.2 (a ‘Pay Less Notice’). Where a Pay Less Notice is given, the payment to be made on or before the final date for payment shall not be less than the amount stated as due in the Pay Less Notice.
4.10.2 A Pay Less Notice:
4.10.2.1 (where it is to be given by the Employer) shall specify both the sum that he considers to be due to the Contractor at the date the notice is given and the basis on which that sum has been calculated;
4.10.2.2 (where it is to be given by the Contractor) shall specify both the sum that he considers to be due to the Employer at the date the notice is given and the basis on which that sum has been calculated.
4.14 The Gross Valuation shall be the total of the amounts referred to in clauses 4.14.1 and 4.14.2 less the total of the amounts referred to in clause 4.14.3, calculated as at the date for making an Interim Application under clause 4.8.3.
9.2 If a dispute or difference arises under this Contract which either Party wishes to refer to adjudication, the Scheme shall apply, subject to the following:
9.2.1 for the purposes of the Scheme the Adjudicator shall be the person (if any) and the nominating body shall be that stated in the Contract Particulars;”
THE RELEVANT EVENTS
In July 2017, S&T commenced the first adjudication. The dispute arose out of their contention that, as a matter of construction, the contract excluded the Schedule...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Swansea Stadium Management Company Ltd v City & County of Swansea
...266 and Henry Boot Construction Ltd v. Alstom Combined Cycles Ltd [2005] EWCA Civ 814; [2005] 1 W.L.R. 3850 to Grove Developments Ltd v. S&T (UK) Ltd [2018] EWHC 123 (TCC); [2018] B.L.R. 173 and, on appeal, [2018] EWCA Civ 2448; [2019] B.L.R. 1 for the proposition that certificates or other......
-
Palmer Birch (A Partnership) v Michael Lloyd
...by Ms Lee was the decision of Coulson J (as he then was, giving his “last substantial judgment in the TCC”) in Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC). In his decision, addressing the provisions of the JCT Design & Build Contract 2011, the judge emphasised (and again......
-
S&T(UK) Ltd v Grove Developments Ltd
...or deduct all or any of the liquidated damages payable, must give the appropriate Pay Less Notice under clause 4.9. 4 or 4.12.8. [NOTE[2018] EWHC 123 (TCC) Royal Courts of Justice Strand, London, WC2A 2LL Anthony Speaight QC and Matthew Thorne (instructed by Trowers & Hamlins Llp) for t......
-
Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd
...in this conclusion by the analysis in a recent case of Coulson J (as he then was) in Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC). In that case, one of the issues was whether the conclusion that I had reached in the liability judgment about whether an adjudicator's decisi......
-
Smash And Grab (AKA Payment Notice Dispute) Adjudications: Where Are We Now?
...Builders Ltd v Greer, Broseley London Ltd v Prime Asset Management Ltd [2020] EWHC 944 (TCC). 18. [2014] EWHC 4007 (TCC). 19. [2018] EWHC 123 (TCC) and upheld subsequently by the Court of Appeal in S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448. 20. M Davenport Builders Ltd v Gr......
-
UK Construction briefing, January 2019
...as well as a raft of decisions on procedural issues. Not least was the TCC's decision in Grove Developments Ltd v. S&T (UK) Ltd [2018] EWHC 123 (TCC) which we reported here, Smash and grab adjudications – redressing the balance and here, Restoring fairness to the adjudication process: anoth......
-
Smash And Grab Adjudications Redressing The Balance
...must still pay up even if it has disputed those valuations throughout the project. In Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC), Coulson J has redressed the balance between contractors and employers and made such adjudications less The background The claimant (Grove) e......
-
Grove v S&T - The Fate Of Smash And Grab Adjudications Is Decided
...the much discussed judgment of Grove Developments Limited v S&T (UK) Limited [2018] EWHC 123 (TCC), Coulson J held that an employer is free to commence a second adjudication to dispute the true valuation of an interim payment application, provided it has paid the sum stated as due in th......
-
Price and payment
...[53]–[58], per DhCJ Nissen QC (considering a JCT Intermediate Building Contract WCD 2011 form); Grove Developments Ltd v S&T (UK) Ltd [2018] EWhC 123 (TCC) at [21]–[26], per Coulson J (airmed: [2018] eWca civ 2448). See also VHE Construction plc v RBSTB Trust Ltd [2000] BLr 187 at 195 [60],......
-
Chapter 13. Damages
...Power Pty Ltd (in liq) [2016] QCA 214 at [14]–[20], per Morrison JA; at [99]–[103], per Philip McMurdo JA; Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC) at [148]–[159], per Coulson J (considering clause 2.29 of the JCT Design & Build Contract 2011) [2018] EWCA Civ 2448); N......
-
Damages
...(in liq) [2016] QCa 214 at [14]–[20], per Morrison Ja; at [99]–[103], per philip McMurdo Ja; Grove Developments Ltd v S&T (UK) Ltd [2018] EWhC 123 (TCC) at [148]–[159], per Coulson J (considering clause 2.29 of the JCT Design & Build Contract 2011) (airmed: [2018] eWCA Civ 2448); Ng Tze Che......
-
Chapter 6. Price and payment
...17 (TCC) at [53]–[58], per DHCJ Nissen QC (considering a JCT Intermediate Building Contract WCD 2011 form); Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC) at [21]–[26], per Coulson J (affirmed: [2018] EWCA Civ 2448); Advance JV v Enisca Ltd [2022] EWHC 1152 (TCC) at [47], per J......