Hutton Construction Ltd v Wilson Properties (London) Ltd

JurisdictionEngland & Wales
JudgeThe Hon. Mr Justice Coulson
Judgment Date16 March 2017
Neutral Citation[2017] EWHC 517 (TCC)
Docket NumberCase No: HT-2016-000362
CourtQueen's Bench Division (Technology and Construction Court)
Date16 March 2017
Between:
Hutton Construction Limited
Claimant
and
Wilson Properties (London) Limited
Defendant

[2017] EWHC 517 (TCC)

Before:

The Hon Mr Justice Coulson

Case No: HT-2016-000362

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice

Rolls Building, Fetter Lane, London, EC4A 1NL

Mr Jonathan Lewis (instructed by Fenwick Elliott LLP) for the Claimant

Mr William Webb (instructed by Birketts LLP) for the Defendant

Hearing date: 23 February 2017

Judgment Approved

The Hon. Mr Justice Coulson
1

INTRODUCTION

1

This is a summary judgment application by the claimant, seeking to enforce the decision of the adjudicator, in the sum of £491,944.73. The defendant does not raise any issue as to the adjudicator's jurisdiction, nor is it said that there was any breach of natural justice. Instead, the defendant seeks to defend the summary judgment application on the grounds that the adjudicator was wrong to reach the conclusion that he did and that, in consequence, there should be no judgment in favour of the claimant. The claimant denies that this is a legitimate approach on the facts of this case.

2

As I pointed out to the parties during the course of argument, the defendant's stance is an increasingly common one amongst those who are dissatisfied with an adjudicator's decision. It raises fundamental points of principle and practice concerning the enforcement of adjudication decisions. For that reason, having informed the parties that I would enter summary judgment for the claimant and would not permit the defendant to raise their challenge in defence of the claim, I reserved this Judgment.

2

THE RELEVANT PRINCIPLES

3

The starting point, of course, is that, if the adjudicator has decided the issue that was referred to him, and he has broadly acted in accordance with the rules of natural justice, his decision will be enforced: see Macob Civil Engineering Limited v Morrison Construction Limited [1999] BLR 93. Adjudication decisions have been upheld on that basis, even where the adjudicator has been shown to have made an error: see Bouygues (UK) Limited v Dahl-Jensen (UK) Limited [2000] BLR 522. Chadwick LJ summarised the principal reason for this in Carillion Construction Limited v Devonport Royal Dockyard Limited [2006] BLR 15: "the need to have the 'right' answer has been subordinated to the need to have an answer quickly."

4

There are two narrow exceptions to this rule. The first, exemplified by Geoffrey Osborne v Atkins Rail Limited [2010] BLR 363, involves an admitted error. In that case the calculation error was raised by the defendant in a separate Part 8 claim. Because the error was admitted by everyone, including the adjudicator, and because there was no arbitration clause, which meant that the court had the jurisdiction to make a final decision on the point, there were no reasons why, in that case, the error could not be corrected. If there had been an arbitration clause, the court would not have had the power to determine the issue and the decision would have been enforced: see Pilon Limited v Beyer Group PLC [2010] BLR 452.

5

The second exception concerns the proper timing, categorisation or description of the relevant application for payment, payment notice or payless notice, and could be said to date from Caledonian Modular Limited v Mar City Developments Limited [2015] EWHC 1855 (TCC). In that case, the defendant had raised one simple issue, in a detailed defence and counterclaim served at the outset, to the effect that a small group of documents could not have constituted a claim for or notice of a sum due for payment. If that argument was right, it was agreed that the claimant was not entitled to summary judgment. At paragraph 11 of my judgment in that case, I reiterated the general principle that it was not open to a defendant to seek to avoid payment of a sum found due by an adjudicator by raising the very issue on which the adjudicator ruled against the defendant in the adjudication. I went on:

"12. That is, of course, the general rule and it will apply in 99 cases out of 100. But there is an exception. If the issue is a short and self-contained point, which requires no oral evidence or any other elaboration than that which is capable of being provided during a relatively short interlocutory hearing, then the defendant may be entitled to have the point decided by way of a claim for a declaration. That is what happened, for example, in Geoffrey Osborne v Atkins Rail Ltd [2010] BLR 363. It is envisaged at paragraph 9.4.3 of the TCC Guide that separate Part 8 proceedings will not always be required in order for such an issue to be decided at the enforcement hearing.

13. It needs to be emphasised that this procedure will rarely be used, because it is very uncommon for the point at issue to be capable of being so confined. But in the present case, it is common ground that the proper meaning and interpretation of the documents of 13 February is a straightforward matter for the court. No other evidence of any kind is required. It is also common ground that, if the adjudicator was wrong, and those documents do not constitute a proper claim for payment or a payee's notice, then the defendant's payless notice was valid and there is no entitlement to summary judgment. Accordingly, this is one of those rare cases where the substantive point in issue can be determined at the enforcement hearing. During the course of his clear submissions on the substantive issues, Mr Webb properly did not suggest to the contrary."

6

What, I think, nobody could have predicted at the time of Caledonian Modular was the proliferation of what I understand are (unhappily) called 'smash and grab' cases: those adjudication claims (usually, but not always, brought by contractors) based on the contention that the other party has failed to serve proper or timeous applications for payment or payment/pay less notices, thereby automatically entitling the claiming party to the sums claimed, no matter how controversial. The significant increase in these sorts of claims seems to me to arise principally from the ill-considered amendments to the 1996 Act, and the over-prescription of the payment terms included in the standard forms of contract, which have led to provisions of unnecessary complexity. I am also aware of the widely-held view that this problem has been inadvertently compounded by the run of authorities starting with ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC), which prohibit a second adjudication dealing with the detailed valuation of an interim payment already awarded by an adjudicator.

7

What should the court do on enforcement in circumstances where the claiming party — whom I shall call the claimant — has been successful, because the adjudicator has ruled that the responding party — whom I shall call the defendant — failed to serve a notice in time, or failed to comply with some other provision of the contract in relation to applications for payment or payment/pay less notices? In many ways, the answer to that is conditioned by the nature and extent of any agreement between the parties.

3

THE SUBSEQUENT AUTHORITIES

8

The authorities since Caledonian Modular demonstrate that, very often, the point taken by the defendant is a straightforward argument to the effect that the adjudicator was wrong and that, either with regard to its timing, or its content, the relevant payment notice was invalid and/or that the pay less notice was valid and prevented payment. In those circumstances, the defendant has issued Part 8 proceedings seeking a declaration to that effect. The claimant may issue its own enforcement claim or, as the cases show, the parties may agree that, if the defendant loses its Part 8 claim, it will pay the sums awarded by the adjudicator in any event.

9

This broadly consensual approach can be seen in a number of the cases, including:

a) Leeds City Council v Waco UK Limited [2015] EWHC 1400 (TCC), a case where LCC was given leave to defend, only on the basis that they pay the sums awarded by the adjudicator to Waco. LCC complied with that order and then brought CPR Part 8 proceedings for a declaration that Waco's application for an interim payment was not a valid application and that the adjudicator's decision was therefore wrong.

b) Manor Asset Limited v Demolition Services Limited [2016] EWHC 222 (TCC), a case where the point in issue in the adjudication was the proper construction of the contract. The losing party, MAL, then brought Part 8 proceedings seeking a declaration that the adjudicator's interpretation was wrong. DSL responded by seeking summary judgment. The adjudicator's decision was upheld, albeit for different reasons.

c) Bouygues (UK) Limited v Febrey Structures Limited [2016] EWHC 1333 (TCC), another dispute about the construction of the contract. Bouygues, who lost the adjudication, sought declarations by way of Part 8. They made plain that they would not pursue any of the issues that they had raised with respect to Febrey's enforcement proceedings, so everything turned on the Part 8 Claim.

d) Kersfield Developments (Bridge Road) Limited v Bray and Slaughter Limited [2017] EWHC 15 (TCC), a case in which there were parallel enforcement and Part 8 proceedings, which were dealt with simultaneously. The judge was required to deal with no less than six issues as to the timing and the content of various notices, and concomitant arguments about estoppel.

e) Surrey and Sussex Healthcare NHS Trust v Logan Construction (South East) Limited [2017] EWHC 17 (TCC), a case in which the Trust lost the adjudication and challenged the decision by way of Part 8. The parties agreed that the questions raised were amenable to consideration by the court by way of a Part 8 claim and that, by consent, there were no separate enforcement proceedings. The judge found...

To continue reading

Request your trial
19 cases
  • Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 12 July 2017
    ...In a recent case, Coulson J described it as "an unhappy expression". In Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC) he said, in describing what such disputes are, the following at [6]: "What, I think, nobody could have predicted at the time of Caledonian M......
  • LJR Interiors Ltd v Cooper Construction Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 11 January 2023
    ...within the type of challenge recognised by Coulson J, as he then was, in Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC). In a passage of the judgment now replicated in paragraphs 9.4.4 and 9.4.5 of the TCC Guide, the judge said, at [17], that in order to res......
  • Willow Corporation S.À.R.L. v MTD Contractors Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 25 June 2019
    ...to have the point decided by way of a claim for a declaration.” 30 In Hutton Construction Ltd v. Wilson Properties (London) Ltd [2017] EWHC 517 (TCC), Coulson J indicated that where a defendant seeks to argue such a short and self-contained point, it should issue a Part 8 claim seeking dec......
  • A & v Building Solutions Ltd v J & B Hopkins Ltd
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 27 January 2023
    ...endeavour to sort out the Part 8 proceedings. The same point was made in Hutton Construction Limited v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC); [2017] BLR 344, where the judge said that the Part 8 claim should be dealt with after the enforcement, unless the point raised was st......
  • Request a trial to view additional results
6 firm's commentaries
  • Adjudication update
    • United Kingdom
    • Mondaq UK
    • 30 November 2017
    ...there is not a substantial dispute of fact and so the claim is capable of being resolved without lengthy and complicated pleadings 6. [2017] EWHC 517 (TCC) 7. Practitioners should also note that Mr Justice Coulson confirmed that his judgment in Hutton now supersedes paragraph 9.4.3 of the T......
  • Too Late: TCC Upholds Part 8 Challenge Against Adjudication On Grounds Of Limitation
    • United Kingdom
    • Mondaq UK
    • 16 February 2023
    ...circumstances), as the primary principle is to "pay now and argue later". Hutton Construction Ltd v Wilson Properties (London) [2017] EWHC 517 (TCC) explained what a party resisting enforcement through a Part 8 claim must show to succeed. It needs to demonstrate that there is a clear-cut is......
  • How Not To Resist Enforcement Of An Adjudicator's Decision - A TCC Guide
    • United Kingdom
    • Mondaq UK
    • 8 September 2017
    ...by Nathaniel Horrocks-Burns (Hutton Construction Limited v Wilson Properties (London) Limited [2017] EWHC 517 (TCC)) The Technology and Construction Court (TCC) generally enforces adjudication decisions, providing the adjudicator has decided the dispute that was referred to him and acted in......
  • Using Part 8 can be used to challenge a wrong adjudicator's decision: but care (and speed) needed - Successful challenges of adjudication enforcement are rare
    • United Kingdom
    • JD Supra United Kingdom
    • 16 August 2019
    ...and Construction Court (TCC) issued guidance on the use of Part 8 in Hutton Construction Ltd v. Wilson Properties (London) Ltd [2017] EWHC 517 (TCC). The Hutton guidance emphasised the Construction Act's aim to keep project cash flowing which is achieved in part by the binding nature of an ......
  • Request a trial to view additional results
3 books & journal articles
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Hutchison Construction Services Pty Ltd v Fogg [2016] NSWCA 135 III.26.236 Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC) II.6.235, III.24.30, III.24.92, III.24.133, III.24.137 H’Var Steel Services Pty Ltd v TDC Concrete Pty Ltd [2017] WASCA 63 III.22.30 ccxl......
  • Statutory adjudication
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...352; ISG Construction Ltd v Seevic College [2014] EWHC 4007 (TCC). See also Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC) at [6], per Coulson J. 205 VHE Construction plc v RBSTB Trust Ltd [2000] BLR 187 at 194 [49], per HHJ Hicks QC. 206 Arcadis UK Ltd v May......
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...the legislation in this respect has been described as “ill-considered”: Hutton Construction Ltd v Wilson Properties (London) Ltd [2017] EWHC 517 (TCC) at [6], per Coulson J. 915 hat is, unless the contract in question expressly contemplates the payer being unable subsequently to recover any......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT