Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd

JurisdictionEngland & Wales
JudgeMR JUSTICE FRASER,Mr Justice Fraser
Judgment Date21 June 2018
Neutral Citation[2018] EWHC 1577 (TCC)
CourtQueen's Bench Division (Technology and Construction Court)
Docket NumberCase No. HT-2015-000381
Date21 June 2018

[2018] EWHC 1577 (TCC)

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT (QB)

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

The Honourable Mr Justice Fraser

Case No. HT-2015-000381

Between:
Imperial Chemical Industries Limited
Claimant
and
Merit Merrell Technology Limited
Defendant

Martin Bowdery QC and Lucie Briggs (instructed by Clyde & Co. LLP) for the Claimant

Justin Mort QC and Robert Scrivener (instructed by Mills & Co.) for the Defendant

Hearing dates: 17, 18, 19, 23, 24, 25, 26 April 2018, 8 May 2018

Draft distributed to parties: 11 June 2018

JUDGMENT (No. 2 QUANTUM)

Mr Justice Fraser

I Introduction

1

This case concerns works performed by Merit Merrell Technology Ltd (“MMT”) for Imperial Chemical Industries Ltd (“ICI”) at a paint manufacturing facility in the North of England between the end of 2012 and into early 2015. MMT was a specialist engineering piping manufacturer, based in Cramlington in Northumberland. It is now in liquidation. On 18 December 2012 MMT and ICI entered into a contract, which was executed as a deed, for works associated with the construction of a new paint manufacturing facility for ICI at the manufacturing facility to which I have referred, which is located at Ashwood Business Park, Ashington, Northumberland (“the Plant”). The value of the works that it was intended, as at that date in 2012, that MMT would perform was quite modest, being only approximately £1.9 million in value. The works the subject of the contract to be performed by MMT were the manufacture, construction, installation, commissioning and handover of steelworks and free issue tank offloading and positioning works. These works were referred to informally during the trial as being those within the Steelworks Contract. No pipework was initially included in those works at all, although in the event 42,000m of such pipework was installed. ICI used to be a major FTSE100 company in its own right, and manufactured many items, including paint, with one of its most well-known brands being Dulux paints. In 2007 it was acquired by AkzoNobel, a Dutch multinational company, whose legal name is Akzo Nobel NV (“AkzoNobel”). ICI was absorbed into the AkzoNobel group as a result of the takeover, but remains a separate legal entity. It was ICI who contracted with MMT for the works. The project was called “Project Fresco”. This judgment is in relation to the quantum disputes between the parties. My judgment on liability is at [2017] EWHC 1763 (TCC), and my judgment on costs in relation to that round of the proceedings is at [2017] EWHC 2269 (TCC). In addition to these judgments, there is one of Jefford J at [2016] EWHC 3082 (TCC) dealing with the adjournment of an earlier trial and the associated costs orders, together with another by the same judge on an adjudication enforcement at [2016] EWHC 3030 (TCC). The first judgment, however, in a long running series is a decision of Edwards-Stuart at [2015] EWHC 2915 (TCC), relating to an attempt by ICI to obtain an order for delivery up of documents. This judgment is therefore the sixth one in this long running series, and is in the following parts:

Section

Paragraph

I Introduction

1

II Disclosure

21

III The issues

26

IV The ability to revisit assessments under the

55

NEC3 contract terms

V The ability to revisit agreements reached with

70

ICI personnel and the Project Manager

VI The burden of proof

75

VII The witnesses of fact

85

VIII ICI's application to adduce new expert evidence and further points on disclosure

149

IX The expert witnesses

165

X Conclusion on expert evidence generally

233

XI The Scott Schedule sub-issues

238

XII Answer to Agreed Issue 1: The total value of MMT's works

352

XIII The Counterclaim

357

XIV Answer to Agreed Issue 2: The Counterclaim

422

XV Answer to Agreed Issues 3 and 4: Interest

423

XVI Conclusion

425

2

ICI maintained in the application before Edwards-Stuart J in witness evidence from its solicitors that without those documents the Plant could not be operated, and further that the Health and Safety Executive would not permit ICI to operate the Plant. This latter point is dealt with at [61] and [62] of that judgment. The judge declined to make the order. The Plant did however operate thereafter. It can therefore be seen that this judgment is potentially the final element of some long running, and bitterly fought, litigation arising out of Project Fresco. In addition to the litigation, there have been four adjudications.

3

For convenience I will provide a brief outline of the dispute in this introduction; however, for a detailed analysis of the liability issues and relevant findings the substantive judgment on liability should be read.

4

The Plant was to produce almost 2 million litres of solvent borne, and water borne, paint products per week. Obviously, such works would require piping in very great quantities, and also in a variety of sizes, and these pipes are joined together by welds. This pipework was not however designed when the contract was agreed with MMT. These proceedings, so far as liability was concerned, essentially concerned the quality of the welds performed by MMT, together with a repudiation issue. The value of the works was also very much in issue, although for the purpose of resolving in the liability trial the legal issue about recovery of a potential overpayment I was asked to assume that ICI had overpaid MMT. All matters of quantum were to be dealt with at a later trial.

5

By way of Project Manager's Instruction No.3 (“PMI03”) the works to be performed by MMT under the contract had been expanded very considerably. PMI03 was dated 5 February 2013, and predominantly concerned pipework, whereas the original contract was predominantly for steelwork. The PMI03 works were referred to informally as the works under the Pipeworks Contract, although that informal nomenclature does not mean that there were two entirely separate contracts. PMI03 instructed works under the existing contract and the NEC3 terms govern all of the works performed by MMT, whether those works were steelworks or pipework. There is a dispute about the total value of the works performed by MMT, but it is common ground that PMI03 increased their value very considerably, and as at the date of issue of the Claim Form in these proceedings MMT had been paid £20.9 million. Even on ICI's case MMT's works were worth approximately £10 million. Both of these sums are obviously far in excess of the originally contracted works of less than £2 million.

6

Between 2012 and 2014 the works proceeded, with the only point of note for these purposes being that the project as a whole began to run substantially over the internal budget set by AkzoNobel, and to take longer than expected. Although ICI was a separate legal entity, all of the decisions that were made that are relevant to the period from the middle of 2014 onwards, were made by personnel at AkzoNobel, who controlled the funding, and who took over and ran the project. A committee within AkzoNobel called the Steering Committee or Steer Co had its own internally approved figure for total expenditure on Project Fresco, which was called CapEx (for Capital Expenditure). In the middle of 2014 the senior management of AkzoNobel decided that Project Fresco had to be finished, and overall expenditure had to be brought down below the approved CapEx figure. Accordingly, some AkzoNobel personnel were dispatched to the site for that sole purpose. By far the most important, and senior, of these for the purposes of this trial (and the earlier trial of liability issues in 2017) was Mr Boerboom. By December 2014 CapEx had been increased by AkzoNobel to £157.7 million, far higher than the figure initially approved by the board earlier in the life of the project. The fact that the cost was increasing so much was one of the main reasons (delay being the other) that the AkzoNobel team were sent to site, and became so involved. The AkzoNobel team were there to get the project back on track. CapEx formed no part of the contractual relations between ICI and MMT. However, given expenditure on the MMT contract (or more accurately, financial exposure by ICI to MMT) was very much higher than initially intended, something of a financial squeeze developed. The amount of CapEx still available to be spent overall, was not necessarily the same as the amount to which MMT was potentially entitled under its contract terms; nor was the amount of CapEx still available to be spent, necessarily sufficient for all the contractual liabilities ICI might have to MMT and the other contractors. These issues were addressed in the first judgment on liability. CapEx was what governed the AkzoNobel approach to MMT and its contract, and not MMT's contractual entitlement, nor the other contract terms.

7

Mr Boerboom is a Director of Engineering Excellence for AkzoNobel Advanced Manufacturing Projects & Engineering based in Arnhem in the Netherlands. Project Fresco had commenced in January 2011 and was supposed to be fully operational by December 2014. Mr Boerboom was sent to the project in July 2014. The contract between ICI and MMT was on the NEC3 form as amended, which is a detailed standard form widely used in the industry and designed to have (as with so many contract forms) an independent third party involved. The Project Manager (the name in the NEC3 form for the entity that performs the independent third party certifier function under the contract) was a company called PROJEN. The relevant person at PROJEN was called Andy Barton. PROJEN was also involved in designing the works. In general terms, such an independent third party...

To continue reading

Request your trial
11 cases
  • Essex County Council v UBB Waste (Essex) Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 18 June 2020
    ...The problem of partisan expert evidence in the TCC was recently considered by Fraser J in ICI Ltd v. Merit Merrell Technology Ltd [2018] EWHC 1577 (TCC). At [237], the judge restated the principles drawn from the case law and the Civil Justice Council's guidance and stressed that partisan ......
  • Alan Bates and Others v Post Office Ltd
    • United Kingdom
    • Queen's Bench Division
    • 16 December 2019
    ...for the Horizon Issues trial. That case is Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd (No.2 Quantum) [2018] EWHC 1577 (TCC). 713 The exchange with the court continued: “Mr Justice Fraser: …In order to apply for permission to adduce extra expert evidence you would have ......
  • Essex County Council v UBB Waste (Essex) Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 11 September 2020
    ...or refused and that there was no excuse for failing properly to disclose the conflict. In ICI Ltd v. Merit Merrell Technology Ltd [2018] EWHC 1577 (TCC), Fraser J rightly observed, at [237], that partisan expert evidence is not the norm in this court. It is very important to the proper adm......
  • Blackpool Borough Council v Volkerfitzpatrick Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 25 February 2020
    ...v Watts Group plc [2017] EWHC 1667 TCC and by Fraser J in Imperial Chemical Industries Limited v Merritt Merrol Technology Ltd [2018] EWHC 1577 (TCC) of experts who had failed to display proper independence in those cases. I entirely agree that where experts fail to perform their obligati......
  • Request a trial to view additional results
6 firm's commentaries
  • Summary of principles from recent NEC cases
    • Hong Kong
    • JD Supra Hong Kong
    • 10 September 2018
    ...with an employee of the employer’s parent company was invalid. Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWHC 1577 (TCC) NEC3 Engineering and Construction Contract The project manager's assessments of compensation events under the NEC3 ECC can be reviewed. The c......
  • Expert Evidence: The English Courts Send A Message To Experts (And Their Instructing Solicitors)
    • United Kingdom
    • Mondaq UK
    • 14 December 2021
    ...even the admissibility, of that expert evidence. Footnotes 1. Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWHC 1577(TCC) 2. Dana UK Axle Ltd v Freudenberg FST GMBH [2021] EWHC 1412(TCC) 3. Beattie Passive Norse Ltd & Anor v Canham Consulting Ltd [2021] EWHC 1116 (......
  • Expert Evidence: The English Courts Send A Message To Experts (And Their Instructing Solicitors)
    • United Kingdom
    • Mondaq UK
    • 14 December 2021
    ...even the admissibility, of that expert evidence. Footnotes 1. Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWHC 1577(TCC) 2. Dana UK Axle Ltd v Freudenberg FST GMBH [2021] EWHC 1412(TCC) 3. Beattie Passive Norse Ltd & Anor v Canham Consulting Ltd [2021] EWHC 1116 (......
  • UK Adjudication Review
    • United Kingdom
    • JD Supra United Kingdom
    • 31 July 2018
    ...The Honourable Mr Justice Fraser commented in his recent judgment in Imperial Chemical Industries Ltd v. Merit Merrell Technology Ltd [2018] EWHC 1577 (TCC) ("a long-running and bitter dispute"): "[This] litigation also stands as something of an advertisement for adjudication". Adjudication......
  • Request a trial to view additional results
4 books & journal articles
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...of Contract for Term partnering (TpC 2005 amended 2008)). 786 See Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWhC 1577 (TCC) at [70]–[74], per Fraser J. 787 London Borough of Camden v homas McInerney & Sons Ltd (1986) 9 Con Lr 99 at 116, per Judge Esyr Lewis QC; ......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Ltd [2017] EWhC 2299 (TCC) III.26.75, III.26.221, III.26.272 Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWhC 1577 (TCC) I.5.84, I.5.161, II.6.204, II.6.368, III.26.83, III.26.113, III.26.127, III.26.240 Imperial Chemical Industries plc v Bovis Construction Ltd (1......
  • Litigation
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...Resources Ltd [2016] HKCFI 1357 at [48], per Anthony Chan J. See also Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWHC 1577 (TCC) at [27]–[30], per Fraser J; Castle Trustee Ltd v Bombay Palace Restaurant Ltd [2018] EWHC 1602 (TCC) at [95], per Jeford J. 330 In Hos......
  • Contract administration
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Merrell Technology Ltd [2017] EWHC 1763 (TCC) at [37], per Fraser J; Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd [2018] EWHC 1577 (TCC) at [17], per Fraser J. 253 here is a qualitative diference between an owner being subject to an obligation “to ensure” that the contrac......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT