James Renwick and Vanessa Renwick v Simon and Michael Brooke Architects and William Atoll & Associates and Aquarend Ltd
| Jurisdiction | England & Wales |
| Court | Queen's Bench Division (Technology and Construction Court) |
| Judge | Mr Justice Akenhead |
| Judgment Date | 05 May 2011 |
| Neutral Citation | [2011] EWHC 874 (TCC) |
| Docket Number | Case No: HT-10-278 |
| Date | 05 May 2011 |
IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Royal Courts of Justice
Strand, London, WC2A 2LL
Mr Justice Akenhead
Edward Bennion-Pedley (instructed by PM Law) for the Claimant
Alexander Hickey (instructed by Hill Dickinson LLP) for the Second Defendant
Hearing dates: 25 March 2011
The Second Defendant, William Attwell and Associates, ("Attwell"), apply for summary judgement in effect to have the Claimants' claim dismissed on the grounds that its limitation defence is bound to succeed. Issues are raised under Section 14A of the Limitation Act 1980 and as to when time for the purpose of limitation begins to run.
The Facts
So far as the facts are concerned as set out in this section of the judgement, the findings are made solely for the purposes of this application and are not intended to bind the trial judge. They are based on the pleadings and the evidence put before the court on Attwell's application.
Mr and Mrs Renwick have at all material times been the owners of a house, 38, Wandle Road London SW17 7DW. Simon Smith and Michael Brooke Architects was a firm of architects (the "Architect"), Attwell was a firm of structural engineers and the Third Defendant, Aquarend Ltd, was a waterproofing contractor, each of whom was engaged by the Renwicks in the period 2000 to 2002. In late 2000, the Renwicks decided to extend and refurbish their home; this project included the construction of a large basement room beneath their rear garden which came to be known as "the Garden Room". Unsurprisingly one of their requirements was that this room was to be waterproof. They say that they engaged the Architect to provide various design, construction and advisory services in relation, amongst other things, to this aspect of the matter.
The Renwicks plead that they contractually engaged Attwell as a structural engineer to provide "structural advice on design for the Garden Room, such that the completed Garden Room would be suitable for both building regulation approval and construction purposes, which…required that the said structural advice and design should deliver a watertight structure." They also plead that Attwell was additionally required to inspect the works as they proceeded.
A contractor, Concrete and Clay Underpinning Ltd ("the Contractor"), was employed by the Renwicks in about May 2001 to carry out the structural work for the Garden Room and the Contractor started work about June 2001. It is suggested that initially the Garden Room was to be a conventional design protected by external waterproofing membrane and covered by an external skin of masonry. However, it is pleaded that there had been a change on the advice of the Architects and/or Attwell in March 2001 whereby "the concrete…was to be dosed with Sika 1 admixture and the said external waterproofing omitted and replaced by volclay matting on the vertical components and asphalt on the horizontal". The Contractor is said to have finished its work by about November 2001.
Fairly soon thereafter, substantial quantities of water came into the Garden Room. The Contractor was called in and pumped out the water. There clearly was a serious problem because the Architect wrote to the Contractor (copied to Attwell and the Renwicks):
"I inspected the basement today, 6 days after my last visit which was just after you pumped out the water and attended to some leaks.
…Despite this, the level of the water has risen by about 75 mm so in my view the construction is still leaking…
The contract was to provide a waterproof basement which it does not yet appear to be. From my point of view it may be that the solution is simple but alternatively it might be necessary to tank the entire space which was not allowed for and will be an additional cost to my clients. Until the basement is leak free, I do not see how I can certify the contract as complete.
I do appreciate that money is tight for you so it is important that the lightwell walls go up quickly to eliminate the question of rainwater. I hope that these will be built within a week but I am still convinced that the problem is that basement floor level."
Mr Renwick accepts that the room filled up with water at an alarming rate. Mrs Renwick also confirms this in an e-mail of 19 February 2002 to the Architect, in which her frustration with Attwell also emerges:
"I returned to site yesterday afternoon and the underground room having been pumped dry was rapidly filling up with water again. You could see quite clearly where the water was gushing in. At this stage, before the joints are covered over, we require the structural engineer to visit site and give us a considered report, failing this we will have no option to take legal action against him to have the whole job re-done."
This was followed by a letter dated 22 February 2002 from the Architects to Attwell which expressed disappointment that Attwell had not been on site on the previous Monday and continued:
"We were all concerned with the situation in the basement room which was still filling up fast at about four" a week. Concrete & Clay have been plugging holes all this week but I do not know with what success as I am in Wales at present. The concern is that as soon as certain holes are plugged, the pressure will merely move elsewhere. Most of the problems seem to be at the joint between the kicker upstand and the walls.
I have seen no certificate from Hansens who provided the Sika mix, but the system of Sika mix and Sika joints, which is supposed to give a waterproof construction, does not appear to have worked. Furthermore, the workmanship is bad, particularly the shuttering which was poor, giving very uneven walls which are far from smooth in places.
We have had a quote from the London Basement Company as the enclosed to remedy the situation if necessary. This involves a sump pump and lining to the walls and floor to allow water to seep behind the sump. The costs are roughly similar to that held back from Concrete & Clay at present.
This major loss of confidence needs to be dealt with quickly and I would like you to produce a thorough report on the concrete, the workmanship and the solutions to providing a waterproof shell as intended."
This was copied to the Renwicks.
Attwell's Mr Dixon visited the site shortly thereafter and he wrote to the Contractor on 28 February 2002 (copied to the Renwicks and the Architect):
"… we completed our inspection as planned and enclose our observations.
The general concrete surfaces appear to be reasonably sound, although there are several areas of honeycombing evident in specific locations especially at the bottom and side of pours i.e against construction joints. There are also a small number of isolated damp patches on the wall furthest away from the main building. Construction joints leave much to be desired with abrupt changes in plane of up to 100 mm being typical. This appears to be as a result of movement of the wall shutters during the pour. We consider this, combined with poorly aligned hydrophilic sealant, to be the main reason for the leaks evident throughout the structure at present.
When we last spoke on site with Paul Langley, he said that he intended to line up the internal faces by scabbling the surface and applying a coating of Sika modified mortar. Is this still your intention?
A visual inspection of the repairs already carried out infers a reactive approach has been utilised to date with little thought and planning other than 'plug what is visibly leaking'. If this is not the case we would appreciate seeing the methodology being used. In our opinion the main zone for water ingress is at kicker level in the walls. Only when that band has been effectively rectified can we look at joints within the floor slab.
In our fax we asked if Sika had been contacted for their opinion. We believe that they should be able to provide invaluable guidance to rectify the problem, and confirm whether or not the situation is retrievable utilising current methods and materials. Could you please speak to them as a matter of urgency and inform us of their reactions.
If you feel that we can contribute to the quick resolution of the problem which is currently dogging the project we would be happy to meet and discuss alternatives with you at your convenience. Please ring to confirm."
The Architect replied on the same day (copied to the Renwicks):
"…I am very concerned that we all work together to deal with this matter. Concrete & Clay have now spent almost two weeks cutting out joints and plugging with Sika stop. Nevertheless the room is still filling up at about 30 mm a day, some 3,300 litres.
Concrete & Clay have assured us that whatever it takes they will waterproof the basement and there will come a point when they give up trying to plug the holes and resort to other means which will have a cost implication as far as they are concerned. We have had an indication from the London Basement company, as the enclosed, that it would cost in the region of £25,850.00 to sort the problem out…
I am holding back Concrete & Clay's last request for payment at about £15,000 and would like to suggest to them when they feel that they need to resort to other means that we will pay them a certain amount, leaving sufficient for someone else to complete the works."
Sika Ltd was called in, by the Architect, to inspect and make recommendations which it did by fax dated 19 March 2002:
"Further to our site meeting on 19 March 2002 concerning the reported problems at the above contract, we comment as follows:-
Observations
The basement construction was covered on the base slab with...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Limitation: When Did The Claimants Have Knowledge Of The Alleged Breach?
...date. In the recent case of Mr & Mrs Renwick v (1) Brooke Architects (2) Attwell & Associates (3) Aquarend Ltd Limited [2011] EWHC 874 (TCC), s14A was again put to the The Facts: In 2000, Mr & Mrs Renwick ("the Claimants") decided to extend and refurbish their home in London. Th......
-
Chapter 14. Defects
...See also Felton v Gaskill Osborne (1992) 10 Const LJ 136; Harris Springs Ltd v Howes [2008] BLR 229; Renwick v Simon and Michael Brooke Architects [2011] EWHC 874 (TCC) at [20] and [24], per Akenhead J; Vinci Construction UK Ltd v Eastwood and Partners (Consulting Engineers) Ltd [2023] EWHC......
-
Chapter 14. Defects
...See also Felton v Gaskill Osborne (1992) 10 Const LJ 136; Harris Springs Ltd v Howes [2008] BLR 229; Renwick v Simon and Michael Brooke Architects [2011] EWHC 874 (TCC) at [20] and [24], per Akenhead 199 Wilson v Le Fevre Wood & Royle (1995) 66 Con LR 74 at 84, per Hutchison LJ. 200 Haw......
-
Defects
...v Gaskill Osborne (1992) 10 Const LJ 136; Harris Springs Ltd v Howes [2008] BLr 229; Renwick v Simon and Michael Brooke Architects [2011] EWhC 874 (TCC) at [20] and [24], per akenhead J. 211 Wilson v Le Fevre Wood & Royle (1995) 66 Con Lr 74 at 84, per hutchison LJ. 212 Haward v Fawcetts [2......
-
Table of cases
...renold australia pty Ltd v Fletcher Insulation (Vic) pty Ltd [2007] VSCa 294 II.13.77 renwick v Simon and Michael Brooke architects [2011] EWhC 874 (TCC) II.14.75 reozone pty Ltd v Santoro [2018] NSWSC 650 III.19.53, III.26.283 republic International Trust Co Ltd v Fletcher ramos & Co [2000......