London North Eastern Railway Limited 4th March 2024

Date04 March 2024
Head Office:25 Cabot Square, London E14 4QZT: 020 7282 2000 orr.gov.uk
Cl ai re Br oo ks
Access Executive
4 March 2024
Mark Garner
Customer Manager
Network Rail Infrastructure Ltd
Floor 4B
George Stephenson House
Network Operations
Toft Green
York YO1 6JT
Malcolm Knight
Head of Operational Planning
London North Eastern Railway Ltd
25 Skeldergate
York
YO1 6DH
Dear Mark and Malcolm
Approval of the 32nd supplemental agreement to the track access contract
between Network Rail Infrastructure Limited and London North Eastern
Railway dated 3 March 2017
We have today approved the above supplemental agreement submitted to us formally on
29 February 2024 under section 22 of the Railways Act 1993 (the Act). This follows an
earlier informal submission of a draft agreement for our consideration. This letter explains
the reasons for our decision.
Purpose
The purpose of this agreement is to extend LNER’s rights to operate services on the East
Coast Main Line on a contingent basis for a further timetable period, in line with Network
Rail Policy. This is effected by way of extending the duration of Part B of Schedule 5 in
LNER’s track access contract to PCD 2024,and delaying the start of Part C until Part B’s
expiry (PCD 2024).
Industry consultation
Network Rail undertook the usual industry consultation, no concerns were raised.