McGlinn v Waltham Contractors Ltd (No 1)

JurisdictionEngland & Wales
Judgment Date24 June 2005
Neutral Citation[2005] EWHC 1419 (TCC)
Docket NumberCase No: HT-05–120
CourtQueen's Bench Division (Technology and Construction Court)
Date24 June 2005
Between
Ian McGlinn
Claimant
and
Waltham Contractors Ltd First
Defendant
and
HUW Thoms Associates Second
Defendant
and
D J Hartigan & Associates Ltd Third
Defendant

[2005] EWHC 1419 (TCC)

Before

His Honour Judge Peter Coulson QC

Case No: HT-05–120

IN THE HIGH COURT OF JUSTICE

QUEENS BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Introduction

1

Mr Ian McGlinn, the Claimant, has issued these proceedings as a result of alleged deficiencies in the building work carried out at his property, Maison d'Or, on Jersey ("the property"). The Defendants are, respectively, the building contractors, Waltham Contractors Ltd ("Waltham"); the Architects, Huw Thomas Associates ("HTA"); and the Engineers, DJ Hartigan & Associates Ltd. The claims involve allegations of defective work which, on the Claimant's case, was so extensive that the property had, eventually, to be demolished. Against Waltham there is an additional claim for over-payment arising out of a dispute over the true value of the Final Account. The claims in total amount to about £4.5 million.

2

Before commencing these proceedings, the Claimant properly went through the steps prescribed by the Pre-Action Protocol for Construction and Engineering Disputes. This led to a mediation in November of last year, which was unsuccessful. The claims now made by the Claimant in the Particulars of Claim are, in some cases, different to those which existed at the commencement of the Pre-Action Protocol procedure.

3

In particular, HTA point out that the claims now made against them in the Particulars of Claim do not include claims in respect of over-payment to Waltham, nor claims in respect of loss and expense paid to Waltham. This is despite the fact that, at the outset of the Pre-Action Protocol procedure, both such claims were asserted by the Claimant against HTA.

4

At the First Case Management Conference, on 24/6/05, HTA sought an interim payment in the sum of £20,000 in respect of the costs which they say were thrown away at the Pre-Action Protocol stage in considering and responding to those two claims (for over-payment and loss and expense). The application was resisted by the Claimant. In deference to the careful submissions made by Mr Roger Stewart QC, for HTA, and Miss Lucy Garrett, for the Claimant, and in the absence of any direct authority on the point, I reserved judgment in order to reflect upon the principles involved. I have now concluded that I should refuse this particular application. My reasons for so doing are set out below.

JURISDICTION: 'Costs of and Incidental to'

5

Section 51 of the Supreme Court Act 1981 provides as follows:

(1) Subject to the provisions of this or any other enactment and to rules of court, the costs of and incidental to the proceedings in –

(a) The Civil Division of the Court of Appeal;

(b) The High Court, and

(c) Any County Court Service

shall be in the discretion of the court.

6

Mr Stewart QC submitted that the costs incurred by a party in complying with any Pre-Action Protocol are capable of being costs "incidental to" any proceedings which are subsequently commenced if the Protocol procedure fails to lead to an early settlement. I did not understand Miss Garrett to dispute that, as a matter of principle, costs incurred during a Pre-Action Protocol procedure may be costs "incidental to" any subsequent proceedings. In my judgment, it seems clear that, as a matter of construction of Section 51, the costs so incurred are capable of being costs "incidental to" the proceedings.

7

I am fortified in this view by the decision of Sir Robert Megarry, Vice Chancellor, in the case of In re Gibson's Settlement Trusts [1981] Ch 179. In that case the Vice Chancellor decided that, on an order for the payment of costs of proceedings, costs incurred before the proceedings commenced would not be disallowed solely on that account. He said that "on an order for taxation of costs, costs that otherwise would be recoverable are not to be disallowed by reason only that they were incurred before action brought". He also made plain that the words "incidental to" extended, rather than reduced, the ambit of any order, although he said that it was important to identify what the proceedings were in any case and how and why the costs claimed were incidental to those proceedings. As to costs incurred before the proceedings commenced he said :

"Of course, if there is no litigation there are no costs of litigation. But if the dispute ripens into litigation, the question then arises how far the ambit of the costs is affected by the shape that the litigation takes"

8

As I have already noted, there is no direct authority on the question of the general recoverability of costs incurred in compliance with Pre-Action Protocols. However in Callery v Gray [2001] 1 WLR 2112, the Court of Appeal were concerned with what costs were recoverable in circumstances where claims had settled without the need for substantive proceedings. At paragraph 54 of his judgment, Lord Woolf CJ said:

"(2) Where an action is commenced and a costs order is then obtained, the costs awarded will include costs reasonably incurred before the action started, such as costs incurred in complying with a Pre-Action Protocol".

9

Accordingly, both as a matter of construction of Section 51, and by reference to In re Gibson's Settlement and to Callery v Gray, I am of the view that, as a matter of principle, the costs incurred...

To continue reading

Request your trial
12 cases
  • E.n.e. Kos v Petroleo Brasileiro S.a. (petrobas)
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 23 July 2009
    ...is affected by the shape that the litigation takes”. 95 This approach is reflected in the decision of HHJ Peter Coulson QC in McGlinn v Waltham Contractors Limited, [2005] EWHC 1419 (TCC), in which he decided that the expense of complying with a pre-action protocol in respect of claims whic......
  • Cape Distribution Ltd v Cape Intermediate Holdings Plc
    • United Kingdom
    • Queen's Bench Division
    • 19 July 2016
    ...he addressed at [95]: "This approach is reflected in the decision of HHJ Peter Coulson QC in McGlinn v Waltham Contractors Limited , [2005] EWHC 1419 (TCC), in which he decided that the expense of complying with a pre-action protocol in respect of claims which were brought in subsequent pr......
  • R (Davey) v Aylesbury Vale District Council
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 15 November 2007
    ...179; [1981] 2 WLR 1; [1981] 1 All ER 233Ladd v Marshall [1954] 1 WLR 1489; [1954] 3 All ER 745, CAMcGlinn v Waltham Contractors Ltd [2005] EWHC 1419 (TCC); [2005] 3 All ER 1126R’s Application, In re [2001] EWHC Admin 571R v Intervention Board for Agricultural Produce, Ex p Fish Producers’ O......
  • Citation Plc v Ellis Whittam Ltd
    • United Kingdom
    • Queen's Bench Division
    • 28 March 2012
    ...of costs before the issue of a claim form. So I reserved this judgment. 8 Having then drawn the attention of the parties to McGlinn v Waltham Contractors Ltd [2005] EWHC 1419 (TCC); [2005] 3 All ER 1126 (discussed in the White Book 2012 para C1A-016), I invited such further submissions as ......
  • Request a trial to view additional results
1 firm's commentaries

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT