Chapter 11: Procurement

LibraryThe Application of Contracts in Developing Offshore Oil and Gas Projects
Pages134-141
AuthorPhilip Loots,Donald Charrett
11.1: Introduction

Once the Contract Strategy has been decided and the Owner has decided to either proceed with an EPC or EPCM contract model, the Owner would appoint a Contractor. This is normally done by a tendering process as outlined in the following section.

We saw in Chapter 5 that a key part of the EPC Contractor’s role is to prepare the procurement strategy for procurement of equipment and materials. A key part of the EPCM Contractor’s role is to advise the Owner on the procurement strategy and then to assist the Owner in implementing that strategy. The procurement of equipment and materials is discussed in section 11.3 below, and expediting procedures in section 11.4 below.

11.2: Tendering procedures for construction contracts

In general, there are four stages in tendering for construction contracts:

  1. selection of tenderers

  2. invitations to bid

  3. tender preparation and delivery and

  4. appraisal of tenders, negotiation and decision.

The award of the contract then follows. In a situation where the detailed design is executed by design specialists separately from the construction Contract(s), the designers usually have a strong technical input to the appraisal of tenders for construction

Where contractors are to be selected to undertake both detailed design and construction, on the basis of the basic engineering, the basic engineering designers should be involved in the tender appraisal process. The tenderers’ proposed arrangements for the detailed design work are a critical element in their ability to fulfil the project objectives.

We are concerned here with evaluation of the tendering process, and particularly with questions influencing the way the design is implemented in construction. Some of the questions below might be raised early in the tendering process; others as part of an evaluation at a later date.

11.2.1: Concerning the pre-tender period
  • How is the tendering process to be managed on behalf of, or by, the Owner? Who is responsible?

  • Do the procedures and documents ensure that only competent contractors will be selected?

  • Are the proposed types of contracts in accordance with the project plan? If not, have the changes been thought through?

  • Do the designs and specifications issued for tender purposes describe the work adequately for the proposed types of contracts?

  • Do the tender documents match the other tender documents? Do they provide a basis for free and fair competition?

  • Do the designs and specifications show that the designer has fulfilled its obligations under the design contract?

  • If the detailed designs are not complete:

  • Are the omissions clearly stated?

  • Are the provisions to complete them explicit?

  • Do the tender documents specify any design work which is to be carried out under the Contract?

  • Are quality assurance requirements stated?

  • Are the provisions for approval of Contractors’ designs, equipment and materials laid down?

  • Are the Contractors’ responsibilities clear as regards implementing the design in practice?

  • Are the Contractors’ responsibilities for sub-suppliers similarly clear?

  • Do the instructions to tenderers specify the documents and data to be submitted?

11.2.2: The tender appraisal period
  • Has a satisfactory procedure for appraisal been written and agreed?

  • Have all tenderers received the same additional information if any has been issued during the tender period?

  • Have the following aspects of the tenders been appraised: technical compliance; project organisation, staff and procedures; the execution plan, program and resources; materials sources; subcontracting arrangements; project control methods; quality assurance and control; plant schedule; current workload etc.?

  • Has the commercial appraisal of tenders covered such necessary elements as:

    sufficiency of tender

    • arithmetical checks

    • bill of quantities/whether each item is priced/dayworks schedule

    • cash flow

    • insurances

    • compliance with contract conditions

    • extent of qualifications of tender potential for claims?

  • sufficiency of tender

  • arithmetical checks

  • bill of quantities/whether each item is priced/dayworks schedule

  • cash flow

  • insurances

  • compliance with contract conditions

  • extent of qualifications of tender potential for claims?

  • If there is more than one Contract:

    How are the interfaces covered?

    • What are the arrangements for coordinating the contracts?

    • Which party carries the responsibility?

  • How are the interfaces covered?

  • What are the arrangements for coordinating the contracts?

  • Which party carries the responsibility?

  • How are the Contracts to be managed?

  • What risks are associated with each tender including potential claims? How are these to be offset?

  • How do the tenders compare with respect to maintainability of the completed works and implications for ‘whole life costs’?

As regards cost, the project estimates should have been updated just before tender stage; the tenders are compared with them. If the tenders are over budget some rethinking is required to effect...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex