Chapter 8: Reconsidering procurement criteria and procedures for major infrastructure projects 1

LibraryThe Application of Contracts in Developing Offshore Oil and Gas Projects
Pages97-110
AuthorPhilip Loots,Donald Charrett
8.1: What is a 'successful project'?

Success is largely judged on whether a project has been completed on budget. 2 The budget usually referred to is the initial ‘price’, on which financing is frequently based, together with a contingency; hence the importance placed by the Owner and the project financiers on the ‘price’. But the basis on which the ‘price’ was arrived at is often not explained or clearly understood, and the ‘price’ may be inherently unrealistic and fundamentally flawed from the outset. Flawed because it is not sufficiently aligned with a realistically resourced schedule, is not based on an accurate scope of work or does not contain contingencies for the chosen risk allocation between the parties.

Table 8.1: LNG project cost blowouts

Project

Operator

Original budget, schedule

Final, or currentbudget, schedule

Pluto

Woodside

US$12 bn. late 2010

US$15 bn. April 2012

QCLNG, QLD

BG Group

US$15 bn. 2014

US$20.4 bn. Jan 2015

Gladstone LNG, QLD

Santos

US$16 bn. 2015

US$18.5 bn. Oct 2015

APLNG, QLD

Origin/Conoco Phillips

US$23 bn. mid-2015

US$24.7 bn. Jan 2016

Gorgon, WA

Chevron

US$37 bn. 2014

$US54 bn, first quarter 2016

Wheatstone

Chevron

US$29 bn. 2016

$US29bn, mid 2017

Ichthys

Inpex

US$34 bn. 2016

$US37.4bn. 2017

Source: Australian Business Review and Wall Street Journal (Tuesday 2 February 2016) 9.

In addition, resourced contingency recovery plans frequently do not exist for ‘known-knowns’ which will almost inevitably occur during the construction of a major project e.g. industrial unrest or cyclone events which will delay progress. Emphasis on ‘price’ in reporting on the success or otherwise of a project is likely to be misleading, because data is not given at the same time in relation to the basis on which that price was arrived at. A price may be no more than an initial estimate on which the Owner bears all the risk of cost increases, or one on which the risk of cost increases falls mainly on the Contractor. Unless the basis of pricing is known, communicated and understood, a conclusion may be erroneously drawn that a project is not a success. 3

Merrow 4 gives five figures of merit in evaluating the success of projects: cost growth, cost competitiveness, schedule slippage, schedule competitiveness and production attainment.

8.2: Why is 'price' currently used as the major comparator in the decision to award contracts?

While searching for reasons for apparent cost and time overruns on major projects 5 it has become obvious that insufficient work is done in preparation for the award of contracts. As we will see below, ‘price’ generally tends to dominate the bid evaluation process. Bid evaluations made predominantly on the initial ‘price’ are likely to create false expectations. Perhaps the reason that ‘price’ is used as the leading comparator is because of the apparent convenience and simplicity of ‘price normalisation’ in the bid evaluation process, and the ease of comparison of ‘normalised prices’ offered by bidders.

A clear definition of the scope of work at the outset – the work that has to be done within the scope of the Contract – is essential to certainty of ‘price’ and schedule. But a clear definition of ‘what will be done when’ is equally, if not more important to certainty that the end date will be met.

There have been numerous attempts to identify those factors that contribute to project success or failure or reduce the incidence of disputes. 6

8.2.1: Life-cycle costs

Owners who procure constructed facilities are ultimately interested in maximising the economic return from their investment over the life cycle. A government procuring public infrastructure aims to obtain the best value for money in order to maximise the benefit to society from the limited funds available. The private sector invests in facilities in order to sell a product and make a profit.

The design and construction of a facility is only the start of an operating life that may span many years. There is increasing emphasis in modern society on sustainability and reducing the carbon footprint of human activities, and this is driving a trend to design facilities for longer life cycles. 7 This focuses attention on the life-cycle costs of a facility – the incremental costs of a longer design life may result in significantly lower life-cycle costs.

The life cycle of a typical facility can be divided into three distinctly different stages: design, construction and operations. The operations stage includes maintenance to sustain operations, refurbishment to restore operations and decommissioning and demolition after operations are not economically viable. Thus, lifecycle costs include the costs of design, construction and operations. The traditional method of project procurement is to focus on the cost of design and construction. However, this does not consider the major component of life-cycle costs: the operations stage.

The design of a facility has a pervading influence, not just on the cost of construction, but even more importantly, on the life-cycle costs. In many construction projects there is a well-known trade-off between the capital cost of construction, and the life-cycle costs: cheaper construction costs, achieved by the selection of less durable materials or less robust equipment, often lead to significantly higher maintenance and operating costs and ultimately a higher life-cycle cost.

The significance of design and construction cost in relation to a project is succinctly encapsulated in the 1:10:100 ‘rule’:

Over one typical ‘life cycle’ of a facility, for every one dollar $1 spent on design, at least ten dollars $10 are spent on construction and at least one hundred dollars $100 are spent on OM&R [operation, maintenance and repairs/refurbishment]. 8

Thus, inadequate time spent at the early design stage may not only result in a sub-optimal design with higher construction costs, it may also result in significantly higher life-cycle costs during the operations stage. This is a further reason why allowing adequate time and resources at the conceptual stage (front-end loading) are so fundamental to a successful project outcome.

Dr John Miller discussed reasons why governments will be increasingly pushed to procure infrastructure on a lowest lifecycle cost basis, including:

Near exclusive use of initial delivery procurement cannot succeed financially because design and construction is inexorably followed by the even more expensive operations, maintenance and repair stage;

Infrastructure properly procured on a lifecycle basis produces 30%–40% savings. 9

Key findings from relatively recent research identified five leading ‘major pressure points’ (obstacles that stand in the way) at all stages of a project’s life cycle. These are:
  • a shortage of skilled resources

  • inadequate scoping

  • use of inappropriate delivery methods

  • poor risk allocation and

  • unrealistic time and cost objectives. 10

The conclusion of this study is that these issues are also strong contributors to adverse outcomes such as delays in completion, cost overruns, and disputes.

But are we asking the right questions when trying to determine the main issues that constrain the success of construction and infrastructure projects?

8.3: The common perception of 'price'

Why does ‘Contract price’ not mean what you think it does? ‘Price’ for what quality? ‘Price’ for what operability and productivity?

‘Price’ may be defined in many different ways. The ‘price’ might not be what it appears to be. How the ‘price’ is defined – the allocation of risk, and whether it is a lump sum or remeasurable price needs to be clearly defined and understood, as well as what work is included and what is excluded from the scope, and what the mechanism is for change. For example, a bid ‘price’ based on an Owner’s bill of quantities which contains underestimated quantities will result in a higher final ‘price’ to be paid by the Owner without any directed change having taken place. Those increased quantities may also affect the schedule.

A well-known Australian example of a major infrastructure project commonly perceived to have suffered a major cost overrun is Parliament House in Canberra, opened in 1988. The initial budget cost was AU$151 million in May 1978, and the actual final cost was AU$1,076 million. However, no meaningful comparison can be made between these figures because of fundamentally different scopes and qualities of work, and no allowance in the initial budget for cost escalation, contingencies or scope changes. For example, 45 per cent of the final cost was a consequence of escalation in building costs from inflation of 1978 prices. 11

The contracting strategy will also have a profound impact on ‘price’ and schedule risk; the differences in risk pricing options and allocation between EPC and EPCM contracts is often not fully appreciated. 12 A common assumption and misconception is that an EPC contract is a lump sum price. This is by no means always the case, and many EPC contracts contain fixed-fee cost reimbursable prices.

Aligning the contract delivery method with the scoping of the project has been identified as a key ingredient for success.

The primary focus at the early stages of a project is usually on the technical aspects of the bid. Commercial issues are often evaluated separately from the technical issues, without adequate communication and management of the interface. If the bid is technically acceptable, ‘bid normalisation’ adjustments to the bid ‘price’ may be made by the Owner for the more obvious errors and omissions, but without fully understanding the effect of such adjustments on the bidder’s resources and execution strategy. The Owner...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex