Savoye and Savoye Ltd v Spicers Ltd

JurisdictionEngland & Wales
JudgeMr Justice Akenhead
Judgment Date15 December 2014
Neutral Citation[2014] EWHC 4195 (TCC)
Docket NumberCase No: HT-14-311
CourtQueen's Bench Division (Technology and Construction Court)

[2014] EWHC 4195 (TCC)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

Mr Justice Akenhead

Case No: HT-14-311

Between:
Savoye and Savoye Limited
Claimants
and
Spicers Limited
Defendant

Anneliese Day QC (instructed by Reed Smith LLP) for the Claimant

Jonathan Acton Davis QC (instructed by Olswang LLP) for the Defendant

Hearing date: 3 December 2014

Mr Justice Akenhead
1

The Claimants, Savoye (a French company) and Savoye Ltd (a related British company) (together "Savoye") seek to enforce an adjudicator's decision in its favour against Spicers Ltd ("Spicers"). The only issue is whether the underlying contract between the parties was a construction contract involving "construction operations". This issue revolves around the application of the proper meaning of the term "construction operations" in Section 105 of the Housing Grants, Construction and Regeneration Act 1996 (" HGCRA") in the context of the facts and the contract between the parties.

Factual Background

2

Spicers is, in a substantial way, in the business of distributing office supplies and equipment. It has a number of warehouses, including one at Smethwick, West Midlands. At Smethwick, its business is mainly storing a very large number and range of products which have come from wholesalers, manufacturers and importers for distribution to other wholesalers, albeit that some of the products are provided direct by Spicers to clients.

3

By a written contract dated 3 January 2013 ("the Agreement"), Spicers engaged Savoye to design, supply, supervise and commission a new conveyor system at its existing factory site in Dartmouth Road, Smethwick, West Midlands. Spicers had invited Savoye amongst others to tender on 11 July 2012 and, by its Proposal (12-P-049 Rev 7), Savoye submitted its tender which was accepted. Clause 2.9 contained an express agreement "that the Equipment and Services to be provided by [Savoye] hereunder are exhaustively defined in the Agreement and Proposal, the provision of any other item necessary for the performance of the Agreement being under Spicers' responsibility". Clause 2.1 required Savoye to "supply the Equipment and the Services in accordance with the Agreement". The Contract Price was identified in Clause 5.1 (a) as £2,370,801. It is, rightly, common ground that Savoye was required to install the Equipment, Clause 6.5 identifying that when "the Equipment has been delivered and installed in accordance with the Agreement, and has passed all required inspection and testing, it will be accepted by Spicers". There were provisions requiring Savoye to rectify defects in or damage to the Equipment and Services. Clause 21 provided for dispute resolution with senior management first to discuss the matter to resolve disputes, Clause 21.2 then providing as follows:

"In the event that no settlement is reached under clause 21.1 and if the Agreement is a "construction contract" as defined in Section 104 of the [HGCRA] either party may refer any dispute or difference arising in relation to any matter under the Contract for adjudication, in which case the adjudication provisions of the TeCSA Adjudication Rules…shall apply…"

Otherwise, the Agreement was by Clause 22.1 "subject to the non-exclusive jurisdiction of the English courts".

4

The tender Proposal, incorporated into the Agreement, was a 50 page document which contained layouts both of the ground floor and a smaller mezzanine floor at the factory. It is clear that the mutual anticipation was that the Equipment to be installed would cover a very substantial part of both floors. What was intended to be provided was "an automated conveyor system for the order fulfilment of office products" (Page 3/50 of the Proposal). The same page identified that as part of a programme of improvements to its operations network:

"Spicers is developing its site at Smethwick in two ways:

Firstly through increasing the storage capacity of the site by building a warehouse extension at the back of the existing building.

Secondly, by increasing the speed and throughput capability of the site's conveyor systems through modernisation & replacement. This development is essential to facilitate the Smethwick site taking on additional activity."

5

The extension to be attached to the existing warehouse was to be built by others before Savoye started its installation and the installation to be provided by Savoye was in the existing warehouse building. To some extent, existing shelving remained to be used by Spicers. Once the new extension was built, much of the product that was in the existing building was to be taken out and stored in new high racking in the new extension.

6

The existing warehouse into which Savoye was to put its installation was a large rectangular open space warehouse (albeit with some offices and reception areas); the open space was (judged by eye) approximately 125m by 175m and there was, broadly over the middle area, a substantial mezzanine floor. That mezzanine floor comprised steelwork with substantial chipboard floor decking and there was extensive racking on that floor. The ground floor was concrete. A reasonable description of the installation to be provided by Savoye is as follows:

(a) The conveyor system was to be automated and computer-controlled so that an order from a customer could be relayed into the system, creating initially a cardboard carton to be forwarded on to the conveyor system, marked with a specific bar code which would then be read at a number of points along the conveyor line, directing it to those parts of the conveyor system where the particular goods which were to go into the carton were located. Once the goods had been placed, manually by workers, into the carton, the carton would be automatically directed towards the end of the conveyor system where a lid would be put on it and labels attached, whence it would be directed out to loading bays and onto lorries.

(b) The conveyor system itself was, on the ground floor, to run in three very long loops; on each loop, one side is referred to as the "picking" side and the other the "replenishment" side. This is explicable because the workforce fulfilling the orders would be on the picking side, placing the required items into the passing cartons, having taken them from racks above the conveyor line; the overhead horizontal part of the racking passed over the conveyor line to the other side where the goods could be replenished by other workers on the replenishment aside. The three loops, although long and extensive, simply housed a wide variety of different items of merchandise.

(c) The three ground floor conveyor loops at one end were located about 1m from the ground but at the end adjacent to the new extension warehouse the metal framework on which they were located was raised up to 2m or possibly a little more as each loop came around from the picking side to the replenishment side.

(d) The conveyor system on the ground floor was also connected by conveyors which went up to the mezzanine floor through an aperture created for the purpose and it then ran virtually the full length of the mezzanine floor. At this level, the cartons could be loaded with, what I understood to be, more "high end" or valuable items. Once the carton had been loaded on that level, the conveyor system took it down to the ground floor.

(e) In addition to the actual conveyor lines, there were substantial and/or important other pieces of equipment. These were, principally:

(i) The PAC 600 and ID Pac which are large and small carton erectors, located at the beginning of the conveyor lines. They rest on the floor under their own weight. The PAC 600 belonged to Spicers but it had to be removed by Savoye and substantially refurbished before being returned to the site; it needed either one 5 ton or two 2.5 ton capacity machines to move it and, I assume therefore that its weight was approaching 5 tons. It was about 8m long, 2m wide and 3m high. The ID Pac was some 4–6m long, 2m wide and 2m high and, I infer, weighed about 3–4 tons. Both were connected to the overall system by compressed air, electrical power and IT connections.

(ii) The routing label printer and applicator was located near the start of the conveyor system and is connected by compressed air, electrical and data feed lines. It rests under its own weight, its structure being broadly in the form of a tripod, which was not bolted down to the floor.

(iii) There are two weight scales. They are part of the conveyor line, having conveyor rollers on them and weigh the empty and later fuller cartons as they pass towards and from the picking lanes. They are connected by electrical and data lines to the overall system. The weighing provides a cross check as to whether all or all the right items have been put into a given carton.

(iv) The "Jivaro" machines are located towards the end of the conveyor lines and places lids automatically onto the now filled cartons. These are not, as such, fixed to the ground, resting on the ground under their own weight, but they are connected with electrical, and data lines into the overall system. They are about 6 to 7m long, 2 m high and, at their widest, about 3m wide. They are likely to weigh several tons each and, as the evidence indicated, they could not readily be moved without a significant amount of dismantling first.

(v) There are logo printers in the line after the Jivaro machines which are connected by power and data lines into the overall system. They are not, as such, bolted to the floor, although they have to be located right beside the conveyor lines because, as their description suggests, they have a facility to print (with quick drying ink) onto the cartons.

(vi) Finally, there is a shipping label printer which prints and attaches despatching information on to the...

To continue reading

Request your trial
4 cases
  • Fahstone Ltd v Biesse Group UK Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • December 18, 2015
    ...the installation of the Uniwin was or was not a construction operation. The authorities 37 The leading case on this topic is Savoye and Savoye Ltd v Spicers Ltd [2015] BLR 151, a comprehensive and authoritative decision of Mr Justice Akenhead. That case concerned a contract for the design, ......
  • Crystal Electronics Ltd v Digital Mobile Spectrum Ltd
    • United Kingdom
    • King's Bench Division (Technology and Construction Court)
    • October 27, 2023
    ...structures or other apparatus on which the works were undertaken form, or were to form, part of the land. 36 In Savoye v Spicers Ltd [2014] EWHC 4195 (TCC), [2015] BLR 151, Akenhead J considered in detail the relevant authorities concerning the phrase “forming part of the land” and conclud......
  • Savoye and Savoye Limite v Spicers Limite
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • January 15, 2015
    ...LLP) for the Defendant Submissions in writing Mr Justice Akenhead 1 I handed down judgment in this matter on 15 December 2014 ( [2014] EWHC 4195 (TCC)). The parties have exchanged written submissions concerning costs. It is common ground that this Court should summarily assess the costs. I......
  • JFC Builders Pte Ltd v Permasteelisa Pacific Holdings Ltd
    • Singapore
    • High Court (Singapore)
    • November 7, 2016
    ...of the Act. Two cases were relied on by the defendant. The first was the decision of Akenhead J in Savoye and another v Spicers Ltd [2015] Bus LR 242 (“Savoye”). In that case, Spicers Ltd (“Spicers”) had engaged the claimants (“Savoye”) to design, supply, supervise and commission a new conv......
2 firm's commentaries
  • Projects And Construction Law Update
    • United Kingdom
    • Mondaq UK
    • February 12, 2015
    ...does give pause for thought. To view the full text of the decision please click here. Savoye and Savoye Ltd v Spicers Ltd [2014] EWHC 4195 (TCC) Here Akenhead J had to consider whether the contract which was the subject of the dispute was a construction contract involving "construction oper......
  • Spring 2015 In Site
    • United Kingdom
    • JD Supra United Kingdom
    • February 19, 2015
    ...The relatively limited case law on what this entails has been developed in the recent case of Savoye and Savoye Ltd v Spicers Ltd [2014] EWHC 4195 (TCC) in the context of the “industrial plant” component of the definition in Section 105(1)(b). The case also considers the extent to which it ......
3 books & journal articles
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • April 13, 2020
    ...[279]–190 [282], per hhJ hornton QC. 274 Coleraine Skip Hire Ltd v Ecomesh Ltd [2008] NIQB 141. 275 Savoye & Savoye Ltd v Spicers Ltd [2014] EWhC 4195 (TCC) at [21], per akenhead J. It has been held that “the land” does not include the sea bed below the low-water mark: Staveley Industries p......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • April 13, 2020
    ...667 at 684 III.26.98 Savory v holland hannen and Cubbits (Southern) Ltd [1964] 1 WLr 1158 II.8.138 Savoye & Savoye Ltd v Spicers Ltd [2014] EWhC 4195 (TCC) II.6.79 Savoye & Savoye Ltd v Spicers Ltd [2015] EWhC EWhC 33 (TCC) III.26.268, III.26.282 Sa Water Corporation v United Water Internat......
  • Building and Construction Law
    • Singapore
    • Singapore Academy of Law Annual Review No. 2016, December 2016
    • December 1, 2016
    ...Pte Ltd v Newcon Builders Pte Ltd [2016] SGHC 246 at [153]–[154]. 22 Cap 30B, 2006 Rev Ed. 23 [2016] SGHC 247. 24 [2001] BLR 407. 25 [2015] Bus LR 242. 26 [2013] QCA 406. 27 JFC Builders Pte Ltd v Permasteelisa Pacific Holdings Ltd [2016] SGHC 247 at [31]. 28 JFC Builders Pte Ltd v Permaste......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT