Scotrail Trains Limited 8 March 2024

Date08 March 2024
Head Office:25 Cabot Square, London E14 4QZT: 020 7282 2000 orr.gov.uk
Claire Brooks
Access Executive
8 February 2024
Iain Sheilds
Customer Manager
Network Rail Infrastructure Ltd
151 St Vincent Street
Glasgow
G2 5NW
John Kerr
Regulated Contracts Manager
Atrium Court
50 Waterloo Street
Glasgow G2 6HQ
Dear Iain and John
Approval of the 42nd supplemental agreement to the track access contract
between Network Rail Infrastructure Limited and ScotRail Trains Limited
dated 3 March 2016
We have today approved the above supplemental agreement submitted to us formally on 7
February 2024 under section 22 of the Railways Act 1993 (the Act). This follows an earlier
informal submission of a draft agreement for our consideration. This letter explains the
reasons for our decision.
Purpose
The purpose of this agreement is to extend ScotRail’s single contingent rights from SCD
2024 to PCD 2024 Edinburgh Waverley to Dunbar route only, in line with the Network Rail
ECML access rights policy. This is effected by replacing Table 2.2 in Schedule 5 with a
new table in which the footnote indicating when the rights expire is amended from SCD
2024 to PCD 2024
Industry consultation
Network Rail undertook the usual industry consultation, no concerns were raised.
ORR review
Our review of the application raised no operational, performance or economic concerns.