Sky UK Ltd v Riverstone Managing Agency Ltd
| Jurisdiction | England & Wales |
| Court | Court of Appeal (Civil Division) |
| Judge | Lord Justice Popplewell,Lord Justice Phillips,Lord Justice Snowden |
| Judgment Date | 16 December 2024 |
| Neutral Citation | [2024] EWCA Civ 1567 |
| Docket Number | Case Nos: CA-2023-001847, CA-2023-001856, CA-2023-001862 |
Lord Justice Popplewell
Lord Justice Phillips
and
Lord Justice Snowden
Case Nos: CA-2023-001847, CA-2023-001856, CA-2023-001862
IN THE COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
COMMERCIAL COURT (KBD)
HIS HONOUR JUDGE PELLING KC, SITTING AS A JUDGE OF THE HIGH COURT
Royal Courts of Justice
Strand, London, WC2A 2LL
David Edwards KC, Crispin Winser KC and Simon Kerr (instructed by Herbert Smith Freehills LLP) for the Claimant/Appellant (705 Claim: Sky)
Paul Reed KC, Ebony Alleyne and James Shaw (instructed by Clyde & Co LLP) for the Claimant/Appellant (536 Claim: Mace)
Andrew Rigney KC, Simon Goldstone and Patrick Maxwell (instructed by DAC Beachcroft LLP) for the Defendants/Respondents/Cross Appellants (705 Claim)
Hearing dates: 15, 16, 17 and 18 October 2024
Introduction
This is an appeal against the Order of HHJ Pelling KC (‘the Judge’) dated 24 August 2023 in respect of claims made by Sky UK Limited (‘Sky’) and Mace Limited (‘Mace’) under a construction all risks policy (‘the Policy’) underwritten by the defendant insurers (‘the Insurers’). The claims were in respect of extensive water damage to the roof of Sky's global headquarters building, known as Sky Central, built on the Sky Campus in Osterley, West London. Sky Central was constructed for Sky in 2014 to 2016 by Mace as main contractor under a JCT 2011 Design and Build Contract dated 17 March 2014 (‘the construction contract’). Mace was a named insured under the Policy.
Section 1 of the Policy covered contract works. The Insuring Clause for section 1 provided:
“The Insurers shall, subject to the Terms of this Contract of Insurance, indemnify the Insured against physical loss or damage to Property Insured, occurring during the Period of Insurance, from any cause whatsoever ….
Basis of Settlement
In settlement of claims under this Section of the Contract of Insurance the Insurers shall, subject to the terms and conditions of the Contract of Insurance, indemnify the Insured on the basis of the full cost of repairing, reinstating or replacing property lost or damaged (including the costs of any additional operational testing, commissioning as a result of the physical loss or damage which is indemnifiable hereunder) even though such costs may vary from the original construction costs ….”
The “Property Insured” was defined as being:
“Permanent works, materials (including those supplied free to the Project by or on behalf of the Principal, provided the value is included in the Contract Works Sum Insured), temporary works, equipment, machinery, supplies, temporary buildings and the contents thereof, camps and the contents thereof and all other property used for or in connection with the Project.”
The Period of Insurance was defined as comprising an “initial period” of insurance, essentially running until the completion of the works including commissioning and testing, and a “maintenance period” comprising a period of one year thereafter. Although the terms of cover were not identical for the two periods, the parties agreed that the claim should be determined as if they were. It was common ground that the Period of Insurance for the purpose of the Insuring Clause in Section 1 ran from 1 February 2014 (commencement of the project) to 15 July 2017 (one year after completion). I shall refer to this, as the Judge and parties did, as ‘the POI’.
At the heart of the disputed issues was the extent of damage at the conclusion of the POI and the quantification of recoverable loss in respect of any such damage. The roof was made up of 472 individual wooden cassettes, into a substantial number of which water had entered and remained for periods during construction, leading to wetting of internal timbers and, so Sky and Mace alleged, irreversible swelling and structural decay by the end of the POI. There was a dispute as to whether this wetting was itself damage, or caused damage, during the POI. It was common ground, however, that there was damage or further damage which occurred after the POI as a result of the wetting which had occurred during the POI: in the period between expiry of the POI and trial, the condition of the timbers worsened, and the moisture spread. The parties referred to this as deterioration and development damage. For the sake of precision and clarity I will use deterioration to refer to damage or additional damage in parts of the timbers already wet or damaged, for example wetting leading to swelling or to structural decay in the wet or swollen parts of the timber; and development to refer to damage to additional parts of timbers by way of spread, for example by way of capillary migration of moisture in timbers or vapour condensing so as to wet new timbers or parts of timbers.
Two aspects are worth emphasising at the outset. First, the ingress of water very largely occurred during construction and therefore during the POI. There was little, if any, relevant ingress after expiry of the POI. Secondly, Insurers do not allege that Sky or Mace failed to take reasonable steps to mitigate loss, or that they in any way failed to act as prudent uninsureds. It is obvious that damage of the kind involved in this case would require some time to address and redress, first by way of investigation as to the nature and extent of the damage; then by design of a remedial scheme of works which was reasonable not only in relation to the physical state of the building but also in relation to the effect of the remedial works on what was a working building including a news studio; and finally by the implementation of such a remedial scheme. This is so irrespective of any dispute between the parties. The issues in the appeal therefore fall to be decided on the basis that the condition of the roof at the time of trial was wholly or very largely the natural and foreseeable consequence of the ingress of water during the POI, and the cost of remedying the condition of the roof as it existed at the time of trial was not in any respect attributable to any failure on the part of Mace or Sky to act reasonably.
At trial Sky and Mace advanced alternative schemes for remedying the situation. Each involved substantial works to the roof. The Mace scheme involved the repair or replacement of damaged wooden components and was costed on the basis that repairs would be required to all 472 cassettes. Mace claimed its own loss by reference to this scheme (‘the Mace Scheme’). Sky advanced an alternative scheme, as cheaper than the Mace Scheme, which involved the replacement of all of the 472 wooden cassettes with new metal cassettes (‘the Sky Scheme’). Sky and Mace advanced their claims on the basis that they were entitled to recover the cost of addressing all damage to the roof structure, including deterioration and development damage which occurred after the expiry of the POI and up to the date on which any remedial works were completed.
The Insurers contended that Mace was not insured under the Policy in respect of any of the sums for which it sought indemnity and was not entitled to any relief. The Insurers' case was that Sky was entitled only to an indemnity in respect of the costs of addressing damage as it existed at the end of the POI. The Insurers put forward a costed scheme of works as a measure of such costs (‘Insurers 2017 Scheme’), based on a retrospective analysis of the likely extent of such damage at the expiry of the POI carried out by the Insurers' wood science expert, Mr James Coulson. The Insurers also analysed how to address such damage as was found to be present following the completion of an extensive drying out process which took place in 2018/9 (‘Insurers 2019 Scheme’). The Insurers selected that point in time because there was contemporaneous evidence of the condition of cassettes in 2018/9 in the form of photographs and moisture readings. The extent of damage had increased after the end of the POI, so the remedial works needed in 2019 would, on the Insurers' case, be greater than in July 2017. Insurers 2019 Scheme involved work to 383 of the 428 cassettes on the main roof.
There was a further issue as to whether a deductible (“Retained Liability”) of £150,000 “any one event” applied once to the whole of the claim or applied separately in respect of damage to each cassette.
The claims made by Sky and Mace were case-managed and tried together at a trial of both liability and quantum before the Judge, which took five weeks. He handed down a reserved judgment and gave three further judgments in relation to consequential applications and disputes. I shall return to aspects of the Judge's findings in more detail, but in summary he held as follows.
(1) There was damage to the cassettes at the end of the POI. The Judge rejected the Insurers' case that “damage” within the meaning of the Insuring Clause required a physical change which so compromises the performance of an individual cassette that, in order to perform the function for which it was intended, it required repair; in other words that it had reached a stage which impaired the structural performance and integrity of the cassette. The Judge held that there is “damage” within the meaning of the Insuring Clause if a tangible physical change has occurred to the property insured (irrespective of whether that is visible...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Aercap Ireland Ltd v Aig Europe S.A. & Others
...developing from [the peril insured against] after the policy period would still be covered.’ 942 Recently, in Sky UK Limited v Riverstone Managing Agency Ltd [2024] EWCA Civ 1567, the Court of Appeal held that deterioration and development of damage to roof timbers occurring after the perio......
-
Nord Stream AG v Lloyd's Insurance Company S.A (on its own behalf and on behalf of all insurers subscribing to the Offshore Operating All Risks policy with unique market reference number B1526ENNMG1900542, the insurer subscribing to Offshore Operating All Risks policy with unique market reference number B1526ENNMG1900745, and all primary section I Property Damage and Section II Terrorism insurers subscribing to the declaration with unique market reference B080114454J19 (as extended by endorsement) attaching to delegated underwriting contract numbers B080110351J19, B080110351J20, B080110351J21, and B080110351J22)
...obligation attaches, which it promises will not occur”: Popplewell LJ in Sky UK Ltd v Riverstone Managing Agency Ltd [2024] EWCA Civ 1567; [2024] 2 CLC 906 at 117 The Defendants accepted in their written opening that there is no “ express” insuring clause in Section I. It was submitted for......
-
Wrbc Corporate Member Ltd (as the sole underwriting member of W.R Berkley Syndicate 1967 at Lloyd's for the Lloyd's 2019 Year of account) v (1) Axa XL Syndicate Ltd (as the sole corporate member of Lloyd's Syndicate 2003 for the 2019 year of account)
...Insurance Plc [2024] EWCA Civ 1281 at paragraph 18. 23 A good example of this in the insurance context is Sky UK Limited v Riverstone Managing Agency Limited [2024] EWCA Civ 1567 which has a certain resonance with the case before me. Here, the Court of Appeal considered the meaning of the p......
-
Court of Appeal clarity on CAR policy interpretation: Sky v Riverstone [2024]
...shown to have been caused by the construction work and then continued to get worse, should be covered under a CARSky UK Ltd v Riverstone Managing Agency Ltd [2024] EWCA Civ 1567 the Court of Appeal has provided welcome clarification on several key issues relating to policy interpretation. B......
-
Chapter 9. Insurance claims
...sought compensation from the Financial Services Compensation Scheme,which agreed that the VAT3 Sky UK Ltd & Anor v Riverstone Managing Agency Ltd & Ors [2024] EWCA Civ 1567 [43] (Popplewell citing Chandris v Argo Insurance Co Ltd [1963] 2 Lloyd’s Rep 635, 73–4 (Megaw J) and Firma C-Trade SA......
-
Table of Cases
...Construction UK Ltd v Egger (Barony) Ltd [2002] EWCA Civ 1914, 18 December 2002 (unreported) 387 Table of Cases xxxv Sky UK Ltd & Anor v Riverstone Managing Agency Ltd & Ors [2024] EWCA Civ 1567 316, 323 Slater v Finning Ltd [1996] UKHL 59, [1997] AC 473 43, 44 Smith, Hogg & Co v Black Sea ......