SONI Licence Condition 16 – Grid Code Modification Determination (FERA)

Published date15 June 2022
Energy SectorElectricity Networks
__________________________________________________________________________________
Northern Ireland Authority for Utility Regulation
Queens House, 10-14 Queen Street, BELFAST, BT1 6ED
T: +44 (0) 28 9031 1575 F: +44 (0) 28 9031 1740 W: www.uregni.gov .uk
Marie Therese Campbell
SONI Ltd
Castlereagh House
12 Manse Road
Belfast
BT9 5HT
Date: 08/06/2022 Our Ref: NET/E/TH/525
Dear Marie Therese
RE: Request to the Authority
1
by SONI for a decision on a Condition 16 Grid Code
modification regarding the Reduction of Aggregator limits from 4MW to 1MW.
Thank you for your email received 22 March 2022 in regards to the proposed modification
to the SONI Grid Code, for the Reduction of the Aggregator Limit from 4MW to 1MW. Your
email contained a Final Modification Report, including representations received by SONI
from the modification consultation.
The Modification
On 14 October 2021, SONI received a modification proposal to the SONI Grid Code
definitions of Aggregated Demand Site, Aggregated Generating Unit, Demand Side Unit,
Demand Side Unit Operator and Generator Aggregator. The modification proposal was
submitted to SONI by Powerhouse Generation Limited. Representing Federation of
Energy Response Aggregators (FERA).
The modification sets out to modify the definitions of the below units within the SONI Grid
Code:
1
In this letter the words “we”, “us” “our” and Authority are used interchangeably to refer to the Northern Ireland