Sylvia Shipping Company Ltd v Progress Bulk Bonding Ltd

JurisdictionEngland & Wales
JudgeMr Justice Hamblen,MR JUSTICE HAMBLEN
Judgment Date18 March 2010
Neutral Citation[2010] EWHC 542 (Comm)
Docket NumberCase No: 2009 : FOLIO 846
CourtQueen's Bench Division (Commercial Court)
Date18 March 2010
Between
Sylvia Shipping Co Limited
Claimant
and
Progress Bulk Carriers Limited
Defendant

[2010] EWHC 542 (Comm)

Before: Mr Justice Hamblen

Case No: 2009 : FOLIO 846

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

COMMERCIAL COURT

Mr John Passmore (instructed by Jackson Parton) for the Claimant

Mr Chirag Karia (instructed by Marine Law) for the Defendant

Hearing dates: 5 th March 2010

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

MR JUSTICE HAMBLEN Mr Justice Hamblen

Mr Justice Hamblen :

Introduction

1

The Claimants (“Owners”) appeal in respect of questions of law arising out of an arbitration award dated 28 April 2009 (“the Award”) of Messrs Alan Oakley and William Wingate (“the Tribunal”).

2

The Award concerned various claims and counterclaims made by the Owners and the Respondents (“Charterers”) in relation to a time charterparty on an amended NYPE (1946) form dated 22 February 2000 (“the charterparty”) of the vessel mv “SYLVIA” (“the vessel”).

3

The Tribunal held that Owners had failed to exercise due diligence and had breached their contractual maintenance obligations, under lines 22–23 and 37–38 of the charterparty, in failing to maintain the steel-work within the cargo holds leading to a delay in readiness of the vessel to load a cargo of wheat at Baie Comeau. As a result a sub-charter made by the Charterers with Conagra Trade Group Inc (“Conagra”) was cancelled when the vessel missed the laycan dates. The Charterers claimed for loss of profit on the cancelled Conagra sub-charter and the Tribunal held that the claim succeeded to the extent of USD 273,706.12. It this part of the Award which is the subject of appeal.

4

The essential issue which arises on the appeal is the proper approach to damages in these circumstances and in particular whether damages based on the loss of a sub-fixture made are too remote in law. The Owners contended, in reliance upon the House of Lords decision in The Achilleas [2009] 1 AC 61, that the recoverable damages were limited to the difference between the charter and the market rate during the period of delay.

Factual background

5

The essential facts as found in the Award are that the Owners chartered the vessel to the Charterers on a period time charterparty dated 22 February 2000. The vessel was a single deck bulk carrier of 22,525 mt dwt, with 5 holds, built in 1981.

6

The charterparty was initially for 2–4 months +/-15 days, but was later extended. The last extension was made by way of an addendum dated 13 June 2003, under which the charterparty was extended for a further period of minimum/maximum 11/13 months in Charterers’ option at a hire rate of USD 5,900 per day.

7

On 11 March 2004 the vessel loaded a cargo of green petcoke at Anacortes, Washington, USA, for discharge at Port Alfred, Quebec Province, Canada.

8

On 30 March 2004, Charterers entered into a sub-voyage charter with Conagra for the carriage of a cargo of wheat from Baie Comeau to Casablanca, with a laycan spread of 14–22 April 2004. On 13 April 2004, Charterers declared the next loadport as Baie Comeau.

9

The vessel arrived at Port Alfred on 14 April 2004. Discharge commenced at 0010 on 15 April 2004.

10

On 15 April 2004 a Port State Control (“PSC”) inspection was carried out, which found 3 structures in the holds to be wasted.

11

Discharge and cleaning of the holds was completed 16 April 2004. On the same day, the Canadian Food Inspection Agency rejected 4 of the vessel's 5 holds for loading of grain and grain products. In response, Owners appointed contractors (who had cleaned the holds) for de-scaling work.

12

On 19 April 2004, the vessel arrived at Baie Comeau. The holds were inspected by PSC, who issued a detention order at 1500 that day due to violation of section 19 of SOLAS, recording that “Main Structure wasted in cargo holds Nos 1, 3 and 4”. Repairs were commenced on 22 April 2004.

13

Also on 22 April 2004, Conagra cancelled the sub-charter. On 23 April 2004, Charterers entered into a substitute fixture for the vessel with York Ltd (“York”) for one time charter trip to Lome, with delivery passing Baie Comeau anchorage outbound between 29 April and 3 May 2004.

14

Hold repairs were accepted as complete by Class and PSC at 1430 on 26 April 2004.

15

In relation to breach the Tribunal found that:

“7.17 We therefore find that the vessel's schedule was not sufficiently tight to have prevented the Owners from being able to have carried out maintenance of the steel work within the cargo holds.

7.18 WE THEREFORE FIND AND HOLD THAT THE OWNERS HAD NOT EXERCISED DUE DILIGENCE AND THAT THEY HAD BREACHED THEIR CONTRACTUAL MAINTENANCE OBLIGATIONS UNDER LINES 22–23 AND 37–38 OF THE CHARTER PARTY.”

16

In relation to remoteness the Tribunal found that damages associated with the loss of the Conagra fixture were “foreseeable” and “within the first limb of “Baxendale”“.

17

They further found that:

“8.11 In our opinion alarm bells should have been ringing loud and clear immediately after the Canadian PSC inspector issued the Form 5 on the 15 th April. As there was a tick in the box for Class being required that should have been attended to immediately. Repairs needed could have/would have been identified while the vessel was at Port Alfred and probably have commenced at that port.

8.12 In the circumstances, we found that had the Owners taken positive and realistic action when the problems were formally identified at Port Alfred, the repairs would in all probability have been completed within the Conagra laycan. We also found that the Owners did not keep the charterers fully or properly informed as to what was really taking place and thereby denied them the opportunity to attempt to negotiate an extension of the laycan.

8.13 In conclusion, WE FIND AND HOLD THAT THE OWNERS ARE LIABLE TO THE CHARTERERS FOR DAMAGES ASSOCIATED WITH THE LOSS OF THE CHARTER WITH CONAGRA.”

18

As to the quantum of damages, they found that the Conagra voyage would have taken 23.7467 days and have yielded a net revenue of USD804,222.05, resulting in a time charter equivalent rate of USD33,866.69 per day.

19

The Tribunal found that earnings made on the substitute charter with York had to be credited against the loss of revenue claimed. The net hire rate under the York charter was USD22,340.62 per day. The difference was therefore USD11,526.07 per day and, on the basis of credit being given throughout the period which the Conagra charter would have taken, they “found the Charterers loss to be: 23.7467 days x US$ 11,526.07 = US$ 273,706.12.”

The law on remoteness

20

The law on remoteness of damages in contract has long been based on the judgment of the Court of Exchequer in Hadley v Baxendale (1854) 9 Ex 341 as refined in subsequent cases, and in particular the House of Lords decision in Czarnikow v Koufos, The Heron II [1969] 1 AC 350.

21

In the classic statement of the rules regarding remoteness Alderson B in Hadley v Baxendale said at p354–55:

“… where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, i.e. according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result of the breach of it. Now, if the special circumstances under which the contract was actually made were communicated by the claimants to the defendants and thus known to both parties, the damages resulting from the breach of such a contract, which they would reasonably contemplate, would be the amount of injury which would ordinarily follow from a breach of contract under this special circumstances so known and communicated. But, on the other hand, if these special circumstances were wholly unknown to the party breaking the contract, he, at the most, would only be supposed to have had in his contemplation the amount of injury which would arise generally, and in the great multitude of cases not affected by any special circumstances, from such a breach of contract.”

22

In The Heron II Lord Reid clarified the law on the degree of likelihood required in order that a claimant may recover damages for a particular type of loss. In a well known passage he said that the proper test is whether the loss in question is (at p382G-383A):

”of a kind which the defendant, when he made the contract, ought to have realised was not unlikely to result from the breach … the words “not unlikely”… denoting a degree of probability considerably less than an even chance but nevertheless not very unusual and easily foreseeable.”

23

In the light of the authorities, the generally accepted test for remoteness has been whether the loss claimed was of a kind or type which it would have been within the reasonable contemplation of the parties at the time that the contract was made as being not unlikely to result. However, the recent House of Lords decision in The Achilleas has called into question whether that remains a sufficient test.

24

In The Achilleas a time chartered vessel was delayed during a legitimate final voyage, and redelivered late. The late redelivery was a breach of the contract, which caused owners to fail to deliver the vessel within the laycan spread of the follow on charter. Owners were forced to renegotiate with the new charterers a substantially reduced rate of hire. Owners claimed damages for the difference between the original and renegotiated rates of hire for the entire duration of the follow...

To continue reading

Request your trial
24 cases
  • Jayesh Shah and Another v HSBC Private Bank (UK) Ltd
    • United Kingdom
    • Queen's Bench Division
    • 16 May 2012
    ...precise manner of its happening. It is enough if he should have contemplated damage of that kind as not unlikely." In Sylvia Shipping Co. Ltd v Progress Bulk Carriers Ltd [2010] 2 Lloyd's LR 81 Hamblen J reviewed the law on remoteness of damages in contract in the light of the House of Lord......
  • ARB v Ivf Hammersmith Ltd R (Third Party)
    • United Kingdom
    • Queen's Bench Division
    • 6 October 2017
    ...and as a free-standing point, I am grateful to Mr Mylonas for drawing to my attention the decision of Hamblen J in Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd [2010] EWHC 542 (Comm) which serves to demonstrate that The Achilleas was a rare instance of the orthodox approach ceding to......
  • Borealis AB v Geogas Trading SA
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 9 November 2010
    ...of dispute. Secondly, because the “orthodox approach” (Hamblen J in Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd (The Sylvia) [2010] EWHC 542 (Comm); [2010] 2 Lloyd's Rep. 81; at [20] et seq) based upon Hadley v Baxendale (1854) 9 Ex 341 and Czarnikow v Koufos (The Heron II) [1969] ......
  • Silverburn Shipping (IoM) Ltd v ARK Shipping Company LLC
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 22 February 2019
    ...21 There is a debate between the parties as to the extent to which the Tribunal's findings are ones of pure law or mixed fact and law. In “ The Sylvia” [2010] EWHC 542 (Comm); [2010] 2 Lloyd's Rep 81 (at [54] and [61] (“ The Sylvia”), Hamblen J (as he then was) confirmed, in the context o......
  • Request a trial to view additional results
5 firm's commentaries
  • Consequential Loss in Energy Commodity Contracts
    • United Kingdom
    • JD Supra United Kingdom
    • 9 October 2015
    ...foreseeability rule based on individual circumstances will be unusual" (para 11). 6 In Sylvia Shipping vs Progress Bulk Carriers [2010] EWHC 542 (Comm), the court stated that the principle of assumption of responsibility would apply in "those relatively rare cases where the application of t......
  • The 'Great Creation': What Can A Shipowner Recover When A Charterer Gives Less Than The Agreed Notice For Redelivery?
    • United Kingdom
    • Mondaq UK
    • 18 February 2015
    ...set out in the authorities, including those relating to remoteness of loss in The Achilleas [2008] 2 Lloyd's Rep 275 and The Sylvia [2010] 2 Lloyd's Rep 81, they had proceeded to apply them incorrectly given their erroneous characterisation of the loss as one relating to a notional voyage f......
  • Is the Pindell Case Manifestation of the Law of Unintended Consequences?
    • United Kingdom
    • Mondaq United Kingdom
    • 5 April 2011
    ...See Supershield Ltd v Siemens Building Technologies FE Ltd [2010] EWCA Civ 7 and Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd [2010] EWHC 542 (Comm) And to some extent Lord Walker as well, but his Lordship also agreed with Lord Hoffmann and Lord The content of this article is intende......
  • Too Remote? Clarification of the Principle of Remoteness of Damages
    • United Kingdom
    • Mondaq United Kingdom
    • 29 April 2010
    ...debated, and to this day, remains somewhat ambiguous. However the recent case of Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd [2010] EWHC 542 addresses the confusion surrounding the principle of remoteness of damages and has clarified the principles under current case As mentioned ab......
  • Request a trial to view additional results
3 books & journal articles
  • CONTRACT LAW IN COMMONWEALTH COUNTRIES: UNIFORMITY OR DIVERGENCE?
    • Singapore
    • Singapore Academy of Law Journal No. 2019, December 2019
    • 1 December 2019
    ...The Amer Energy [2009] 1 Lloyd's Rep 293 at [17]–[18]; Borealis AB v Geogas Trading SA [2010] EWHC 2789 (Comm) at [48]; The Sylvia [2010] EWHC 542 (Comm); [2010] 2 Lloyd's Rep 81 at [40]–[48]; Ispat Indurstries Ltd v Western Bulk Pte Ltd [2011] EWHC 93 (Comm) at [53]; and Jayesh Shah, Shale......
  • Claims for the value of the lost contractual performance
    • Australia
    • University of Western Australia Law Review No. 45-1, June 2019
    • 1 June 2019
    ...like Supershield Ltd v Siemens Building Technologies FE Ltd [2010] EWCA Civ 7, Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd [2010] EWHC 542 (Comm) and John Grimes Partnership Ltd v Gubbins [2013] EWCA Civ suggest that the decision merely adds a ‘gloss’ to the usual approach, requirin......
  • Lecture
    • Singapore
    • Singapore Academy of Law Journal No. 2017, December 2017
    • 1 December 2017
    ...Shipping Inc v Mercator Shipping Inc[2009] 1 AC 61; [2008] UKHL 48 at [93]. 11Sylvia Shipping Co Ltd v Progress Bulk Carriers Ltd[2010] EWHC 542 (Comm); Classic Maritime Inc v Lion Diversified Holdings Berhad Limbungan Makmur Sdn Bhd[2009] EWHC 11 42 (Comm); Supershield Ltd v Siemens Buildi......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT