The Progress Power (Gas Fired Power Station) (Amendment) Order 2020
Jurisdiction | UK Non-devolved |
Citation | SI 2020/807 |
Year | 2020 |
2020 No. 807
Infrastructure Planning
The Progress Power (Gas Fired Power Station) (Amendment) Order 2020
Made 27th July 2020
Coming into force 28th July 2020
An Application has been made, under paragraph 2 of Schedule 6 to the Planning Act 20081, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 20112for non-material changes to the Progress Power (Gas Fired Power Station) Order 20153.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—
Citation and commencement
1. This Order may be cited as the Progress Power (Gas Fired Power Station) (Amendment) Order 2020 and comes into force on 28th July 2020.
Amendment to the Progress Power (Gas Fired Power Station) Order 2015
2. The Progress Power (Gas Fired Power Station) Order 2015 (“the 2015 Order”) is amended in accordance with this Order.
Amendments to Schedule 2 (requirements)
3. For paragraph 1 of Schedule 2 to the 2015 Order substitute “The authorised development must commence no later than 13th August 2021.”.
Gareth Leigh
Head of Energy Infrastructure Planning
Department for Business, Energy and Industrial Strategy
27th July 2020
EXPLANATORY NOTE
(This note is not part of the Order)
This Order amends the Progress Power (Gas Fired Power Station) Order 2015, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material amendment under paragraph 2 of Schedule 6 to the Planning Act 2008. This Order amends the time limit within which the development authorised by the Order must be commenced.