The Triton Knoll Electrical System (Correction) Order 2017

JurisdictionUK Non-devolved

2017 No. 467

Infrastructure Planning

The Triton Knoll Electrical System (Correction) Order 2017

Made 23th March 2017

Coming into force 24th March 2017

The Triton Knoll Electrical System Order 2016 (“the Order”)1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)2, contains correctable errors within the meaning of the Act3.

Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicant4for the correction of errors and omissions in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed the relevant local planning authorities5that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and (8) of Schedule 4, to the Act, makes the following Order:

S-1 Citation and commencement

Citation and commencement

1. This Order may be cited as the Triton Knoll Electrical System (Correction) Order 2017 and comes into force on 24th March 2017.

S-2 Corrections

Corrections

2.—(1) The Triton Knoll Electrical System Order 2016 is corrected as set out in the table in the Schedule to this Order, where—

(a)

(a) the first column sets out where the correction is to be made;

(b)

(b) the second column sets out how the correction is to be made; and

(c)

(c) the third column sets out the text to be substituted, inserted, or omitted.

Giles Scott

Head of Energy Infrastructure Planning and Coal Liabilities

Department for Business, Energy and Industrial Strategy

23rd March 2017

SCHEDULE

Article 2

SCHEDULE

Table

Where the correction is to be made

How the correction is to be made

Text to be substituted, inserted, or omitted

Preamble

For “RWE Innogy UK Ltd” substitute

“Innogy Renewables UK Limited”

Article 2(1), definition of “cable ducts”

For “electrical cables” substitute

“electrical circuits”

Article 2

After paragraph (5) insert

SCH-1.6

“6 In this Order—

(a) all offshore coordinates are latitude and longitude degrees, minutes and seconds to three decimal places in WGS84 Datum; and

(b) all onshore coordinates are Eastings and Northings in OSGB36 Datum, British National Grid Projection”

Article 35(1)(k)

For “the outline code of construction practice (onshore) (rev. C)” substitute

“the outline code of construction practice (onshore) (rev. B)”