Toucan Energy Holdings Ltd v Wirsol Energy Ltd
Jurisdiction | England & Wales |
Judge | Mr Justice Henshaw |
Judgment Date | 14 April 2021 |
Neutral Citation | [2021] EWHC 895 (Comm) |
Date | 14 April 2021 |
Docket Number | Case No: CL-2018-000640 |
Court | Queen's Bench Division (Commercial Court) |
[2021] EWHC 895 (Comm)
THE HONOURABLE Mr Justice Henshaw
Case No: CL-2018-000640
IN THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Royal Courts of Justice
Rolls Building, Fetter Lane,
London, EC4A 1NL
Stephen Cogley QC, Samuel Townend and Sophia Hurst (instructed by Stewarts Law LLP) for the Claimants
Craig Morrison, Emily Husain and Jacob Rabinowitz (instructed by Enyo Law LLP) for the Defendants
Hearing dates: 7–8, 12–15, 19–23, 26–30 October and 4–5 November 2020
Draft judgment circulated to the parties on 20 March 2021
Approved Judgment
(A) INTRODUCTION | 7 |
(B) FACTUAL BACKGROUND | 8 |
(1) The parties | 8 |
(2) Original acquisition and construction of the solar parks | 9 |
(a) The EPC Contracts and O&M Agreements | 9 |
(b) Financing by BLB | 9 |
(c) Design and construction of the solar parks | 10 |
(3) Negotiation and execution of the SPAs and ALE Contract | 11 |
(a) Negotiation of the SPAs | 11 |
(b) Negotiations and entry into the ALE Contract | 12 |
(4) Taking Over of the solar parks and performance in 2017 | 12 |
(a) Issuing the Taking Over Certificates | 12 |
(b) Performance in 2017 | 13 |
(5) Performance under the ALE Contract | 14 |
(a) Initial steps | 14 |
(b) Waiver of CS49 | 14 |
(c) Procurement of asset life extensions | 14 |
(d) Events after December 2017 | 15 |
(6) Development of a dispute regarding the solar parks | 16 |
(7) Legal proceedings | 17 |
(a) The ALE Claim | 17 |
(b) The Claimants' refinancing | 17 |
(c) The Claimants' claims | 17 |
(d) The conclusion of Wirsol's summary judgment application | 18 |
(e) Further procedural steps | 19 |
(8) Brief summary of the components of a solar park | 19 |
(C) OVERVIEW OF CLAIMS | 21 |
(D) WITNESSES | 21 |
(1) Claimants' witnesses of fact | 21 |
(2) Defendants' witnesses of fact | 23 |
(3) Experts | 23 |
(E) DEFECTS: OVERVIEW OF CLAIMS AND CONTRACTUAL SCHEME | 24 |
(1) Overview of claims | 24 |
(2) The EPC Contractual Scheme | 25 |
(3) The O&M Agreements scheme | 26 |
(F) CAPACITY DEFECTS AND PROTECTION SETTINGS (Scott Schedule Items 1 and 3) | 26 |
(1) Introduction | 26 |
(2) Contractual obligations | 29 |
(3) Maximum load curve | 34 |
(4) Relevant combinations of voltage and power factor | 48 |
(5) Voltage variations and use of transformer taps | 55 |
(6) Transformer ratings | 60 |
(a) General | 60 |
(b) SEA transformers | 63 |
(c) GBE transformers | 66 |
(d) Imefy transformer | 67 |
(e) Hammond transformer | 68 |
(7) De-rating for Site Conditions | 68 |
(8) Safety margin/protection settings | 70 |
(9) Conclusions in relation to busbar capacity | 72 |
(10) Conclusions in relation to transformer capacity | 72 |
(11) Remedy | 73 |
(12) Postscript | 74 |
(G) LOSSES CAUSED BY CAPACITY DEFECTS: CAPPING OR ‘CLIPPING’ OF INVERTERS (Scott Schedule Item 2) | 75 |
(1) Introduction | 75 |
(2) Extent of clipping | 76 |
(3) Guaranteed Performance Ratio | 78 |
(4) EPC clause 17.6 | 78 |
(a) Scope of clause 17.6 | 79 |
(b) Deliberate default | 79 |
(c) Gross negligence | 80 |
(5) Application of EPC clause 17.6 | 80 |
(6) Remedy | 86 |
(H) USE OF FORCED AIR COOLED TRANSFORMERS (Scott Schedule Item 4) | 92 |
(1) Whether there was a breach of Employer's Requirements clause 4.4.7 | 92 |
(2) Rectification for common mistake | 95 |
(3) Employer's Requirements § 2.1 | 97 |
(4) Remedy | 102 |
(I) SUBSTATION HUMIDITY (Scott Schedule Item 5) | 102 |
(1) Introduction and relevant standards | 102 |
(2) Design of the substations | 103 |
(3) Humidity monitoring data | 108 |
(4) Operational experience | 113 |
(a) Cranham transformer failure | 117 |
(b) Corrosion of transformers | 118 |
(c) Voltage transformers (VTs) | 122 |
(d) Microswitches | 125 |
(e) Condensation at cable entries | 126 |
(5) Conclusion on humidity | 127 |
(6) Remedy on humidity | 127 |
(J) INGRESS OF WATER (Scott Schedule Item 6) | 127 |
(K) USE OF PLYWOOD IN SUBSTATIONS (Scott Schedule Item 7) | 130 |
(1) Flammability | 130 |
(2) Durability and water damage | 133 |
(3) Remedy | 134 |
(L) LACK OF HV AND LV CIRCUIT BREAKERS (Scott Schedule Items 8 to 12 and 14) | 135 |
(1) Contractual obligations | 136 |
(2) HV Circuit Breakers (Scott Schedule Item 10) | 137 |
(3) LV circuit breakers (Scott Schedule Item 8) | 138 |
(a) Liability | 138 |
(b) Remedy | 142 |
(4) Bus Section Breakers (Scott Schedule Items 9 and 11) | 143 |
(5) Wilbees Third Circuit Breaker (Scott Schedule Item 12) | 144 |
(6) Combiner box miniature circuit breakers (Scott Schedule Item 14) | 145 |
(M) MONITORING DEFECTS (Scott Schedule Items 15 to 19) | 148 |
(1) Measurement of voltage at string level (Scott Schedule Item 15) | 148 |
(2) Voltage measurement at combiner box (Scott Schedule Item 16) | 149 |
(3) Remote monitoring of transformer temperature (Scott Schedule Item 17) | 149 |
(4) Alarms and alerts (Scott Schedule Item 18) | 150 |
(5) Storage of reactive energy data for 90 days (Scott Schedule Item 19) | 151 |
(6) Remedy | 152 |
(N) INADEQUATE SITE FINISHING AND LANDSCAPING WORKS ((Scott Schedule Item 20) | 153 |
(O) 25 YEAR MINIMUM OPERATIONAL LIFE WARRANTY (Scott Schedule Item 21) | 153 |
(1) Contractual obligations | 153 |
(2) C's case as to Wirsol's design operational life | 154 |
(3) Transformers | 154 |
(4) Forced air cooled transformers, water ingress and excessive humidity | 156 |
(5) Plywood flooring | 156 |
(6) Circuit breakers | 157 |
(P) OTHER ISSUES RELATING TO REMEDY | 157 |
(1) General approach to quantification of loss | 157 |
(2) The Claimants' remedial scheme | 158 |
(3) Replacement of substations | 160 |
(4) The Cranham transformer | 169 |
(5) Other costs of remedial work | 169 |
(a) Downtime while remediation takes place | 169 |
(b) Removal and disposal of transformers, switchgear and containers | 170 |
(c) Disconnection, civils and installation works at final commissioning | 171 |
(d) Specialist screw pile foundations: difference £68,400 | 171 |
(e) Insurances | 172 |
(f) Inflation | 173 |
(g) Contingency/ design development costs: difference £29,564 | 173 |
(Q) BLIGHT | 173 |
(1) Introduction | 173 |
(2) Principles | 174 |
(3) Factual witnesses' evidence of blight | 175 |
(4) Expert evidence as to existence of blight | 176 |
(5) Inclusion of non-defective sites | 182 |
(6) Quantum of alleged blight | 184 |
(7) Conclusion on blight claims | 185 |
(R) REFINANCING COSTS | 185 |
(1) Causation | 185 |
(2) Quantum of the refinancing claim | 194 |
(a) Basis of assessment | 194 |
(b) The 2018 refinancing: relevant capital sum | 194 |
(c) The 2023 refinancing: interest and fees | 197 |
(d) Discount rate | 197 |
(e) Conclusion as to quantum | 197 |
(3) Title to sue | 197 |
(4) EPC clause 17.6 | 198 |
(S) TERMINATION OF EPCS AND O&M CONTRACTS | 198 |
(1) Termination of the EPC Contracts | 199 |
(2) Termination of the O&M Agreements | 201 |
(3) Mitigation of loss | 202 |
(4) Clause 13.4 of the O&M Agreements | 207 |
(T) DELAY LIQUIDATED DAMAGES | 207 |
(1) Introduction | 207 |
(2) Legal principles | 208 |
(3) Representation | 208 |
(4) SPVs' intention or knowledge | 211 |
(5) Reliance | 212 |
(6) Inequitable for Claimants to resile from waiver | 213 |
(U) ABAKUS BYES DELAY LIQUIDATED DAMAGES | 213 |
(1) Background | 213 |
(2) The provisions of the SPA | 214 |
(3) Disclosure by Wircon UK and Wircon Germany | 216 |
(4) Discussion | 217 |
(V) THE OUTWOOD OPTION | 219 |
(1) Background | 219 |
(2) Toucan Gen Co's claims | 219 |
(3) Toucan Gen Co's pleaded case | 221 |
(4) Toucan Gen Co's proposed new case | 222 |
(5) Conclusion on the Outwood Option | 223 |
(W) BREACH OF WARRANTY: DEFECTS | 223 |
(X) THE ALE CLAIMS | 226 |
(1) Introduction | 226 |
(2) Relevant provisions | 226 |
(3) Facts | 230 |
(4) Type of waiver required by § 13 of the ALE Contract | 245 |
(5) Whether Toucan Energy waived CS49 under the ALE Contract | 250 |
(6) Non-disclosure under SPA clause 20.2 | 258 |
(7) Other matters concerning the waiver of CS49 | 259 |
(8) Implied terms | 260 |
(a) Proposed implied terms | 260 |
(b) Principles | 261 |
(c) Application | 261 |
(9) Whether compliant asset life extensions obtained | 264 |
(a) Use of template | 266 |
(b) Whether BLB consented to the final form option agreement | 267 |
(c) Whether Toucan, acting reasonably, would have consented to the form of option | 271 |
(d) Subsequent changes to the forms of option | 278 |
(e) Adequacy of the alleged written confirmation from the landlord | 280 |
(f) Whether an engrossment form of option was provided to the Claimants | 281 |
(g) Whether a planning extension was achieved | 282 |
(10) Conclusion on ALE Contract claims | 284 |
(Y) ADDITIONAL CLAIMS AGAINST THE SPVS | 284 |
(Z) OVERALL CONCLUSIONS | 285 |
ANNEX – THE DEFENDANTS' APPLICATION TO AMEND | 287 |
(1) Introduction | 287 |
(2) Applicable principles | 287 |
(3) Background | 293 |
(4) Transformer and busbar capacity | 295 |
(5) ‘Capping’ or ‘clipping’ of inverters | 301 |
(6) Adjustments to protection settings | 301 |
(7) HV circuit breakers | 303 |
(8) HV and LV bus section circuit breakers | 305 |
(9) Miniature Circuit Breakers | 305 |
(10) Landscaping | 305 |
(11) Other matters | 306 |
(12) Conclusions | 306 |
...
To continue reading
Request your trial-
Invest Bank P.S.C. v Ahmad Mohammad El-Husseini
...pleadings bring the case in line with the witness or expert evidence. For example, in Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021] EWHC 895 (Comm), Henshaw J. identified at [9] (of the Annex to the judgment): “It is relevant to have regard to the degree to which the case sought to......
-
John Alexander Melvin Hemming v Sonia Vanessa Poulton
...which are said to undermine his case on serious harm. The White Book at 17.3.5 cites Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021] EWHC 895 (Comm), Annex, [9]–[10] as authority for the proposition that if the case sought to be advanced by the proposed amendment is one which the par......
-
Steenbok Newco 10 Sarl v Formal Holdings Ltd
...pleadings bring the case in line with the witness or expert evidence. For example, in Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021] EWHC 895 (Comm), Henshaw J. identified at [9] (of the Annex to the judgment): “ It is relevant to have regard to the degree to which the case sought t......
-
Havila Kystruten A.S. v Abarca Companhia De Seguros, S.A.
...7The Yard cited my recent summary of the principles relevant to permission to amend in Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021] EWHC 895 (Comm) (Annex, §§ 4–10), indicating that: i) the Court has a discretion to permit amendments to a statement of case under CPR 17.1(2)(b) and ......
-
The Sun Shines For Wirsol Energy: Guidance On The Circumstances In Which Waiver Can Be Given In A Commercial Contract
...Henshaw handed down judgment on 14 April 2021 in Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021] EWHC 895 (Comm), a substantive dispute begun in 2018 regarding the construction and sale of 19 solar parks located throughout Great Britain and Northern Wirsol has very successfully defend......
-
The Sun Shines For Wirsol Energy: Guidance On The Circumstances In Which Waiver Can Be Given In A Commercial Contract
...Henshaw handed down judgment on 14 April 2021 in Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021] EWHC 895 (Comm), a substantive dispute begun in 2018 regarding the construction and sale of 19 solar parks located throughout Great Britain and Northern Wirsol has very successfully defend......
-
Legal Developments In Construction Law: May 2021
...must be proved by cogent evidence. Generalised views or assertions are inadequate. Toucan Energy Holdings Ltd v Wirsol Energy Ltd [2021]EWHC 895 (Comm) 2. Court of Appeal revisits the strict constraints on implying contract When a court implies a term in a contract, it is including somethin......