UR Decision: C30 Extension Request - 86 Cumber Road, Claudy
Published date | 08 October 2024 |
Year | 2024 |
Energy Sector | Electricity Networks |
_______________________________________________________________________________
Utility Regulator
Queens House, 14 Queen Street, BELFAST, BT1 6ED
T: +44 (0) 28 9031 1575 F: +44 (0) 28 9031 1740 W: www.uregni .gov.uk
John Heywood
Northern Ireland Electricity Networks Ltd
Unit 3
21 Old Channel Road
Belfast
BT3 9DE
By Email Only: John.Heywood@nienetworks.co.uk
Date: 13 June 2024
Our Ref: NET/E/JF/963
Dear John,
Application for consent to a longer period for the issuance of a Connection Offer
for 86 Cumber Road Claudy, NIE Networks Reference: 24/01576
Thank you for your letter dated 7 June 2024 (the Letter) setting out an application (the
Application) made by NIE Networks Limited (NIE Networks) for an extension to the
period within which NIE Networks is required to make a connection offer (the relevant
Connection Offer), concerning a Connection Equipment at 86 Cumber Road Claudy.
1. The Application
The Letter describes the relevant background
1
to the Application. Reference is made to
Condition 30 of NIE Networks’ licence authorising participation in the activity of
distribution (the Licence).
2
Condition 30 (6) (of the Licence) provides that (barring specified exceptions)
3
NIE
Networks is obliged to make an offer for connection to the distribution system as soon as
practicable and (by operation of Condition 30 (6)(b)) in any event within 3 months from
receipt of a valid/completed application for connection to the distribution system.
1
What follows is a summary of the Application. It is not intended to be a complete rehearsal. All parts of
the Application have been considered in making the decision set out in this correspondence. Failure to
mention parts of the Application (or related correspondence) should not be taken as representing any failure
to have regard to those parts.
2
NIE Distribution Licence.
3
Recorded in Article 21 of the Electricity (NI) Order 1992 (the Electricity Order).