West African Resources processes first ore at Sanbrado Gold Project.

ENPNewswire-March 10, 2020--West African Resources processes first ore at Sanbrado Gold Project

(C)2020 ENPublishing - http://www.enpublishing.co.uk

Release date- 09032020 - Unhedged near-term gold producer West African Resources Limited ('West African' or the 'Company', ASX: WAF) is pleased to announce it has completed all construction activities and has started processing ore through the milling and CIL circuits its Sanbrado Gold Project, Burkina Faso.

Highlights

Ore introduced to the milling circuit on March 7th 2020

First gold expected within four weeks

Processing plant and power station operational

Open-pit ore is feeding the mill with 360,000t at 1.5 g/t Au on the ROM pad

West African Executive Chairman Richard Hyde commented: 'This is a major milestone for West African Resources and testament to the quality of our team and contractors. Commissioning activities will continue over the next four weeks with the first gold pour on track for early Q2 2020. We look forward to keeping investors updated throughout this exciting transition period for the Company.

Project Update

Construction and Commissioning Activities

On Saturday March 7th 2020 the Company introduced ore to the milling and CIL circuits at Sanbrado Gold Project. Construction activities have now been completed on all areas of the process plant and tailings storage facility. All four heavy fuel oil generators have been commissioned in the power station and are now operational. The desorption and gold room circuits are undergoing commissioning in preparation for a maiden gold pour within the next four weeks.

Open Pit Mining

Open-pit mining contractor African Mining Services, a subsidiary of the Perenti Group (ASX: PRN) has ramped up mining activities to include both the M5 and M1 South pits, with day and night shifts starting in the past week. Currently, over 360,000 tonnes of oxide ore are stockpiled on the ROM pad at average grade of 1.5g/t gold.

Underground Mining

Underground development continues to progress on-schedule with mining contractor Byrnecut Offshore, a subsidiary of the Byrnecut Group. The primary ventilation raise bore has been completed, with the ventilation fan currently being installed. First development ore remains on track for late March and first stoping ore is forecast for Q3 2020.

About West African Resources

West African Resources Limited (ASX: WAF) announced the results of its updated Feasibility Study for the Sanbrado Gold Project in Burkina Faso in an...