Winch Design Ltd v Carl Le Souef

JurisdictionEngland & Wales
CourtCommercial Court
JudgeMs Lesley Anderson
Judgment Date23 January 2025
Neutral Citation[2025] EWHC 120 (Comm)
Docket NumberCase No: LM-2023-000117
Between:
Winch Design Limited
Claimant
and
Carl Le Souef
Defendant

and

Somnio Superyachts Pty Limited
Part 20 Defendant
Before:

Ms Lesley Anderson KC sitting as a Deputy Judge of the High Court

Case No: LM-2023-000117

IN THE HIGH COURT OF JUSTICE

KING'S BENCH DIVISION

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

COMMERCIAL COURT

Royal Courts of Justice, Rolls Building

Fetter Lane, London, EC4A 1NL

Adam Board (instructed by HFW, Friary Court, 8 Bishopgate, City of London, London EC2N 4BQ) for the Claimant

Karl Anderson (instructed by Wedlake Bell LLP, 71 Victoria Street, London EC4V 4AY) for the Defendant

Hearing dates: 28 and 29 October 2024

Approved Judgment

This judgment was handed down remotely at 3pm on January 23 rd 2025 by circulation to the parties or their representatives by e-mail and by release to the National Archives.

Ms Lesley Anderson KC:

Introduction

1

This is a dispute about an ambitious project ( the Project) to build a luxury yacht, comprising several, single, luxurious, residential apartments, which is intended to be one of the largest and most luxurious yachts ever to be built ( the Yacht).

2

The Claimant, Winch Design Limited ( Winch), is an English company that provides design services in relation to the manufacture of, amongst other things, luxury yachts. Although he has since retired, Winch's non-executive chairman at the relevant time was Russell Clive Beharell ( Mr Beharrell). Aino-Leena Grapin ( Ms Grapin) has been its Chief Executive Officer since September 2016 when she took over that role from the company's co-founder Andrew Winch ( Mr Winch).

3

The Defendant, Mr Le Souef ( Mr Le Souef), is an entrepreneur and businessman and an Australian national. There is some disagreement over his true net worth or at least how that was projected to Winch.

4

The Part 20 Defendant, Somnio Superyachts Pty Ltd ( Somnio), was incorporated in Australia on 17 April 2019. It was co-founded by Mr Le Souef and Capt. Erik Bredhe ( Capt. Bredhe), a Finnish national, now living in Spain. Mr Le Souef is Somnio's sole director.

5

Mr Le Souef and Capt. Bredhe met in 2007 when Capt. Bredhe was captaining MS The World, another private residential cruise ship on which Mr Le Souef had an apartment. They discussed the possibility of them combining to engage in a project for the construction of a new highly exclusive, ultra-luxury residential yacht (destined to become the Yacht). An early promotional brochure describes this as a lifestyle project which was to be funded by a consortium of investors (invited by Mr Le Souef and who would each contribute via non-refundable deposits of $125,000 for apartments on the Yacht). Each investor would become part of a steering committee ( the Steering Committee) in order to drive the Project forward and to influence aspects of the Yacht's design and development. According to Mr Le Souef, the total estimated cost of the project is $500 million and Somnio was incorporated to act as a special purpose vehicle ( SPV) for the development of the Yacht. According to its accounts for the year ended 30 June 2021, Somnio had raised $760,000 for the Project's initial research and feasibility costs, which Mr Le Souef says was intended to be used mainly for the creation of marketing materials and initial design work. Somnio is the owner of the relevant intellectual property in relation to the Yacht.

6

By an email dated 1 May 2019, Mr Le Souef and Capt. Bredhe were introduced to Mr Beharrell of Winch by Mr Jon Stewart, one of Mr Le Souef's business partners, and discussions then took place, including at various meetings, and including Ms Grapin, about Winch's potential involvement in the Project. Unsurprisingly, given the nature and extent of the Project, Winch was very excited about its potential involvement, and it is common ground that it represented a significant commercial and financial opportunity for Winch.

7

It is not in dispute that Winch did some initial work on the Project in 2019 and 2020 before the formal contract was executed, including some exterior design work for the Monaco Yacht Show in 2019, and some design development work in 2020. During this period, the work appears to have been the subject of separate contractual negotiations. Some design work was undertaken by Winch in June 2019 and invoiced to Somnio on or about 20 June 2019. Some specific tasks were undertaken which were the subject of separate “Fee Overview” letters sent to Capt. Bredhe. In addition, Winch also produced fee proposals for the main Project on 5 June 2019, 5 July 2019 and 16 October 2019 which led, during the negotiations, to an agreed reduction in the price of c.£1m on 22 July 2020.

8

Negotiations for a formal contract took place in October and early November 2020. It is common ground that the relevant contractual framework is as follows:

8.1. A written contract was entered into dated 3 November 2020 ( the Initial Contract) by which Winch was engaged to provide certain interior and exterior design services in relation to the construction of the Yacht;

8.2. The Initial Contract was amended by an Addendum dated 9 April 2021 ( the Addendum); (and save where otherwise specified together I refer to this as ( the Contract)).

9

The claim is by Winch for unpaid invoices in relation to its work done on the Project pursuant to the Contract. It is common ground that Winch issued invoices under the Contract as follows:

9.1. Invoice No 9422 in the amount of £200,000 on 12 April 2021 which was paid on 15 April 2021;

9.2. Invoice No 9455 in the amount of £197,500 on 27 April 2021 which has not been paid;

9.3. Invoice No 9485 in the amount of £197,500 on 10 May 2021 which has not been paid;

9.4. Invoice No 9502 in the amount of £338,750 on 19 May 2021 which has not been paid;

(the unpaid invoices ( Disputed Invoices) together amount to £733,750).

10

However, Mr Le Souef and Somnio challenge Winch's entitlement to be paid the Disputed Invoices on various grounds, namely: (i) an issue as to the true identity of Winch's counterparty to the Contract on its proper construction and/or through rectification and/or estoppel ( the Contracting Party Issue); (ii) the proper meaning and construction of the payment terms in the Contract and/or whether Mr Le Souef is estopped from denying that the payments are due in full ( the Payment Terms Issue); (iii) whether Winch agreed with Mr Le Souef to forbear from demanding or suing for payment of the Disputed Invoices pending Somnio being placed in funds by third party investors ( the Forbearance Issue); (iv) whether Winch breached the terms of the Contract by failing to provide the services covered by the Disputed Invoices and was entitled to suspend providing further performance of the Contract in light of their continuing non-payment ( the Winch Performance Issue) and (v) if Winch had broken the terms of the Contract whether Mr Le Souef/Somnio have suffered a recoverable loss for which he/it is entitled to counterclaim for damages ( the Counterclaim Issue).

11

Mr Le Souef and Somnio were represented at the trial before me by Karl Anderson and Winch was represented by Adam Board. I have been assisted by an Agreed List of Common Grounds and Issues and by detailed written skeleton arguments and helpful oral submissions from Counsel for both parties. I am grateful to them for the way in which they assisted me during the trial and for the assistance provided by their respective solicitors in compiling the trial bundles, including providing me with a retrospective core bundle of documents referred to during the trial.

The Contract

12

The Initial Contract comprises: (i) a document described as a Proposal (which is described in the footer as being a 21 page document) and is dated 3 November ( the Proposal); (ii) a signature page on page 18 of 21 ( the Signature Page); (iii) at Annex 1 Winch's Terms of Engagement which runs to nine pages ( Terms of Engagement) and (iv) a document headed “Scope of Supply (Owners Area) Interface Matrix at Annex II. Although the Initial Contract purported to have a further Annex V (described as a “Demarcation Plan”) the actual page is blank and I am satisfied this can be disregarded. The Initial Contract was signed by Ms Grapin on behalf of Winch on 4 November 2020 and is expressed to be “ Signed by Erik Bredhe on behalf of Carl Le Souef”.

13

So far as material to the present dispute the Initial Contract provides as follows.

13.1. Mr Le Souef is described and defined as “the Client” on the first page of the Proposal.

13.2. The “Client's Representative” is described and defined to be Erik Bredhe on the first page of the Proposal.

13.3. The Period of the Contract is described and defined on the first page of the Proposal to mean “ October 2020 to March 2024 (approximately 42 months, subject to any extension)”.

13.4. The first page of the Proposal states: “ This Proposal, together with the annexed Terms of Engagement, sets out the terms on which [Winch] are to be engaged by the Client to provide interior and exterior, decorative design and other associated services for the luxury areas of a turnkey motor yacht project to be constructed at the Vard shipyard, in Aalesund, Norway (the “Shipyard” or “Contractor”)”.

13.5. Page 2 of 21 to page 12 of 21 of the Proposal set out a detailed scope of works for the Project to be carried out in six stages: Stage One – Concept Design (which is then sub-divided into Stage One Part One — Interior & Exterior Preliminary Concept Design and Stage One Part Two – Interior & Exterior Final Concept Design); Stage Two – Exterior Detail Design; Stage Three — Interior Detail Design; Stage Four – Interior Decorative Design; Stage Five – Design Management and Stage Six – Procurement.

13.6. At page 13 of 21 of the Proposal under the sub-heading “The Winch Charges” and at page 15 of 21 there is a payment schedule based on the start date of October 2020. The...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
2 cases
  • Trident House Development Ltd v Mohammed Yousaf
    • United Kingdom
    • Chancery Division
    • 21 Febrero 2025
    ...an adverse inference from the absence of a witness are not made out (see, for example, most recently Winch Design Ltd v. Le Souef [2025] EWHC 120 (Comm) at [45]); in particular, because Mr Yousaf did not adduce evidence that the completion of the project was not delayed. Nor is it appropria......
  • Trident House Development Limited v Mohammed Yousaf
    • United Kingdom
    • Chancery Division
    • 21 Febrero 2025
    ...for drawing an adverse inference from the absence of a witness are not made out (see, for example, most recently Winch Design Ltd v. Le Souef [2025] EWHC 120 (Comm) at [45]); in particular, because Mr Yousaf did not adduce evidence that the completion of the project was not delayed. Nor is ......