Crossrail decision letter dated 28 March 2024

Head Office:25 Cabot Square, London E14 4QZT: 020 7282 2000 orr.gov.uk
Jonathan Rodgers
Senior Executive
28 March 2024
Alex Aitken
Customer Relationships Executive
Network Rail Infrastructure Limited
Hawker House, 5/6 Napier Road
Reading
RG1 8BW
Joanna Kinnish
Concession Support Manager
MTR Corporation (Crossrail) Limited
63 St Mary Axe
London
EC3A 8NH
Dear Alex and Joe
Approval of the 30th supplemental agreement to the track access
contract between Network Rail Infrastructure Limited (Network Rail) and
MTR Corporation (Crossrail) Limited dated 21 November 2018
We have approved the above supplemental agreement submitted to us formally on 28
March 2024 under section 22 of the Railways Act 1993 (the Act). This follows an earlier
informal submission of a draft agreement for our consideration. This letter explains the
reasons for our decision.
Purpose
The purpose of this agreement is to amend the current Schedule 8 Appendix 1, in order to
reflect the addition of a Public Differential at specific locations from the 10 December 2023
timetable change. The effective date of this amendment is applied retrospectively from
02:00 on 10 December 2023.
Industry consultation
An industry consultation was not required as no other parties are affected.
ORR review
Our review of the application raised no concerns.

To continue reading

Request your trial