Costs Management Order (For use where budgets have not been wholly agreed)

Published date21 March 2018
Subject MatterChancery forms
Costs Management Order

Costs Management Order CH 40

For use where budgets have not been wholly agreed

Claim No.

Upon a CCMC having been held on [date]

(1) The court has made a costs management order.

(2) The budget phases which have been agreed or approved are set out in the schedule to this order.

(3) Amended budgets to take account of the budget phases set by the court should not be filed.

Schedule

PHASE (total figures)

CLAIMANT

1ST DEF

2ND DEF

3RD DEF

Agreed or approved total

Pre-action

Issue/pleadings

CMC

Disclosure

Witness Statements

Experts’ reports

PTR

Trial preparation

Trial

ADR

Contingencies

...