Merseyrail Electrics Limited 10 July 2023

Date10 July 2023
SectionAgreed amendments to contracts (section 22)
Head Office:25 Cabot Square, London E14 4QZT: 020 7282 2000 orr.gov.uk
David Reed
Senior Executive, Access & Licensing
10
July 2023
Devon
Wall
Franchise and Access Support Manager
Network Rail Infrastructure Ltd
Square
One, 4 Travis Street
Manchester
M1 2NF
George Williams
Concession
& Business Framework
Mana
ger
Mer
seyrail Electrics 2002 Limited
R
ail House, Lord Nelson Street
Liver
pool, Merseyside,
L1 1JF
Dear Devon and George,
Approval of the 10th supplemental agreement to the track access
contract between Network Rail Infrastructure Limited and Merseyrail
Electrics 2002 Limited dated 1 April 2019
We have today approved the above supplemental agreement submitted to us formally on
3 July 2023 under section 22 of the Railways Act 1993 (the Act). This follows an earlier
informal submission of a draft agreement for our consideration. This letter explains the
reasons for our decision.
Purpose
The purpose of this agreement is to amend Appendix 1 to Schedule 8 to reflect the
introduction of a new station at Headbolt Lane currently due to enter into service in
September 2023 and Headbolt Lane to replace Kirkby as a monitoring point (reverse
direction) at that time.
Industry consultation
No industry consultation was required as the changes do not affect any other party.
ORR review
Our review of the application raised no operational, performance or economic concerns.

To continue reading