Quadrangle Development and Construction Company Ltd v Jenner
Jurisdiction | England & Wales |
Date | 1974 |
Year | 1974 |
Court | Court of Appeal (Civil Division) |
-
- This document is available in original version only for vLex customers
View this document and try vLex for 7 days - TRY VLEX
- This document is available in original version only for vLex customers
32 cases
-
Tyndarius v O'Mahony and Others
...into existence is as equally bound thereby as the recipient of the notice (seeQuadrangle Development and Construction Co.Ltd. -v- Jenner [1974] 1 WLR 68). I am satisfied that under the language of the clause, the party giving the notice must be ready and willing at the time of the giving of......
-
J.T.M. Construction and Equipment Ltd v Circle B Farms Ltd
...must himself be ready and willing to complete at the time of service: Quandrangle Development and Construction Co. Ltd. v Jenner [1974] 1 All ER 729 at 731. (2) The notice can only be served after unreasonable delay. (3) The notice must allow a reasonable time for completion. 53 In terms of......
-
Redmount Trust Company Ltd
...of a land transaction, the meaning of “completion” is as stated by Buckley LJ in Quadrangle Development and Construction Co Ltd v Jenner [1974] 1 WLR 68 at p. 72: … the word of “completion” may be capable of different meanings in different contexts, but prima facie completion of the contrac......
-
Midill (97PL) Ltd v Park Lane Estates Ltd and another
... ... International Limited A Merrill Communications Company 190 Fleet Street, London EC4A 2AG Tel No: 020 7404 1400, ... ...
Request a trial to view additional results
1 books & journal articles
-
Mind the gap! Payment of price and transfer of title
...Holdings Ltd v Citycrest Properties Ltd (2002) P&CR 305, para. 24 per Blackburne J. See also Quadrangle Development Ltd v Jenner [1974] 1 WLR 68. 16 Northstar Land v Brooks [2005] EWHC 1919, para. 189 per Toulmin QC. 17 Cole v Rose [1978] 3 All ER 1121 per Deputy Judge Davies QC. 18 Rawson ......