SONI Licence Condition 16 – Grid Code Modification Determination (DRAI)

Published date15 June 2022
Year2022
Energy SectorElectricity Networks
__________________________________________________________________________________
Northern Ireland Authority for Utility Regulation
Queens House, 10-14 Queen Street, BELFAST, BT1 6ED
T: +44 (0) 28 9031 1575 F: +44 (0) 28 9031 1740 W: www.uregni.gov .uk
Marie Therese Campbell
SONI Ltd
Castlereagh House
12 Manse Road
Belfast
BT9 5HT
Date: 08/06/2022 Our Ref: NET/E/TH/524
Dear Marie Therese
RE: Request to the Authority
1
by SONI for a decision on a Condition 16 Grid Code
modification regarding SONI Grid Code Clause CC13.1
Thank you for your email, received 22 March 2022 in regards to the proposed modification
to SONI Grid Code clause CC13.1 within the SONI Grid Code. Your email contained a Final
Modification Report, including representations received by SONI from the modification
consultation.
The Modification
On 13 October 2021, SONI received a modification proposal to the SONI Grid Code Clause
CC13.1. The modification proposal was submitted to SONI by Demand Response
Association of Ireland (DRAI).
The modification set out to remove the minimum time duration of the Maximum Down-Time
for a Demand Side Units (DSU) operating capabilities, Grid Code Clause CC13.1
Red-line Version of Impacted Grid Code Section
Green-line Version of Impacted Grid Code Section
The justification for proposing the modification is as follows, stated by DRAI:
1
In this letter the words “we”, “us” “our” and Authority are used interchangeably to refer to the Northern Ireland
Authority for Utility Regulation.

To continue reading

Request your trial