Jarvis (J.) & Sons Ltd v Westminster Corporation

JurisdictionUK Non-devolved
CourtHouse of Lords
Year1969
Date1969
[HOUSE OF LORDS] WESTMINSTER CORPORATION APPELLANTS AND J. JARVIS & SONS LTD. AND ANOTHER RESPONDENTS [On appeal from J. JARVIS & SONS LTD. v. WESTMINSTER CORPORATION AND ANOTHER] 1970 Feb. 12, 16; March 18 Lord Reid, Lord Hodson, Lord Guest, Viscount Dilhorne and Lord Wilberforce

Building - Contract - R.I.B.A. form - Extension of time - Sub-contract works apparently completed by due date for completion - Defects subsequently appearing - Remedial work delaying progress of main contract works - Whether main contract works “delayed … by delay on the part of nominated sub-contractors” - R.I.B.A. contract (1963 ed.), cl. 23 (g).F1

By a contract in the R.I.B.A. standard form (Local Authorities Edition (with Quantities), 1963), the appellants (“the employer”) employed the first respondents (“the contractor”) to erect a multi-storey car park, and nominated the second respondents (“the nominated sub-contractor”) to carry out the necessary piling work. The nominated sub-contractor purported to complete that work by the due date for its completion, namely, June 20, 1966, and withdrew from the site. Subsequently, many of the piles were found to be defective, and remedial work was carried out by the nominated sub-contractor whereby progress of the main contract works was delayed. By originating summons, the contractor sought determination of the question whether he was entitled to an extension of time for completion of those works on account of delay caused by the nominated sub-contractor. Donaldson J. answered that question in the negative, holding that “delay on the part of nominated sub-contractors” in the context of clause 23 (g) of the R.I.B.A. form of contract could only occur whilst the nominated sub-contractor was still in the process of performing or purporting to perform the sub-contract and that the nominated sub-contractor had achieved apparent completion of the sub-contract works and handed over to the contractor on June 20, 1966. The Court of Appeal allowed appeals by the contractor and the nominated sub-contractor.

On appeal by the employer:—

Held, allowing the appeal, that, on a true construction of clause 23 (g) of the R.I.B.A. form of contract in its context, “delay” did not, for practical purposes, run after there was such completion of the sub-contract works as would enable the contractor to take over himself the “delay” with which clause 23 was concerned being delay in terms of the main contract, that, on June 20, 1966, there had been apparent completion of the sub-contract works, the nominated sub-contractor having returned subsequently not in order to fulfil its contract but to remedy its breach of it; and that the judgment of Donaldson J. had been correct in fact and in law.

Decision of the Court of Appeal [1969] 1 W.L.R. 1448; [1969] 3 All E.R. 1025, C.A. reversed.

No cases are referred to in their Lordships' opinions or were cited in argument.

APPEAL from the Court of Appeal (Civil Division) (Davies, Salmon and Karminski L.JJ.).

This was an appeal brought pursuant to leave granted by the House of Lords on October 13, 1969, by the Westminster Corporation (“the employer”) from an order of the Court of Appeal dated July 11, 1969, allowing appeals by J. Jarvis & Sons Ltd. (“the contractor”) and Peter Lind & Co. Ltd. (“the nominated sub-contractor”) from an order of Donaldson J. given on June 17, 1968, whereby he answered in the negative the question:

“Whether [the contractor is] entitled to an extension of time for completion of the works required to be carried out at Rochester Row in the City of Westminster under a contract between [the employer] and [the contractor] in the R.I.B.A. standard form made on September 21, 1966, on account of delay caused by [the nominated sub-contractor].”

By an originating summons taken out by the contractor as plaintiff, joining the employer as first and the nominated sub-contractor as second defendants, the contractor sought determination of the above question. On an interlocutory application, it was ordered that there be no pleadings and that the trial be before the commercial judge. The parties exchanged contentions and agreed a statement of facts which was, so far as material, as follows.

1. By a contract in writing made on September 21, 1966 (hereinafter called “the main contract”), the contractor agreed to carry out and complete for the employer certain building works (hereinafter called “the contract works”) for the consideration set out in the main contract and subject to conditions therein referred to. The contract works consisted of a multi-storey car park with flats, offices, showrooms, petrol filling station and computer centre at Rochester Row, London S.W.1. 2. (a) The main contract incorporated the R.I.B.A. Conditions (Local Authorities Edition (with Quantities) 1963 ed.). The main contract, appended to the agreed statement of facts, provided that the contractor should be liable to the employer in the event of the contractor failing to complete the works by the agreed completion date for liquidated damages at the rate of £1,800 a week. By clause 23:

“Upon it becoming reasonably apparent that the progress of works is delayed, the contractor shall forthwith give written notice of the cause of the delay to the architect … and if in the opinion of the architect … the completion of the works is likely to be or has been delayed beyond the date for completion stated in the appendix to these conditions or beyond any extended time previously fixed under either this clause or clause 33 (1) (c) … (g) by delay on the part of nominated sub-contractors … which the contractor has taken all practicable steps to avoid or reduce … then the architect … shall … make … a fair and reasonable extension of time for completion of the works …”

By clause 27:

“The following provisions of this condition shall apply where prime cost sums are included in the contract bills, or arise as a result of architect's … instructions given in regard to the expenditure of provisional sums, in respect of persons to be nominated by the architect … to supply and fix materials or goods or to execute work … (d) … (ii) If any nominated sub-contractor fails to complete the sub-contract works or … any section thereof within the period specified in the sub-contract or within any extended time granted by the contractor with the written consent of the architect … then if the same ought reasonably so to have been completed the architect … shall certify in writing accordingly …”

Possession of the site was given to the contractors on December 6, 1965, and the main contract required the contractor to complete the contract works by January 15, 1968, subject to such extensions of time as the architect might make. The contractor had been granted extensions of time for causes other than the delay the subject-matter of these proceedings amounting to 14½ weeks. The contract works had not yet been completed. 3. The employer appointed Messrs. Howard V. Lobb and Partners as the architect and Messrs. Jan Bobrowski and Partners (hereinafter called “the engineer”) as consulting engineers. 4. The architect nominated the nominated sub-contractor to carry out certain piling work referred to in the bills of quantities. 5. The contract works commenced on December 6, 1965. 6. The nominated sub-contractor commenced the piling works on April 4, 1966. 7. On May 26, 1966, the engineer wrote to the contractor concerning a defect observed in the piling. 8. The nominated sub-contractor purported to complete the piling works by June 20, 1966, and removed [its] equipment and men by June 24, 1966. Further construction work on the site was then carried out by the contractor. 9. The date by which the nominated sub-contractor should have completed the piling work, that was, the end of the period specified in the piling sub-contract for the completion thereof as extended by the contractor with the consent of the architect, was June 20, 1966. 10. By letter dated July 20, 1966, the resident engineer drew the nominated sub-contractor's attention to the fact that the cut-off levels of the piles that had so far been exposed were too high. 11. On the morning of July 21, 1966, one of the contractor's excavating machines accidently nudged one of the exposed piles (No. 57) and the top part of it broke off. 12. Later on the morning of July 21, 1966, there was a meeting which began at the office of the contractor, which adjourned to the site after the representatives of the nominated sub-contractor had been informed of the matter referred to in paragraph 11 hereof. 13. A further meeting was held in the afternoon of July 21, 1966, in the conference room of the employer. No representatives of the nominated sub-contractor were present at this meeting. 14. The parties are unable to agree whether any and if any what instructions were given on July 21, 1966, in respect of the piles and how far if at all the work referred to in paragraphs 17 and 19 below was carried out in compliance with such instructions if any. 15. On July 22, 1966, evidence of a gap at high level in pile no. 57 was found. 16. A further meeting was held on July 27, 1966, at the contractor's site offices. Minutes of that meeting were prepared by the contractor and sent to the employer and the nominated sub-contractor. 17. Subsequent to the meetings referred to in paragraphs 12 and 13 the nominated sub-contractor drilled 74 piles and inspected them by lowering a television camera into the hole made by the drill. Of those 74 piles 65 were inspected by or on behalf of the architect or by the district surveyor the other nine not being inspected by the architect or the district surveyor because on the nominated sub-contractor's suggestion they were abandoned. Of the 65 piles drilled 18 were found to be defective. The defects were the result of bad workmanship or the use of bad materials on the part of the nominated sub-contractor. 18. (a) The architect was suspicious about the...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
25 cases
4 books & journal articles
  • Security for performance
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...or nominated suppliers had been used at least since the decision of the house of Lords in Westminster Corporation v J Jarvis & Sons Ltd [1970] 1 WLr 637: Keating, “alwyn Waters Memorial Lecture: he Making of a Standard Form” (1995) 11 Const LJ 170 at 178. See further powell, “Subcontracting......
  • Defects
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...being a Master Builders’ association form, used a virtually identical expression. 125 See Westminster Corporation v J Jarvis & Sons Ltd [1970] 1 WLr 637 at 647, per Viscount Dilhorne. however, it will not usually be contemplated by a contract that manifest material defects (ie, items which ......
  • Contract formation
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Contracts and Law Survey 2018 (nBS, 2018) (downloadable at www.thenbs.com) 446 Westminster Corporation v J Jarvis & Sons Ltd [1970] 1 WLr 637 at 644, per Viscount Dilhorne; City of Westminster v Cliford Culpin & Partner (1987) 12 Con Lr 117 at 138–139, per Sir John Megaw; Fillite (Runcorn) ......
  • Contract administration
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...per Coulson LJ. 357 See, eg, Morgan v S&S Constructions Pty Ltd [1967] VR 149 at 154–156; Westminster Corporation v J Jarvis & Sons Ltd [1970] 1 WLR 637 at 646, per Viscount Dilhorne; Re an arbitration between Taylor Wood-row International Ltd and the Minister of Health (1978) 19 SASR 1 at ......