Willow Corporation S.À.R.L. v MTD Contractors Ltd

JurisdictionEngland & Wales
JudgeMr Justice Pepperall
Judgment Date25 June 2019
Neutral Citation[2019] EWHC 1591 (TCC)
CourtQueen's Bench Division (Technology and Construction Court)
Docket NumberCase Nos: HT-2018-000395 & HT-2019-000009
Date25 June 2019
Between:
Willow Corp S.À.R.L.
Claimant
and
MTD Contractors Limited
Defendant

[2019] EWHC 1591 (TCC)

Before:

THE HONOURABLE Mr Justice Pepperall

Case Nos: HT-2018-000395 & HT-2019-000009

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT (QBD)

Rolls Building

Fetter Lane, London EC4A 1NL

Paul Cowan (instructed by Bryan Cave Leighton Paisner LLP) for the Claimant

Abdul Jinadu (instructed by BDB Pitmans LLP) for the Defendant

Hearing dates: 21 February & 25 March 2019 Further written submissions: 15 April 2019

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

Mr Justice Pepperall
1

By an adjudication decision dated 19 December 2018, Matthew Molloy ordered that Willow Corp. S.À.R.L. should pay MTD Contractors Limited the sum of £1,174,854.92 plus VAT and interest of £36,294.84. No payment was made. Instead, on 28 December 2018, Willow issued a Part 8 claim seeking declarations as to the proper construction of a supplementary agreement reached in June 2017 and that the adjudicator's decision was unenforceable. MTD defends the Part 8 proceedings and, on 7 January 2019, issued separate Part 7 proceedings seeking to enforce the adjudication.

2

Both matters are now before me. Willow seeks judgment upon its Part 8 claim. MTD resists the claim for declaratory relief and seeks summary judgment in order to enforce the adjudication.

PROCEDURAL BACKGROUND

3

Willow's Part 8 claim was issued on 28 December 2018. The claim was supported by a witness statement made by Willow's solicitor, Daniel Gilberthorpe, on the same day.

4

On 7 January 2019, MTD issued its Part 7 claim and made an immediate application for summary judgment. The application was supported by a witness statement made by MTD's solicitor, David Gwillim, dated 4 January 2019. Further, on 17 January 2019, Mr Gwillim made a second statement both supplementing his original statement in the Part 7 claim and responding to Mr Gilberthorpe's evidence in the Part 8 claim. Such statement was late, but the parties sensibly agreed that MTD should have permission to rely on Mr Gwillim's statements.

5

The parties then agreed directions for the orderly listing of both the Part 8 claim and MTD's summary judgment application. Such directions were approved by the court and allowed for Willow to file its evidence in response in the Part 8 claim and in answer to the summary judgment application by 6 February 2019. The directions did not envisage any further round of evidence.

6

On Friday 15 February 2019, MTD filed two further statements, being statements made by Marius Deaconescu in earlier adjudication proceedings in January and February 2018. Further, after business hours on the evening before the case came on for hearing, MTD served a further 302 pages of documents dated between February 2017 and November 2018. They were not exhibited to any further witness statement.

7

At the start of the hearing on 21 February 2019, I heard argument upon MTD's oral application to rely on Mr Deaconescu's statements and the further 302 pages. I refused permission to make such application orally and indicated that I would not have admitted the evidence in any event. I did not then give my reasons for these rulings in what turned out to be a vain attempt to complete submissions that day. I therefore start this judgment by giving my reasons.

LATE EVIDENCE IN THE PART 8 PROCEEDINGS

8

Rule 8.6(1) of the Civil Procedure Rules 1998 provides:

“No written evidence may be relied on at the hearing of the claim unless–

(a) it has been served in accordance with rule 8.5; or

(b) the court gives permission.”

9

Rule 8.5 requires the defendant's evidence to be filed with its acknowledgment of service. While the rule then allows a further 14 days for the claimant's responsive evidence, it does not envisage a second round of defence evidence. Accordingly, such further evidence can only be relied upon with the permission of the court. Equally, the agreed directions did not allow for further evidence from MTD. Still less did they allow parties to put documents in evidence other than by way of exhibit to their witness statements.

10

By analogy with the case law under rule 32.10, any application to rely on late evidence is therefore in substance an application for relief from the sanction imposed by rule 8.6(1). Rule 23.3 states the general rule that applicants must file an application notice. Further, rule 3.9(2) requires that any application for relief from sanctions must be supported by evidence. Here, MTD has neither filed an application notice nor any evidence in support of its application.

11

Rule 23.3(2) provides:

“An applicant may make an application without filing an application notice if–

(a) this is permitted by a rule or practice direction; or

(b) the court dispenses with the requirement for an application notice.”

12

Paragraph 3 of Practice Direction 23A provides:

“An application may be made without serving an application notice only:

(1) where there is exceptional urgency;

(2) where the overriding objective is best furthered by doing do;

(3) by consent of all parties;

(4) with the permission of the court;

(5) where paragraph 2.10 above applies; or

(6) where a court order, rule or practice direction permits.”

13

Paragraph 2.10 adds:

“Where a date for a hearing has been fixed and a party wishes to make an application at that hearing but he does not have sufficient time to serve an application notice he should inform the other party and the court (if possible in writing) as soon as he can of the nature of the application and the reason for it. He should then make the application orally at the hearing.”

14

While there are many circumstances in which the court will entertain an application made orally at a hearing that has already been fixed, I refused to allow MTD permission to make this application orally and unsupported by any evidence. I should, in any event, have dismissed this application had it been necessary for me to engage with the principles in Denton v. TH White Ltd [2014] EWCA Civ 906; [2014] 1. W.L.R. 3296:

14.1 The failure to file evidence in good time was serious. The default was not de minimis. Further, such failure is especially significant where hundreds of pages of material are dumped on a litigant the night before a hearing. There was no merit in Mr Jinadu's submission that Willow had previously seen this material. In preparing for this hearing, Willow and its lawyers were entitled to focus on the actual evidence filed in these proceedings. Neither could be expected to assimilate and deal with this evidence overnight.

14.2 The lack of evidence in support of the application for relief from sanctions made it difficult to assess the reasons for default. It appeared from Mr Jinadu's submissions that the reason for the late evidence was simply his decision as counsel that he wished to rely on this material. This is not a proper reason for the default in circumstances where the evidence was available to Willow since 2018.

14.3 If admitted, the late evidence would have subverted the order of evidence, both contained in rule 8.5 and the agreed directions, and allowed MTD the last word. Alternatively, the late evidence would have put the hearing at risk in order to allow Willow a fair opportunity to consider and respond to the late evidence. In all the circumstances of this case, and having regard to the matters highlighted at rules 3.9(1)(a) and (b), the interests of justice plainly favoured dismissing any application for relief.

LATE EVIDENCE IN THE SUMMARY JUDGMENT APPLICATION

15

Rule 24.5(2) provides:

“If the applicant wishes to rely on written evidence in reply, he must–

(a) file the written evidence; and

(b) serve a copy on the respondent,

at least 3 days before the summary judgment hearing.”

16

The fresh evidence was not both filed and served at least three clear days before the summary judgment hearing. Indeed, the bulk of the new material was provided after hours the night before the hearing and was not exhibited to a statement. It is, in my judgment, important that applicants seeking summary judgment should not be permitted to ambush respondents. There are therefore sound reasons both for the requirement that the applicant should give at least 14 days' notice of the application for summary judgment and of the evidence in support. Equally, the court should be reluctant to allow late evidence in reply.

17

Taking into account the seriousness and significance of seeking to rely on late evidence in support of a summary judgment application, the lack of any proper explanation for the late evidence and the potential risk of an adjournment in order to allow Willow a proper opportunity to assimilate and respond to this evidence, I refused MTD permission to rely on the late evidence.

THE FACTS

18

Willow is a limited liability company incorporated in Luxembourg. MTD is an English building contractor. On 22 September 2015, MTD entered into a contract with Willow to design and build the 150-bed, 7-storey Nobu Hotel in Shoreditch. The contract price was £33,500,000.

19

The project was delayed. On 16 February 2017, the parties agreed a plan for the phased handover of the hotel in order to allow staff training and planned pre-opening activities to commence. MTD asserted claims for loss and expense and unexpected cost overruns. The parties discussed these claims and entered into a written agreement on 21 June 2017. They agreed a revised date for Practical Completion of 28 July 2017.

20

By his decision in the first adjudication, Jonathan Cope decided that the June agreement did not deem Practical Completion to have been achieved on 21 July 2017, but rather imposed an amended...

To continue reading

Request your trial
6 cases
  • Downs Road Development LLP v Laxmanbhai Construction (U.K.) Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 7 September 2021
    ...different elements of an adjudication decision was to the be that set out by Pepperall J in Willow Corp SARL v MTD Constructors Ltd [2019] EWHC 1591 (TCC) and by the Inner House of the Court of Session in Dickie & Moore Ltd v McLeish [2020] CSIH 38 which I will consider below. Applying tha......
  • Bexheat Ltd v Essex Services Group Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 19 April 2022
    ...the remainder: Cantillon Ltd v. Urvasco Ltd [2008] EWHC 282 (TCC) per Akenhead J at [63]; Willow Corp SARL v MTD Contractors Ltd [2019] EWHC 1591 (TCC) per Pepperall J at [68]–[74]. In this case, the compensation awarded is a fixed sum in respect of a discrete issue and of very modest val......
  • Dickie & Moore Limited Against Ronald James Mcleish, Diane Mcleish And Catriona Watt
    • United Kingdom
    • Court of Session
    • 8 November 2019
    ...High Court Judge Ms Finola Farrell QC (as she then was) at paragraphs 68, 70-71; and Willow Corp SARL v MTD Contractors Limited [2019] EWHC 1591 (TCC), per Pepperall J at paragraphs 67-74. If and in so far as observations in Cantillon Limited v Urvasco Limited [2008] BLR 250, (2008) 117 Con......
  • CC Construction Ltd v Raffaele Mincione
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 15 September 2021
    ...sum. In those circumstances I am minded to adopt the approach commended by Pepperall J in Willow Corp SARL v MTD Contractors Ltd [2019] EWHC 1591 (TCC) at [74] namely considering whether there is “a core nucleus of the decision that can be safely enforced”. Here the decision to the extent ......
  • Request a trial to view additional results
8 firm's commentaries
3 books & journal articles
  • Statutory adjudication
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...UK Ltd v Vinci Construction UK Ltd [2016] EWHC 2283 (TCC) at [16], per Fraser J. See also Willow Corp SARL v MTD Contractors Ltd [2019] EWHC 1591 (TCC) at [56]–[60], per Pepperall J. 559 In considering whether a respondent has had adequate opportunity to deal with the referring party’s case......
  • Contract administration
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Ltd v Costplan Services (South East) Ltd [2019] EWCA Civ 502 at [62]–[74], per Coulson LJ; Willow Corp SARL v MTD Contractors Ltd [2019] EWHC 1591 (TCC) at [41], per Pepperall J. See also Emson Eastern Ltd v EME Developments Ltd (1991) 55 BLR 114 at 122, where Judge Newey QC, considering th......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...EWCA Civ 519 III.21.47 Willow Corp SARL v MTD Contractors Ltd [2019] EWHC 1192 (TCC) III.24.89 Willow Corp SARL v MTD Contractors Ltd [2019] EWHC 1591 (TCC) I.5.117, III.24.109, III.24.139 Willshee v Westcourt Ltd [2009] WASCA 87; [2008] WASC 18 I.3.15, I.3.37, II.13.47, II.14.100, II.14.10......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT