Public Works Commissioner v Hills

JurisdictionUK Non-devolved
Judgment Date1906
Date1906
Year1906
CourtPrivy Council
[PRIVY COUNCIL.] COMMISSIONER OF PUBLIC WORKS (AND AS SUCH REPRESENTING THE COLONIAL GOVERNMENT) DEFENDANT. AND HILLS PLAINTIFF. ON APPEAL FROM THE SUPREME COURT OF THF CAPE OF GOOD HOPE. CROSS APPEALS CONSOLIDATED. 1906 April 9, 10; May 24. THE LORD CHANCELLOR, LORD DAVEY, LORD DUNEDIN, LORD ATKINSON, and SIR ARTHUR WILSON.

Railway Contract - Construction - Penalty for Non-completion of Line - Liquidated Damages - “Actual Cost” does not include Interest on Moneys expended.

It was provided in a railway construction contract that in the event which happened of non-completion of the line within a specified period the plaintiff contractor should forfeit to the defendant Government certain percentages which the Government retained out of moneys payable under this and two other railway contracts as a guarantee fund to answer for defective work and also certain security money lodged with its Agent-General “as and for liquidated damages sustained by the said Government for the non-completion of the said line”; and that it should be lawful for the Government to take possession of the incomplete line and pay the balance due in respect of its “actual cost”:—

Held that, on its true construction, the term “actual cost” was limited to the amount of moneys expended on the work, and that interest thereon could not be added.

Held, further, that the Government was not entitled to the retention and security moneys as liquidated damages; for the total amount thereof was indefinite, and in the case of the retention moneys depended on the progress of construction, the amount of the percentages, and the quantity of defective work. It could not, therefore, be treated as a genuine pre-estimate of loss, but the Government was entitled to obtain judgment in reconvention for such damages as it may have actually suffered through the plaintiff's breach of contract and deduct the same from the funds in question.

CROSS appeals from a decree of the Supreme Court of the Cape of Good Hope (February 29, 1904).

The questions determined arose in the circumstances detailed in the judgment of their Lordships under an agreement dated July 4, 1900, for the construction of a railway from Mossel Bay to Oudtshoorn, and were shortly — (1) upon what basis the actual construction of the railway is to be computed; (2) whether the respondent Hills is entitled to recover from the Colonial Government certain moneys deposited with and certain moneys retained by them as security for the completion of the said agreement; and (3) whether the Colonial Government is entitled to recover from Hills under the provisions of clause 16 of the said agreement the sum of 10,000l. by way of forfeit.

By clause 16 provision was made for the completion of the sections of the line within the periods of time therein mentioned, and the clause further provided: “If the concessionary shall not complete the sections of the line and works described in this clause within the periods aforesaid the concessionary shall forfeit to the Government the sum of 10,000l. (ten thousand pounds sterling) unless the delay is proved to the satisfaction of the Commissioner to have been caused by the act of God, war, insurrection, rebellion, strikes, lock-outs or combinations of workmen or other extraordinary or unforeseen circumstances beyond the control of the concessionary or from or on the part of the Railway Department.”

Judgment was entered in the Supreme Court for the respondent Hills for — (1.) 73,500l. 12s. 7d.; (2.) the return of the 50,000l. lodged with the Agent-General; and (3.) the payment of the retention moneys, viz., 66,146l. 18s. 7d., with interest from the date of summons.

The balance of the actual cost of construction not paid by the Government as found by the referees amounted, in fact, to 78,413l. 15s., and the amount of 73,500l. 12s. 7d. mentioned in the judgment was arrived at by deducting from the sum of 78,413l. 15s. the sum of 4913l. 2s. 5d. retention money under clause 6 of the contract, which was then added to the sum of 61,233l. 16s. 2d. (due to Hills in respect of the construction of the other lines, and retained under the provisions of clause 15 of the contract), so making up the sum of 66,146l. 18s. 7d. retention moneys ordered to be returned to the respondent Hills.

The Chief Justice, in his reasons, held that according to the true construction of the agreement the term “actual cost” was meant to include no more than payments actually made for materials used and work done by Hills, and therefore did not include interest as claimed by him; that the sum of 50,000l. and the retention moneys were, under the terms of the said agreement, held as security only for the completion of the line; that the Government having determined the agreement was not entitled to retain such security without proof of damage, and that there was no proof of any damage having been sustained by the Government. The Chief Justice further held, as to the sum of 10,000l. claimed by the Government to be forfeited under clause 16 of the said agreement, that the forfeiture was a penalty for non-completion of certain sections of the said line; that, unless damage by such non-completion was proved, the Government was not...

To continue reading

Request your trial
121 cases
  • Bulsing Ltd v Joon Seng & Company
    • Singapore
    • High Court (Singapore)
    • 29 September 1971
    ...(refd) Jones v Littledale 6Ad & E 486; 112 ER 186 (refd) Magee v Atkinson 2M & W 440; 150 ER 830 (refd) Public Works Commissioner v Hills [1906] AC 368 (folld) Thompson (WL) Ltd v Robinson (Gunmakers) Ltd [1955] Ch 177 (refd) Vic Mill Ltd, Re [1913] 1 Ch 183 (refd) Vic Mill Ltd, Re [1913] 1......
  • Cavendish Square Holdings Bv and Another v Talal El Makdessi
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 14 December 2012
    ...v New Garage and Motor Co. Ltd [1915] AC 79, for which he had had a dry run in delivering the judgment of the Privy Council in Public Works Commissioner v Hill [1906] AC 368. There were three other speeches of their Lordships in the House of Lords, and, as they were unanimous, to an exten......
  • Amble Assets Llp ((in Administration)) and Another v Longbenton Foods Ltd ((in Administration))
    • United Kingdom
    • Chancery Division
    • 21 July 2011
    ...ordering repayment of the sum so paid, less any damage actually proved to have been suffered as a result of non-completion: Commissioner of Public Works v. Hills [1906] A.C. 368. Accordingly, there is jurisdiction in the court to order repayment of the 25 per cent. deposit. 72 On behalf of ......
  • Talal El Makdessi v Cavendish Square Holdings Bv (Respondent/ 1st Claimant) Team Y&r Holdings Hong Kong Ltd (2nd Claimant)
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 26 November 2013
    ...it could not possibly have been regarded as damages for any possible breach which was in the contemplation of the parties". In Commissioner of Public Works v Hills [1906] AC 368 Lord Dunedin spoke of " a genuine pre-estimate of the creditor's probable or possible interest in the due perfor......
  • Request a trial to view additional results
1 firm's commentaries
7 books & journal articles
  • Damages
    • Canada
    • Irwin Books The Law of Contracts. Third Edition Remedies
    • 4 August 2020
    ...question of whether there has been a genuine pre-estimate of loss would focus on the intentions 391 Public Work Commissioner v Hills , [1906] AC 368 at 376 (PC), Lord Dunedin. See also Clydebank , above note 389. 392 Above note 384. 393 Dunlop , above note 387 at 89, quoted by Martin JA in ......
  • Table of cases
    • Canada
    • Irwin Books Remedies: The Law of Damages. Third Edition Limiting Principles
    • 21 June 2014
    ...231 Commercial Electronics Ltd v Savics, 2011 BCSC 1275 .............................. 255–56 Commissioner of Public Works v Hills, [1906] AC 368 (PC) .................... 530, 532 Compania Financiera Soleada SA v Hamoor Tanker Corpn Inc (“The Borag”), [1981] 1 All ER 856, [1981] 1 WLR 274,......
  • Judicial Oversight of Remedy Stipulation
    • Canada
    • Irwin Books Remedies: The Law of Damages. Third Edition Limiting Principles
    • 21 June 2014
    ...Clydebank Engineering & Shipbuilding Co v Don Jose Ramos Yzquierdo y Castaneda , [1905] AC 6 (HL); Commissioner of Public Works v Hills , [1906] AC 368 (PC) [ Hills ]; Jobson v Johnson , [1989] 1 All ER 621 (CA); Gilby, above note 6. Judicial Oversight of Remedy Stipulation 531 The question......
  • Lecture
    • Singapore
    • Singapore Academy of Law Journal No. 2017, December 2017
    • 1 December 2017
    ...37Clydebank Engineering and Shipbuilding Co Ltd v Don Jose Ramos Yzquierdo y Castaneda[1905] AC 6; Commissioner of Public Works v Hills[1906] AC 368; Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd[1915] AC 79. 38Cavendish Square Holding BV v Talal El Makdessi[2015] UKSC 67 at [3......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT