Arroyo and Others v Equion Energia Ltd (formerly known as BP Exploration Company (Colombia) Ltd)

JurisdictionEngland & Wales
JudgeMr Justice Stuart-Smith
Judgment Date27 July 2016
Neutral Citation[2016] EWHC 1699 (TCC)
Docket NumberCase No: HT-2013-000003
CourtQueen's Bench Division (Technology and Construction Court)
Date27 July 2016
Between:
Pedro Emiro Florez Arroyo & Others
Claimants
and
Equion Energia Limited (formerly known as BP Exploration Company (Colombia) Limited)
Defendant

[2016] EWHC 1699 (TCC)

Before:

The Honourable Mr Justice Stuart-Smith

OCENSA PIPELINE GROUP LITIGATION

Case No: HT-2013-000003

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

The Rolls Building

Fetter Lane, EC4A 1NL

Alexander Layton QC, Sudhanshu Swaroop, Justine Thornton, Angharad Parry and Claire McGregor (instructed by Leigh Day) for the Claimants

Charles Gibson QC, Oliver CampbellQC, Christopher Lewis, Noel DilworthandKathleen Donnelly (instructed by Freshfields Bruckhaus Deringer LLP) for the Defendant

Hearing dates: 2 October 2014, 15 October 2014 – 5 March 2015

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

Mr Justice Stuart-Smith Mr Justice Stuart-Smith
1
1

Large-scale civil engineering and infrastructure projects routinely give rise to public benefit and private detriment, whether they be in the Cotswolds or the Andes. This case involves the consequences of laying a pipeline in Colombia in the mid-1990s, which ran from the oil-fields of Cusiana and Cupiagua in the South to the sea at Coveñas in the North. Construction work commenced in about December 1995 and continued until August 1997 { J24/82T/1}. The pipeline is known as the Ocensa pipeline for reasons that will appear. It passed through regions characterised by difficult terrain, fragile soils, tropical rainfall, and a lawless lack of security; and in doing so it passed through many and varied private land-holdings. For all of these reasons it was a challenging undertaking.

2

The benefits of such a pipeline to the Colombian economy and public need hardly be stated. At the same time, the potential detriments to private landowners whose properties were affected by the creation of and works on a Right of Way ["the ROW"] that was seldom (if ever) less than 25 metres wide and in which the pipeline was laid are easy to imagine. In particular, it was well known at all material times that the stripping of the land, storage of quantities of soil, working with heavy machinery, and crossing of watercourses gave rise to a risk of erosion of materials from the ROW, especially if disturbed or newly reinstated soil was subject to heavy rainfall. To obviate that risk, temporary and permanent works were undertaken that were intended to minimise or prevent erosion.

3

There was nothing new in the recognition of the risks inherent in the laying of the Ocensa pipeline, though the protective techniques were subject to development with time. One of the features of the Ocensa project was that for much of its course it followed the path of another pipeline ["the ODC pipeline"] so that much of the work for the Ocensa pipeline took place on or adjacent to what had been the ROW for the ODC pipeline when it had been laid in about 1990–1992.

4

This litigation is brought by 109 claimants in respect of 73 farms, each of whom claims that the Ocensa pipeline caused damage for which he or she should be compensated. It is brought in England because the Defendant was at the relevant time an English subsidiary of BP and was involved in the Ocensa project. The substantive claims are subject to the Colombian law of torts and contract. The State of Colombia formally recognises the public benefit attaching to oil pipeline projects and has established a regulatory legal framework that reflects the tension between public benefit and private detriment to which I have already referred. Whether and to what extent that framework creates, limits or excludes private law rights is only one of the elements of Colombian law affecting the outcome of this litigation.

5

The existence of 74 claims led the parties and the Court initially to choose 10 and to treat them as "lead cases" in the hope that decisions of the Court on those 10 would lead to resolution of all or most of the others. This approach was proportionate, sensible and inevitable given that each claim is fact specific and, although financially significant for the individual claimants, the claims are not enormous in absolute terms. In the event, as the accumulated evidence for the lead cases expanded, the parties agreed that it was only feasible to try four cases in the period allotted by the Court for the trial. This judgment is the result of the trial of those four cases, which took 62 court days of openings, evidence and closing submissions. The time spent in court was only the tip of an iceberg of time and effort invested by the parties. The trial bundle was about 135,000 pages, including expert evidence that took up about 45,000 pages. The Court did not visit Colombia but over 20 hours of film footage and many photographs have been available which provide important evidence both for the experts and for the Court. Closing submissions were formidably ordered, cross-referenced and presented in texts of over 2400 pages plus numerous attachments. It might be thought that, with such an abundance of material, no stone has been left unturned, and so it has sometimes felt. Even so, the documentation was not complete, not every witness who might have had relevant evidence to give was called, and the pressures on those conducting the litigation to concentrate on a selection of the most important aspects of the litigation were considerable.

6

Because I have been unable to make the judgment shorter, I should issue two health warnings for anyone tempted to read it. First, while the trial and its outcome are of intense interest to those directly involved, I doubt whether my attempts to determine how the Supreme Court of Colombia would apply Colombian law to the facts of these cases will interest or influence either English or Colombian lawyers who are not obliged to read them. Second, I think it unlikely that the detailed facts underlying the individual claims will be of general interest. Also, it should be understood that, although I have considered and taken into account the entirety of the closing submissions on both sides (including following every hyperlinked reference in those submissions) when preparing and writing the judgment I have not attempted to set out every argument or to refer to every piece of evidence in the judgment. To follow the traditional format of setting out both sides' arguments and all of the evidence relied upon would probably have doubled the length of the judgment and the time taken to produce it. I have therefore attempted to synthesise the positions adopted and the main arguments advanced by the parties, without necessarily setting out everything on which the parties have relied, and have referred to evidence to the extent necessary for coherence. In particular, I have generally given the page reference for the evidence on which I have relied for my findings rather than setting out all relevant evidence either by reference or in full.

7

In briefest outline, I have concluded that all four of the Lead Claims that are the direct subject of this action fail. Very largely they fail on the facts; but I have in each case also considered the legal basis on which the Claims were brought and the application of relevant principles of Colombian Law to each claim. The purpose of this judgment is to decide the four Trial Lead Claims and to provide a basis for the resolution of the claims regarding the 69 farms that were not considered in detail at the trial. To that end I have, as requested, made extensive findings about Colomibian Law irrespective of their direct applicability to the four Trial Lead Cases. I have also considered the entire body of expert evidence in considerable detail, outlining what appear to an English Court to be the strengths and weaknesses of the expert evidence that was led and tested at trial. That has been made necessary partly in order to reach necessary findings in the Trial Lead Cases and partly so that the parties may appreciate their general position on the expert evidence when considering the merits of the cases that were not tried.

2

Index

Section

Paragraphs

1. Preliminary

1

2. Index

-

3. Legal Framework

9

4. The Lay Witnesses

247

5. General Narrative

253

6. Procedural History

397

7. Legal Responsibility

418

8. The Four Trial Claims

490

9. The Lay Witnesses

492

10. The Expert Evidence

494

Geotechnical Engineering & Photointerpretation

503

Hydrology & Water Quality

618

Agrology

723

Agronomy

767

Fishing and Aquaculture

793

Veterinary Science

817

Pipeline Project Management

886

Economics and Pricing

888

11. Note on Expert Evidence

921

12. Lead Claimant 54 in Detail

925

13. Lead Claimant 74 in Detail

1133

14. Lead Claimant 39 in Detail

1410

15. Lead Claimant 50 in Detail

1649

3

The Legal Framework.

8

Section Index

Applicability of Colombian Law

Applicability of Colombian Law

9

The Experts

17

The Hierarchy of Colombian Law

20

Rules for the Interpretation of the Law

23

The Regulatory Framework

24

The Codes of Mines 1887, 1947 and 1988

26

The Exploitation of Oil and the Petroleum Codes

37

Ecopetrol and Association Contracts

44

The Requirements for the existence of a contract and/or valid contractual obligations

48

Principles and rules for the interpretation of contracts

71

The Duty of Good Faith in Contract

74

Due Care in the Performance of the Contract

104

Abuse of Rights in Contract and Tort

105

Circumstances in which a contract is superseded or extinguished by a later agreement.

...

To continue reading

Request your trial
6 cases
2 books & journal articles
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Ocean Outdoor UK Ltd v London Borough of hammersmith and Fulham [2019] EWCa Civ 1642 I.4.67 Ocensa pipeline Group Litigation, re [2016] EWhC 1699 (TCC) III.20.81 Ochroid Trading Ltd v Chua Siok Lui [2018] SGCa 5 I.2.167, II.6.361 O’Connell v Commissioner for Government Transport (1954) 100 ......
  • Subcontracts, assignment, novation, waiver and estoppel
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...for a novation to transfer both contractual obligations and obligations in tort: see, eg, Re Ocensa Pipeline Group Litigation [2016] EWHC 1699 (TCC) at [184]–[185] and [488]–[489], per Stuart-Smith J (considering Colombian law). 231 It may not strictly be correct to describe novation as inv......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT