Dr James Charles Dixon and Another v Radley House Partnership (A Firm)and Others

JurisdictionEngland & Wales
JudgeThe Honourable Mr Justice Stuart-Smith
Judgment Date17 October 2016
Neutral Citation[2016] EWHC 2511 (TCC)
Docket NumberCase No: HT-2015-000407
CourtQueen's Bench Division (Technology and Construction Court)
Date17 October 2016
Between:
(1) Dr James Charles Dixon
(2) Dr Jenni Julie Dixon
Claimant
and
(1) Radley House Partnership (A Firm)
(2) Mr Christopher Reading T/A Chris Reading & Associates
(3) Chris Reading & Associates (A Firm)
Defendant

[2016] EWHC 2511 (TCC)

Before:

The Honourable Mr Justice Stuart-Smith

Case No: HT-2015-000407

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice

Strand, London, WC2A 2LL

Mr Tom Owen (instructed by BPL Solicitors Limited) for the Claimants

Ms Krista Lee (instructed by DWF LLP) for the First Defendant

Mr Daniel Goodkin (instructed by Beale & Company Solicitors LLP) for the Second and Third Defendants

Hearing dates: 20 September 2016

The Honourable Mr Justice Stuart-Smith

Introduction

1

The Defendants apply to amend their Defences to plead limitation. On normal principles I would expect to allow the amendments if they had any real prospects of success at trial. For the reasons set out in this Judgment, the amendments as drafted have no prospects of success and I refuse permission to amend. The applications generated over 1250 pages of documents, much of which related to the procedural chronology which I summarise below. At the heart of the applications lies a dispute about the consequences that follow when a Claimant fails to proffer the correct fee for the issuing of proceedings.

2

The summary answer to the dispute, in a case where it is not alleged that a Claimant's failure to proffer the correct fee is abusive procedural conduct, may be split into two periods:

i) In the period between (a) when the Claimant submits the claim form and proffers the inadequate fee and (b) when the Court issues proceedings, the failure to proffer the correct fee will prevent the conclusion that the action has been "brought" for the purposes of the Limitation Act 1980 before the moment that the Court issues the proceedings; but

ii) Once the Court issues the proceedings, the mere fact that the fee proffered by the Claimant and accepted by the Court (a) is less than should have been proffered and accepted for the claim identified in the Claim Form or (b) becomes so because of a subsequent increase in the quantum of the claim advanced in the proceedings does not prevent the action from being "brought" for the purposes of the Limitation Act 1980 when it is issued by the Court.

The Factual Background

3

The Claimants own and live in a house in Hambledon in Hampshire. In and from 2007 they wanted to carry out substantial refurbishment of their home. To that end they engaged the First Defendant ["RHP"] in October 2007 to act as architect and the Second Defendant ["CRA"] in November 2007 as M&E Consultants. I understand the Third Defendant to be the principal or guiding light of CRA. I shall refer to the Second and Third Defendants collectively as CRA unless it is necessary to distinguish between them. The refurbishment of the house did not go smoothly, with the result that CRA's appointment ended on 3 June 2009 and RHP's appointment ended on 18 March or 1 April 2010. For the purposes of these applications I assume that the cause of action in contract or tort underlying any claim that the Claimants might have against CRA and RHP would have accrued, at the latest, on the date of conclusion of their respective retainers.

The Claim against RHP

4

On 23 December 2010 solicitors acting for the Claimants wrote a Pre-Action Letter of Claim to RHP. The letter alleged that RHP had negligently advised that it would be more economical for RHP to charge on an hourly basis rather than on the basis of a percentage of the cost of the works. The letter alleged that the difference between the fees the Claimants would have had to pay RHP adopting a percentage-based calculation and the fees they actually paid on the hourly basis of calculation was £35,894.78 inclusive of VAT and it claimed that sum as damages for misrepresentation. For the purposes of RHP's application I assume that any cause of action accruing in relation to that misrepresentation claim would have accrued not later than the date on which the Claimants retained RHP on terms providing for fees calculated on an hourly basis, i.e. on or about 27 October 2007. RHP does not submit that it accrued before then.

5

The Pre-Action Letter of Claim also made generalised assertions that RHP had acted in breach of contract and negligently in the performance of its services during the course of its retainer. The letter said that rectification of defects and completion of the project was being undertaken using another architect and that full particulars would be provided "in due course". The letter continued (at [25]):

"In the meantime, and on the basis that the Claimants reserve the right to provide further particulars, the Claimants contend that in breach of contract and negligently [RHP]:

25.7 Failed to administer the building Contract so as to achieve speedy and economical completion of the works;

25.8 Certified monies as due to the contractor without exercising any reasonable skill and care to ascertain the value of the works carried out and materials supplied;

25.9 Failed to inspect and/or supervise the works properly or at all"

The letter then asserted (at [26]) that:

"The Claimants have thereby suffered loss and damage, including but not limited to the overpayment of fees in the sum of £35,894.78 (inc VAT)."

6

It would have been understood by anyone reading the Pre-action letter that the Claimants considered that they may have a claim over and beyond the misrepresentation claim but were not yet in a position to articulate it further or more precisely. In particular, they were not in a position to quantify what, if any, loss or damage had flowed from the negligence or breach of contract that they identified in general terms in the letter. In its itemised letter of response, which was sent on 2 February 2011, RHP denied the allegations set out in [25] and [26] of the Pre-action Letter of Claim.

7

The Claimants prepared to issue proceedings against RHP and sent their draft claim form and a fee of £395 to the Bournemouth and Poole County Court so that they arrived at the Court on 25 October 2013. The Court had a backlog of cases as a result of which the proceedings were not issued until 7 November 2013. By a letter dated 19 November 2013, the Court wrote that the date on which the claim form is received by the Court "is the date used for the purpose of limitation." 25 October 2013 was less than 6 years after the cause of action for the Claimants' misrepresentation claim or any causes of action in tort or contract relating to the discharge of RHP's obligations under its retainer. 7 November 2013 was more than 6 years after the assumed latest date for the accrual of the cause of action for the misrepresentation claim and any cause of action in tort of contract that had accrued during the first ten days of RHP's retainer.

8

The content of the Claim Form is central to RHP's submissions on its application to amend. Under the heading "Brief details of claim" it stated:

"The Claimants' claim is for damages for breach of a written contract made between the Claimants and the Defendant on or about 27 October 2007 and/or breach of duty and/or negligence and/or misrepresentation and/or negligent misstatement on or about 12 October 2007 arising out of or in connection with the oral and/or written statements made by the Defendant its servants or agents, and in connection with the Defendant acting as architect for the Claimants in or about 27 October 2007 to 1 April 2010 for carrying out and/or supervision of the building works at [the Claimants' home], together with interest pursuant to Section 60 of the County Courts Act 1984."

Under the heading "Value" it stated:

"Payment of £35,894.78; Damages for breach of contract and/or Damages for negligence to be assessed; interest and costs."

In the boxes at the bottom of the front page of the claim form it stated:

It is common ground that a Court Fee of £395.00 was the fee that was required to be paid in respect of a money claim of up to (but not more than) £50,000.

Amount Claimed

£35894.78

Court Fee

£395.00

Solicitor's Costs

to be assessed

Total Amount

£36289.78

9

On 24 February 2014, the Claimants served the Claim Form and their Particulars of Claim on RHP. The Particulars of Claim pleaded the claim in misrepresentation at [27]–[32]. From [82] it set out the Claimants' case on breach of duty under three headings: (1) cost control; (2) the supply and installation by the contractor of M&E Services; and (3) repudiation of the appointment by RHP. There is nothing to suggest that any of the three heads of claim arose in the first 10 days of RHP's retainer. The Particulars of Claim alleged (at [98]) that the Claimants had been obliged to engage a remedial works contractor to remedy the original contractor's works at a cost to the Claimants of £431,305 plus VAT of £84,389.53; and (at [100]) that the Claimants had incurred an additional cost of £75,589.00 plus VAT because of replacing RHP with another architect.

10

It has not been suggested that the claims advanced in the Particulars of Claim were not covered by the terms of the "Brief details of Claim" in the Claim Form. Despite (or perhaps because of) the fact that the Particulars of Claim were advancing a claim for damages way in excess of the sums claimed under the misrepresentation claim, RHP's solicitors wrote to the Claimants' solicitors on 12 March 2014 including the sentence: "We note that your Claim Form caps your clients' recoverable losses at £35,895." The letter also asked for an extension of time for service of the Defence. It did not raise any question of limitation. When the Claimant's solicitors replied to that letter on 21 March, they did not respond to the reference to capping of losses but...

To continue reading

Request your trial
4 cases
  • Hayes v Butters and another (No 2)
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 1 January 2021
  • Atha & Company Solicitors v Zoe Liddle
    • United Kingdom
    • Queen's Bench Division
    • 9 July 2018
    ...retreat from the more mechanistic approach taken in the earlier first instance decisions was accelerated by Stuart-Smith J in Dixon v Radley House Partnership [2016] EWHC 2511 (TCC). In that case, the claimant brought negligence proceedings against the defendant architects. Proceedings wer......
  • Dr. James Charles Dixon and Another v Radley House Partnership and Others
    • United Kingdom
    • Queen's Bench Division
    • 25 November 2016
    ...the application to amend the defences made by both parties and the judgment which I gave on 17 October refusing permission to amend: [2016] EWHC 2511 (TCC). 2 In the light of that judgment, the claimants apply for the costs of the application on an indemnity basis, and for those costs to b......
  • Freeport Container Port Ltd v Jermaine Campbell
    • Bahamas
    • Court of Appeal (Bahamas)
    • 30 March 2021
    ...252 applied David Cornish v DPP SCCrApp. No. 174 of 2018 mentioned Dixon and another v Radley House Partnership (A Firm) and others [2016] EWHC 2511 (TCC) applied Hortenberry v. Palmer 992 N.E.2d 921 (Ind. App. 2013) distinguished Shaquille Culmer v DPP SCCrApp. No. 141 of 2019 mentioned W......
2 books & journal articles
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...McKrill [2005] WaSCa 222 II.8.137, II.8.142 Dixon v Hatield (1825) 2 Bing 439; 130 ER 375 III.20.50 Dixon v Radley House Partnership [2016] EWHC 2511 (TCC) III.26.38, III.26.74 Dixon v Radley House Partnership [2016] EWHC 3485 (QB) III.26.272 clxxxvi TaBLE OF CaSES Dixon v South australian ......
  • Litigation
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...statute, at least where the claimant is not guilty of any procedurally abusive conduct: see Dixon v Radley House Partnership [2016] EWHC 2511 (TCC). See also Glenluce Fishing Co Ltd v Watermota Ltd [2016] EWHC 1807 (TCC). 132 Which includes arbitration proceedings: Arbitration Act 1996 (UK)......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT