Joseph Gleave & Son Ltd v Secretary of State for Defence

JurisdictionEngland & Wales
JudgeThe Hon Mr Justice Coulson,The Hon. Mr Justice Coulson
Judgment Date17 February 2017
Neutral Citation[2017] EWHC 238 (TCC)
Docket NumberCase No: HT-2016-000302
CourtQueen's Bench Division (Technology and Construction Court)
Date17 February 2017

[2017] EWHC 238 (TCC)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice

Rolls Building, Fetter Lane, London, EC4A 1NL

Before:

The Hon Mr Justice Coulson

Case No: HT-2016-000302

Between:
Joseph Gleave & Son Limited
Claimant
and
Secretary of State for Defence
Defendant

Jason Coppel QC and Fiona Banks (instructed by Weightmans LLP) for the Claimant

Sarah Hannaford QC and Ewan West (instructed by Treasury Solicitor) for the Defendant

Hearing date: 3 February 2017

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

The Hon Mr Justice Coulson The Hon. Mr Justice Coulson
1

INTRODUCTION

1

This is a dispute about the ongoing procurement of over 6,000 product lines of hand tools for essential military needs. Following various delays, the second stage of the tender process is now likely to be completed at the end of February 2017, and the award of the contract is scheduled for early May 2017. At the CMC on 3 February, when considering the procedural way forward, the parties adopted polarised positions: the claimant sought an expedited trial so that the outcome of its challenge would be known before the contract was awarded in early May, whilst the defendant sought a stay of the proceedings until after the contract award.

2

The hearing took significantly longer than the parties had estimated, in part because both sides were also using their respective applications to try and obtain tactical advantages for the future, particularly if the trial was not expedited and there was then a dispute about the contract award. In addition, both sides indicated that the outcome of this procedural dispute might have ramifications beyond the confines of these particular proceedings: towards the end of his submissions in reply, Mr Coppel expressly warned me about "the message" I would be sending to prospective claimants in procurement cases if I refused his application.

3

For these reasons, I had no real option but to reserve judgment. After the hearing, the parties provided yet further written arguments. On the next working day after the hearing (6 February), I informed leading counsel of the result and the particular order I proposed to make. I refer to that in greater detail at the end of this Judgment, at paragraphs 60–63 below.

4

This Judgment is structured as follows. In Section 2, I set out the factual background. In Section 3, I address the general principles of law concerned with speedy relief in procurement cases. In Section 4, I identify certain particular features of this case which I consider to be relevant to the applications before the court. Then, in Section 5, I deal with the principles relating to expedition and, in Section 6, analyse the claimant's claim for expedition. In Section 7, I address separately the defendant's application for a stay.

2

THE FACTUAL BACKGROUND

5

This procurement for hand tools has had a chequered history. There were at least two attempts in 2015 to procure hand tools by reference to particular manufacturers. These procurements were challenged by the claimant and subsequently abandoned. In February 2016, there was a procurement in respect of hand tools by reference to technical specifications ("the first 2016 procurement"). That procurement too was challenged by the claimant in the TCC, but proceeded to tender evaluation. I am told that it did not lead to a contract because no compliant bids were received.

6

In relation to the first 2016 procurement, following the challenge by the claimant but before the outcome of the tender process was known, the claimant's solicitors wrote to the Treasury Solicitor on 5 May 2016 to propose a stay of the proceedings pending the outcome of the tender process. The defendant agreed to that suggestion. That is the course of action now proposed by the defendant in respect of the latest challenge, but it is opposed by the claimant.

7

The current procurement is a further attempt to procure hand tools for essential military needs. The tender documents were made available at some point between 7 and 12 October 2016 (the precise date, like everything else in this case, appears to be disputed). The relevant product lines are set out within Annex A to the Invitation to Tender ("ITT"). Many are referenced by a Manufacturers' Part Number ("MPN"). The claimant contends that this is a breach of the Public Contracts Regulations 2015 ("the Regulations"): they argue that the use of MPNs cannot be justified and that, accordingly, the use of MPNs is an unlawful obstacle to the opening up of the procurement to competition.

8

The claimant's letter of claim was dated 2 November 2016. The Claim Form was issued on 10 November 2016, and the Particulars of Claim served on 17 November 2016. The Defence was served on 15 December 2016, and included the assertion of a limitation defence. The Reply was dated 23 January 2017.

9

It was not until 23 January 2017 that the claimant suggested, for the first time, that the trial in these proceedings should be expedited. A trial date of 13 March was suggested. Subsequently, in the days leading up to the CMC on 3 February, the claimant produced a flurry of proposals dealing with the detail of how the trial might be expedited. As previously noted, however, the parties' positions remained polarised.

3

SPEED IN PROCUREMENT CASES

10

The importance of speed in procurement cases was first identified in the Council Directive (89/665/EEC) (as amended), commonly known as the "Remedies Directive". The preamble to the Remedies Directive stated:

"Whereas the opening-up of public procurement to Community competition necessitates a substantial increase in the guarantees of transparency and non-discrimination; whereas, for it to have tangible effects, effective and rapid remedies must be available in the case of infringements of Community law in the field of public procurement or national rules implementing that law…

Whereas, since procedures for the award of public contracts are of such short duration, competent review bodies must, among other things, be authorized to take interim measures aimed at suspending such a procedure or the implementation of any decisions which may be taken by the contracting authority; whereas the short duration of the procedures means that the aforementioned infringements need to be dealt with urgently…"

11

The relevant parts of the Articles (as amended) state:

" Article 1

Member States shall take the measures necessary to ensure that, as regards contracts…decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in the following Articles 2–2F of this Directive…

Article 2

1. The Member States shall ensure that the measures taken concerning the review procedures specified in Article 1 include provision for the powers to:

(b) either set aside or ensure the setting aside of decisions taken unlawfully, including the removal of discriminatory technical, economic or financial specifications in the invitation to tender, the contract documents or in any other document relating to the contract award procedure…"

12

The United Kingdom complied with the Remedies Directive through the Public Contracts Regulations, which have been amended on a number of occasions and are now in the 2015 version. The Regulations concerned with time limits are Regulations 92 and 94–96 as follows:

" General time limits for starting proceedings

92. (1) This regulation limits the time within which proceedings may be started where the proceedings do not seek a declaration of ineffectiveness.

(2) Subject to paragraphs (3) to (5), such proceedings must be started within 30 days beginning with the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen.

(3) Paragraph (2) does not require proceedings to be started before the end of any of the following periods:-

(a) where the proceedings relate to a decision which is sent to the economic operator by facsimile or electronic means, 10 days beginning with—

(i) the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision;

(ii) if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;

(b) where the proceedings relate to a decision which is sent to the economic operator by other means, whichever of the following periods ends first:-

(i) 15 days beginning with the day after the date on which the decision is sent, if the decision is accompanied by a summary of the reasons for the decision;

(ii) 10 days beginning with—

(aa) the day after the date on which the decision is received, if the decision is accompanied by a summary of the reasons for the decision; or

(bb) if the decision is not so accompanied, the day after the date on which the economic operator is informed of a summary of those reasons;

(c) where sub-paragraphs (a) and (b) do not apply but the decision is published, 10 days beginning with the day on which the decision is published.

(4) Subject to paragraph (5), the Court may extend the time limits imposed by this regulation (but not any of the limits imposed by regulation 93) where the Court considers that there is a good reason for doing so.

(5) The Court must not exercise its power under paragraph (4) so as to permit proceedings to be started more than 3 months after the date when the economic operator first knew or ought to have known that grounds for starting the proceedings had arisen.

(6) For the purposes of this regulation, proceedings are to be regarded as started when the...

To continue reading

Request your trial
3 cases
  • The Secretary of State for Transport v Arriva Rail East Midlands Ltd (“Arriva”)
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 18 December 2019
    ...respondents. 128 Another example of the Jobsin approach that was cited to us is Gleave and Son Ltd v Secretary of State for Defence [2017] EWHC 238 (TCC); [2017] PTSR 607. In that case, the ITT identified relevant product lines by reference to a manufacturers' part number (“MPN”) and the ......
  • Access for Living v London Borough of Lewisham
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 23 December 2021
    ...and Mr Paines submits, relying on Jobsin and the decision of Coulson J in Joseph Gleave & Son Ltd. v Secretary of State for Defence [2017] EWHC 238 (TCC) at [13], that the date when the cause of action accrued in relation to a challenge to tender documents was the date of the tender docume......
  • CMAC Group UK Ltd v Abellio Trandport Holding Ltd and Others
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 17 September 2021
    ...order to see whether the loss will crystalise. The point was considered in Joseph Gleave & Son Ltd v Secretary of State for Defence [2017] EWHC 238 (TCC), [2017] PTSR 607. In that case, the Ministry of Defence conducted a procurement exercise. The claimant company sought to challenge the ......
3 books & journal articles
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Steamship Line Ltd v Imperial Smelting Co Ltd [1942] 1 AC 154 II.9.143 Joseph Gleave & Son Ltd v Secretary of State for Defence [2017] EWHC 238 (TCC) I.4.69, III.26.85 Jose v MacSalvors Plant Hire Ltd [2009] EWCA Civ 1329 I.3.14, II.12.40 Joseph Finney plc v Vickers (Unreported, TCC, HHJ Wi......
  • Litigation
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...applicable in England for when an expedited trial will be ordered, see Joseph Gleave & Son Ltd v Secretary of State for Defence [2017] EWHC 238 (TCC) at [24], per Coulson J. 341 State of Queensland v J L Holdings Pty Ltd (1997) 189 CLR 146 at 154, per Dawson, Gaudron, McHugh JJ. LITIGATION ......
  • Procurement
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Decommissioning Authority [2016] EWHC 3326 (tCC) at [7], per Fraser J; Joseph Gleave & Son Ltd v Secretary of State for Defence [2017] EWHC 238 (tCC) at [17], per Coulson J; Sysmex (UK) Ltd v Imperial College Healthcare NHS Trust [2017] EWHC 1824 (tCC) at [12]–[13], per Coulson J; DHL Suppl......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT