SSE GENERATION Ltd Pursuer against HOCHTIEF SOLUTIONS AG and Another Defender

JurisdictionScotland
JudgeLord Woolman
Neutral Citation[2016] CSOH 177
Year2016
Docket NumberCA162/12
Date21 December 2016
Published date21 December 2016
CourtCourt of Session (Outer House)

OUTER HOUSE, COURT OF SESSION

[2016] CSOH 177

CA162/12

OPINION OF LORD WOOLMAN

In the cause

SSE GENERATION LIMITED

Pursuer

against

HOCHTIEF SOLUTIONS AG & ANOTHER

Defender

Pursuer: Moynihan QC, S Smith QC, Barne, Delibegović-Broome & P O’Brien; CMS Cameron McKenna

Defender: Clark QC, Richardson & A Sutherland; Clyde & Co

21 December 2016

Contents

1. Introduction

Summary

Issues

Preliminary Matters

2. The Principal Persons

SSE

Hochtief

Donaldson

Pöyry

Andritz

3. Hydroelectric Tunnels

History

Design & Rock Classification

Methods of Construction

Lined & Unlined Tunnels

Previous Tunnel Collapses

4. The Glendoe Scheme

Geography

Main Features

Headrace Tunnel

Tailrace Tunnel

Turbine

Other Aspects

Head Loss

Aqueduct and Access Tunnels

General Operating Centre

Watering Up and Dewatering

Measurements

5. Award of the Contract

Tender Procedure

6. The Construction Period

Hochtief arrives on Site

Tunnel Boring Machine

The TBM Drive

Task of the Engineering Geologist

Four Excavation Classes

Rock Support Methodology

Mapping Procedure

Geological Database

Signing the REC sheets

What Classes were Predicted and Found?

Conagleann Fault Zone

7. From Watering up to Takeover

8. SSE Operates the Scheme

Takeover

O & M Manuals

National Grid Tests

Monitoring

Glendoe’s Role within the SSE Fleet

Odd Readings

9. The Collapse & Its Aftermath

Detection

Initial Strategy

SSE Informs Hochtief

Tunnel Inspections

10. Relations Cool

Attempts to Reach a Consensus

Conference Call on 25 September

Meeting at Edinburgh Airport on 5 October

SSE Meets HSE on 12 October

Two Further Meetings on 20 and 21 October

Essen Design Workshop on 29 October

Hochtief’s Proposals

SSE Issues an Ultimatum

11. Specialist Investigations

Jacobs

British Geological Survey

Donaldson

12. The Recovery Project

Commercial Pressures on SSE

SSE Selects BAM

Choice of Option E

BAM Mobilises to Site

Scope of the Remedial Works

Contract Changes

13. Why did the Tunnel Collapse?

The Short Answer

A Longer Answer

14. Witnesses & the Burden of Proof

15. Was there a Defect at Takeover?

Scope of the Dispute

Was The Scheme Contrary to the Works Information?

Was The Scheme Contrary to the Design?

16. Reasonable Skill and Care

What did the parties agree about classification?

Standard of Mapping

Joint Inspections in 2008

Three Miscellaneous Issues

(a) Did the REC Sheets Address Long Term Hazards?

(b) Was Hochtief’s Classification System Deficient?

(c) Would Probe Drilling Have Made a Difference?

Conclusion on Reasonable Care

17. Should Hochtief have Returned to Site?

18. Contributory Negligence

19. Causation

20. The Costs of the Recovery Project

Introduction

The Position of the Parties

General Principle

Choice of Option E

Costs Monitoring

Expert Evidence on Costs

Health and Safety

Betterment

21. Individual Heads of Claim

Bypass Tunnel

Downstream Access Tunnel

Concrete Invert

Three Concrete Plugs

Plant & Equipment

Secondary ‘Defects’

SSE Management Time

Progress, Delays & Productivity

Adjudication Award, Insurance & Low Availability Damages

22. The Counterclaim

23. Observations on the Proof

24. Conclusions

25. Appendix


1. Introduction

Summary

[1] Glendoe hydroelectric scheme was constructed between 2006 and 2008. It was the biggest such scheme to be built in Scotland for many years. It failed eight months after take over. A collapse had occurred in a main tunnel. Rock material had fallen from a breach in the crown over several months, leading to a blockage.

[2] The owner was anxious to recover its asset as soon as possible. It was losing substantial amounts of revenue while the scheme was out of commission. It entered into discussions with the contractor about remedial works. They were, however, unable to reach agreement. The main sticking point was money. Each party said that the other should bear the initial liability for the cost of the works. Attempts to broker a compromise were unsuccessful.

[3] Four months passed without a resolution. The owner then issued an ultimatum requiring the contractor to return to site to carry out the recovery project. The contractor declined to do so. In consequence, the owner instructed another engineering concern to undertake the remedial works. The works took much longer and cost far more than expected. The scheme did not begin to generate electricity again until August 2012.

[4] This litigation arises out of the collapse. The owner seeks to recover about £130 million. It maintains that various provisions in the contract imposed obligations on the contractor to undertake the remedial works. The contractor disputes liability. It contends that: (a) it completed the works in accordance with the contract, (b) the owner assumed the risk of the collapse at takeover, (c) the scope and cost of the recovery project is unreasonable, and (d) it was entitled to carry out the remedial works.

Issues

[5] There are several key questions in this case. Why did the collapse occur? Could it have been foreseen? Is the contractor to blame? Is the owner also partly to blame? Were the remedial works reasonable and necessary? The contract itself distinguishes between employer’s risk events and contractor’s risk events. It also prescribes the circumstances where the contractor is obliged to carry out the remedial works.

[6] At the core of the dispute lies a deceptively simple issue. It relates to the construction of the tunnel. Did the contractor misclassify the rock and in consequence fail to install the correct support? The owner submits that the answer is Yes. The contractor takes the opposite position. It maintains that it exercised reasonable skill and care in the design and construction of the tunnel and is therefore not liable.

Preliminary Matters

[7] At an earlier stage, the contractor argued that the joint insurance policy governed the matter and that the owner was precluded from bringing this action. Following a debate I issued a decision in favour of the owner: [2015] CSOH 92. The contractor undertook not to reclaim that issue prior to the proof. In closing submissions I learned that the owner has made a claim under the policy, which is the subject of arbitration. If it received an award that would have to be taken into account in respect of any damages it received in this action.

[8] I fixed the proof to take place over two court terms. At the end of the first term, the parties made a joint application to set aside a third term to deal with quantum. I refused that request.

[9] It is important to keep in mind the distinction between the collapse and the blocked section of the tunnel. The location, length and scale of the blocked section are known. The same parameters in respect of the collapse remain unknown.

[10] To avoid verbiage, I have rounded up most sums and measurements.

2. The Principal Persons

SSE

[11] I shall refer to the Scottish & Southern Electricity group of companies as ‘SSE’. SSE owns and operates a fleet of 80 hydroelectric power stations. Ten lie in the Great Glen area close to Glendoe. The SSE fleet contains a total of 214 tunnels with a combined length of 320km. Despite its substantial tunnelling experience, SSE took a limited role during the construction of Glendoe. Its project manager, Mr Neil Sandilands, said that was because “the process was being carried out by one of the world’s top contractors and supervised by one of the world’s top consultants.”

Hochtief

[12] Hochtief Solutions AG is a long-established engineering contractor with its headquarters in Germany. It has constructed rail, road and hydroelectric tunnels throughout the world. It set up an internal joint venture chaired by Bert Hoekstra to deliver the Glendoe scheme. It comprised various Hochtief divisions, including Hochtief UK Construction Ltd. I shall refer to the joint venture as ‘Hochtief’.


Jacobs

[13] SSE appointed Jacobs Gibb Ltd and Jacobs UK Ltd (together ‘Jacobs’) to act as its engineering geology consultant at Glendoe. Jacobs had an important role in relation to the design of both the original scheme and the recovery project. During the construction of the original scheme, it also had a supervisory function. Mr Sandilands described Jacobs as being SSE’s “eyes and ears in the tunnel”.

Donaldson

[14] SSE engaged Donaldson Associates Limited (‘Donaldson’) to provide technical advice on the recovery project. It also appointed Professor Andrew Sloan of Donaldson to act as its expert in this case.

Pöyry

[15] Hochtief retained Pöyry Energy JV (‘Pöyry’), a Finnish company, as its sub-contractor for the design of the civil works. Mr John Ager of Pöyry regularly visited the tunnels to monitor the works and liaise with Hochtief.

Andritz

[16] Hochtief also engaged Andritz, an Austrian company, to be its mechanical and electrical sub-contractor. In the early 2000s, SSE refurbished 25 of its power stations. Andritz was involved in that project, which standardised the electronic signals sent out by each plant. It therefore had some knowledge of SSE’s operations.


3. Hydroelectric Tunnels

History

[17] The science of tunnelling dates back to antiquity. Its modern history is linked to Scandinavia. After the First World War there was a shortage of steel for industry. Norwegian engineers discovered that water can be taken through unlined tunnels, provided that there is enough rock cover to counteract the water pressure inside the tunnel. The unlined tunnel concept was further developed in the 1950s as it afforded substantial savings in cost and time. Norway is now completely dependent on hydropower and has several thousand kilometres of unlined tunnels.

Design & Rock Classification

[18] There are risks to a tunnel at each stage of its life: excavation, watering up, operation and dewatering. It is crucial to ensure that the correct level of support is installed within the tunnel. Otherwise it may collapse. There are several recognised...

To continue reading

Request your trial
1 firm's commentaries
  • Contractor not liable following tunnel collapse
    • United Kingdom
    • JD Supra United Kingdom
    • 10 February 2017
    ...and care, and did not guarantee the fitness for purpose of its works including the tunnel. SSE Generation Ltd v Hochtief Solutions AG [2016] CSOH 177 The Glendoe Hydro Scheme, located above Loch Ness in the Highlands of Scotland, is the biggest scheme for the generation of hydro-electric po......
3 books & journal articles
  • The site
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...simply undertook to exercise reasonable skill and care in the performance of its works: see SSE Generation Ltd v Hochtief Solutions AG [2016] CSOh 177 at [159]–[164], per Lord Woolman (considering the NEC2 form of contract. he appeal from Lord Woolman’s judgment was allowed by a 2–1 majorit......
  • Litigation
    • United Kingdom
    • Construction Law. Volume III - Third Edition
    • 13 April 2020
    ...litigation are not bound by the agreement unless they expressly agree to be bound. 562 Any joint statement produced as a Solutions AG [2016] CSOH 177 at [156] and [258], per Lord Woolman (appeal allowed, for unrelated reasons: [2018] CSIH 26); Burr, “Hot-Tubbing with Witnesses of Opinion: C......
  • Defects
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...Ltd [2009] NSWSC 1302 at [69], per White J (considering the JCC-D 1994 form) (26 BCL 335); SSE Generation Ltd v Hochtief Solutions AG [2016] CSOh 177 at [188]–[189], per Lord Woolman (considering clause 82.1 of the NEC2 form of contract) (appeal allowed on unrelated grounds: [2018] CSIh 26)......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT