Stocznia Gdynia SA v Gearbulk Holdings Ltd

JurisdictionEngland & Wales
JudgeWard,Smith,Moore-Bick L JJ
Judgment Date13 February 2009
Neutral Citation[2009] EWCA Civ 75
Docket NumberCase No: A3/2008/1320
CourtCourt of Appeal (Civil Division)
Date13 February 2009
Between
Stocznia Gdynia S.A.
Claimant/Respondent
and
Gearbulk Holdings Ltd
Defendant/Appellant

[2009] EWCA Civ 75

Before : Lord Justice Ward

Lady Justice Smith and

Lord Justice Moore-Bick

Case No: A3/2008/1320

IN THE SUPREME COURT OF JUDICATURE

COURT OF APPEAL (CIVIL DIVISION)

ON APPEAL FROM THE HIGH COURT OF JUSTICE

Mr. Justice Burton

[2008] EWHC 944 (Comm)

QUEEN'S BENCH DIVISION (COMMERCIAL COURT)

Mr. Stewart Boyd Q.C. and Mr. Vernon Flynn Q.C. (instructed by Ince & Co) for the appellant

Mr. Graham Dunning Q.C. and Mr. Edmund King (instructed by Eversheds LLP) for the respondent

Hearing dates : 21 st and 22 nd January 2009

Lord Justice Moore-Bick

Lord Justice Moore-Bick :

Introduction

1

In 2000 and 2001 the appellant, Gearbulk Holdings Ltd (“Gearbulk”), entered into contracts with the respondent, Stocznia Gdynia S.A. (“the Yard”), for the construction of six 'Fleximax' vessels for delivery on various dates between 2001 and the end of March 2004. A separate contract was signed in relation to each vessel, but in all material respects they were in the same form. The present appeal is concerned with three of those contracts, namely, those relating to the vessels identified by the Yard as Hulls 24, 25 and 26.

2

In the event none of the three vessels in question was delivered. Some steel cutting was carried out in relation to Hull 24, but work on the vessel stopped in January 2003. No construction work of any kind was carried out on Hulls 25 and 26. Between June and October 2003 there were discussions between the parties, but they were inconclusive and on 7 th November 2003 Gearbulk wrote to the Yard terminating the contract in respect of Hull 24. It then exercised its right to recover under a bank guarantee the first instalment of the price which it had paid on signing the contract, together with interest at the agreed rate.

3

On 4 th August and 30 th November 2004 Gearbulk took similar steps to terminate the contracts relating to Hulls 25 and 26 respectively and to recover the first instalments of the price paid in respect of those two vessels. The terms of the letter terminating the contract for Hull 25 were in all material respects identical to those of the letter written in relation to Hull 24. The letter written in relation to Hull 26, however, was different and it will become necessary at a later stage to refer to the terms of all these letters in a little more detail.

4

Following the termination of the contracts a dispute arose between Gearbulk and the Yard. Gearbulk asserted that it was entitled in each case to recover damages for the loss of its bargain. The Yard said that because Gearbulk had exercised a right to terminate given by the contract its remedy in each case was limited to the recovery of the instalments of the price in accordance with the contract and nothing more. The dispute was referred to arbitration in accordance with the terms of the contract. The parties appointed Sir Brian Neill as sole arbitrator.

The contracts

5

It is convenient at this point to refer in more detail to the terms of the three contracts. Since they were materially identical it is sufficient to refer to the contract for Hull 24, the most important parts of which for present purposes provided as follows:

“ARTICLE 5

TERMS OF PAYMENT

5.2 … the Contract Price shall be paid by the Purchaser to Seller in five (5) instalments in the manner set out below.

5.3 …

(a) Five (5) per cent … within seven (7) Banking Days from the Purchaser having received an executed Refund Guarantee

(b) Five (5) per cent … within seven (7) Banking Days of the date on which the Seller has given notice to the Purchaser of commencement of the steel cutting …

(c) Ten (10) per cent … within seven (7) Banking Days of the date on which the Seller has given notice to the Purchaser of commencement of the keel laying of the Vessel …

(d) Twenty (20) per cent … within seven (7) Banking Days of the date on which the Seller has given notice to the Purchaser of successful launching of the Vessel …

(e) Sixty (60) per cent … shall be paid to the Seller upon delivery of the Vessel …

5.7 Purchaser's Default

The Seller shall be entitled, but not bound, to declare the Purchaser in default where the Purchaser

(a) fails to pay to the Seller any instalment of the Contract Price when the same is due for payment..

(b) is declared … insolvent or bankrupt …

(c) fails to take delivery of the completed Vessel within three (3) Banking Days of when she is duly tendered for delivery by the Seller.

5.9 In the event of such termination by the Seller due to the Purchaser's default as provided for in this Article, the Seller shall be entitled to retain and apply the instalments already paid by the Purchaser towards the Seller's recoverable loss and damage and at the same time the Seller shall have the full right and power either to complete or not to complete the Vessel and to sell the Vessel at a public or private auction … provided that the Seller is always obliged to mitigate all losses and damages due to any such Purchaser's default …

The proceeds received by the Seller from the sale and the instalments already paid and retained shall be applied by the Seller … as follows:

First, in payment of all reasonable costs and expenses of the sale of the Vessel.

Second, if the Vessel has been completed, in or towards satisfaction of the unpaid balance of the Contract Price, or if the Vessel has not been completed, in or towards the satisfaction of the unpaid amount of the cost incurred by the Seller prior to the date of sale on account of [the] construction of the Vessel …

Third, the balance of the proceeds, if any, shall belong to the Purchaser and shall forthwith be paid over to the Purchaser by the Seller.

5.10 Refund Guarantee

(a) The instalments of the Contract Price paid by the Purchaser prior to delivery of the Vessel … shall be in the nature of advances to the Seller. In the event that the Purchaser shall exercise its right to terminate this Contract pursuant to any of the provisions hereof, the Seller shall forthwith refund to the Purchaser the aggregate amount of such instalments … together with interest thereon at the rate of 1 month LIBOR per annum.

(b) It is a fundamental term of this Contract that the Seller's obligation to make such refund of any of the pre-delivery instalments, with interest, shall be secured under and pursuant to the Refund Guarantee issued in favour of the Purchaser…

ARTICLE 10

DELAY in DELIVERY and DEFICIENCIES: SELLER'S DEFAULT

The Contract Price of the Vessel shall be adjusted by way of reduction in the event of any of the contingencies set out in this Article. Such adjustment shall be effected by way of reduction of the amount of the delivery instalment of the Contract Price … (it being understood by the Parties that any such reduction of the Contract Price shall [be] by way of liquidated damages and not by way of penalties).

The Purchaser shall not be entitled to claim any other compensation and the Seller shall not be liable for any other compensation for damages sustained by reason of events set out in this Article and/or direct consequences of such events other than liquidated damages specified in this Article.

In case the total amount of liquidated damages claimed by the Purchaser under this Article exceeds five per cent (5%) of the Contract Price, the Purchaser's right to liquidated damages shall be limited to such amount equal to and not exceeding five (5) per cent of the Contract Price as specified in Article 4.1 of this Contract.

10.1 Delay in Delivery

(a) In the event that delivery of the Vessel should be delayed beyond the Delivery Date, the Contract Price shall be reduced as follows

(i) no adjustment shall be made for the first thirty (30) days …

(v) the maximum reduction of the Contract Price pursuant to this Article 10.1(a) shall not exceed … $930,000

(b) If the delay in delivery of the Vessel shall comprise a period of more than one hundred and fifty (150) days beyond the Delivery Date then the Purchaser may, at its option, terminate this Contract.

(c) Without any prejudice to, and separately from, the foregoing, the Purchaser shall also be entitled, at its option, to terminate this Contract in the event that, for any reason whatsoever, the Vessel shall not have been delivered to the Purchaser hereunder on or prior to 15 August 2003 … [the “drop dead date”]

10.6 Seller's Default

The Purchaser shall also be entitled, but not bound, to declare the Seller in default and terminate the Contract:-

(a) if there is a major breach by the Seller of its obligation hereunder to proceed with the construction of the Vessel, such that, in the reasonable opinion of the Purchaser (supported by the opinion of the Classification Society), the Vessel cannot be completed and delivered to the Purchaser on or before the date specified in Article 10(1)(c) hereof …

(b) …

Upon the occurrence of any such event of default the [Purchaser] shall be entitled to terminate this Contract with the consequences hereinafter provided.

10.7 Effect of Termination

Upon termination of this Contract by the Purchaser in accordance with the provisions of Article 10 or any other provision of this Contract expressly entitling the Purchaser to terminate this Contract, the Seller shall forthwith repay to the Purchaser all sums previously paid to the Seller under this Contract, together with interest accrued thereon calculated at the rate of 1 month LIBOR per annum from the respective date(s) of payment of such sums until date of refund …

It is however further expressly understood and agreed upon by the Parties hereto that, if...

To continue reading

Request your trial
62 cases
  • Kuwait Rocks Company v AMN Bulkcarriers Inc. (The Astra) [QBD (Comm)]
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 18 April 2013
    ...Giorgis)UNK [1976] 2 Ll Rep 192. Stocznia Gdanska SA v Latvian Shipping Co [2003] 1 CLC 282. Stocznia Gdynia SA v Gearbulk Holdings Ltd [2009] 1 CLC 134. Tankexpress A/S v Compagnie Financiere Belge des Petroles SAELR [1949] AC 76. Tenax Steamship v Owners of the Brimnes (The Brimnes)WLR [1......
  • Soteria Insurance Ltd (formerly CIS General Insurance Ltd) v IBM United Kingdom Ltd
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 4 April 2022
    ...be used in order to rebut the presumption.” 35 That point was taken up by Moore-Bick LJ in Stocznia Gdynia SA v Gearbulk Holdings Limited [2010] QB 27, where he said: “The court is unlikely to be satisfied that a party to a contract has abandoned valuable rights arising by operation of law......
  • ISG Retail Ltd v Castletech Construction Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 22 May 2015
    ...in that contract (see, for example, Slade LJ in Fillite (Runcorn) Ltd v Aqua-Lift [1989] WL 649986, at page 8). 17 In Stocznia Gdynia SA v Gearbulk Holdings [2009] EWCA Civ 75, Moore-Bick LJ said, at [40]: "On discharge of a contract of this kind a buyer who has paid the whole or part of th......
  • Spm Membrane Switch Sdn Bhd v Kerajaan Negeri Selangor
    • Malaysia
    • Federal Court (Malaysia)
    • Invalid date
  • Request a trial to view additional results
8 firm's commentaries
  • COVID-19: Checklist – Issuing A Termination Notice Under English Law
    • United Kingdom
    • JD Supra United Kingdom
    • 2 April 2020
    ...689, 717-718). The more valuable the right, the clearer the exclusory words will need to be (Stocznia Gdynia SA v Gearbulk Holdings Ltd [2009] EWCA Civ 75 [23]). xiii Unfair Contract Terms Act 1977 (UK) s 3(1)&(2) (b)(ii). xiv Stocznia Gdanska SA v Latvi an Shipping Co (No.2) [2002] EWCA Ci......
  • A Counterclaiming Defendant Can Make A Valid "claimant's" Part 36 Offer
    • United Kingdom
    • Mondaq UK
    • 3 February 2022
    ...a court must consider the substance of the Part 36 offer. This follows the decision of the Court of Appeal in the case of AF v BG [2009] EWCA Civ 75 (considered here), where it was held that a defendant could be treated as a claimant in respect of its counterclaim even in circumstances wher......
  • A Counterclaiming Defendant Can Make A Valid "claimant's" Part 36 Offer
    • United Kingdom
    • Mondaq UK
    • 3 February 2022
    ...a court must consider the substance of the Part 36 offer. This follows the decision of the Court of Appeal in the case of AF v BG [2009] EWCA Civ 75 (considered here), where it was held that a defendant could be treated as a claimant in respect of its counterclaim even in circumstances wher......
  • Case Law Review - Construction, Property & Real Estate (May/June 2009)
    • United Kingdom
    • Mondaq United Kingdom
    • 16 July 2009
    ...that frustration will rarely be available. Termination And Repudiation Stocznia Gdynia SA v Gearbulk Holdings Ltd [2009] BLR 196 and [2009] CILL 2708 The (ship-building) case concerned interpretation of the termination clauses and whether it prevented the client, who had terminated the cont......
  • Request a trial to view additional results
4 books & journal articles
  • Back on Course - Excluding the Right to Limit Liability Under the 1976 Convention: Bahamas Oil Refining Company International Ltd v The Owners of the Cape Bari Tankschiffahrts GMBH & Co KG ('The Cape Bari') [2016] UKPC 20
    • Australia
    • Australian and New Zealand Maritime Law Journal No. 30-2, October 2016
    • 1 October 2016
    ...Casualty & General Insurance Ltd v Chase Manhattan Bank [2003] 2 Lloyd’s Rep 61, 67 [11]; Stocznia Gdynia v Gearbulk Holdings Ltd [2009] 1 Lloyd’s Rep 461, 468 [23] ( ‘Stocznia Gdynia’) ; Seadrill Management Services Ltd v OAO Gazprom [2010] 1 CLC 934, [29]; Ingram & Royle Ltd v Services Ma......
  • No (,) More Bolam Please: Montgomery v Lanarkshire Health Board
    • United Kingdom
    • The Modern Law Review No. 79-3, May 2016
    • 1 May 2016
    ...vAustralia and New Zealand Banking Group Ltd [2006] EWCA Civ 386;[2006] 2 Lloyd’s Rep 511.29 Stocznia Gdynia SA vGearbulk Holdings Ltd [2009] EWCA Civ 75; [2010] QB 27 at [23].30 In some ways this is the obverse inquiry to that posed in S. Rowan, ‘For the Recognitionof Remedial Ter ms Agree......
  • Injunctive Relief: But Let's Agree Not To Have It?
    • United Kingdom
    • The Modern Law Review No. 79-3, May 2016
    • 1 May 2016
    ...vAustralia and New Zealand Banking Group Ltd [2006] EWCA Civ 386;[2006] 2 Lloyd’s Rep 511.29 Stocznia Gdynia SA vGearbulk Holdings Ltd [2009] EWCA Civ 75; [2010] QB 27 at [23].30 In some ways this is the obverse inquiry to that posed in S. Rowan, ‘For the Recognitionof Remedial Ter ms Agree......
  • Attribution and the Illegality Defence
    • United Kingdom
    • The Modern Law Review No. 79-3, May 2016
    • 1 May 2016
    ...vAustralia and New Zealand Banking Group Ltd [2006] EWCA Civ 386;[2006] 2 Lloyd’s Rep 511.29 Stocznia Gdynia SA vGearbulk Holdings Ltd [2009] EWCA Civ 75; [2010] QB 27 at [23].30 In some ways this is the obverse inquiry to that posed in S. Rowan, ‘For the Recognitionof Remedial Ter ms Agree......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT